Jaypee Greens Boomerang Residences, Noida

UPRERANCLT

Jaypee Greens Boomerang Residences, Noida is a RERA-registered residential project by Adani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited) in Gautam Budh Nagar (RERA ID UPRERAPRJ3872). RERA status: NCLT (since 3 Jun 2024).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: NCLT.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Oct–Dec 2021
Quarters shown are calendar quarters. UP-RERA files them by financial year.
12%Q2'20
12%Q3'20
12%Q4'20
12%Q1'21
12%Q2'21
12%Q3'21
12%Q4'21

Construction stayed at 12% across 7 consecutive filed quarters (Apr–Jun 2020 to Oct–Dec 2021). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ3872
Project categoryResidential
Registration typeOngoing
RERA statusNCLTNCLTThe tribunal that hears company insolvency cases. UP-RERA lists projects whose promoter is before it.Read the full entry in the glossary
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start29 Mar 2012
Original start29 Mar 2012
Project duration118 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressSector - 128, Noida - 201304, Uttar Pradesh (India)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    Submitted vide lettter No. JIL/GHP/NOIDA/74

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. Permit revalidated

    Noida/cap/2023/III-285/1234

  8. Building permit sanctioned

    Noida/cap/2023/III-285/1234

  9. NCLT order

Published without a date
UPRERA lists this project as NCLT. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Jul 2017
Original completion30 Jun 2021
Revised completion29 Dec 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹63,000
Sanctioning authorityNoida Authority
NCLT order date3 Jun 2024

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors124 · 2 · 36 (units from plan)
ConfigurationUnitsCarpet area
4 BHK124141-601
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower A · OTHER, 4 BHK3662141-601
Tower B · OTHER, 4 BHK3662348-601
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
M/s La Archplan
License Mr. Sanjay Kataria CA/93/15554
D-2, Swami Nagar (South), New Delhi-110017
Engineer
"BMSF DESIGN CONSULTANTS"
"13-A, Bhawani Kunj, Behind D2, Vasant Kunj, New Delhi-110070"
Contractor
Jaiprakash Associates Limited
Site Office, Sector -128, Noida 201 304
Sr.Development work declared to RERA
1Demarcation of Plots
"As per location of Plot : NE - Approach Road / Group Housing SE - Golf Club SW - Golf Course NW - Golf Course The Plot has been demarcated"
2Boundary Wall
"This Project is part of Wish Town Township. The Over all Boundary Wall of Town Township has been Constructed except few Passages. Due to cluster planning Boundary Wall for this Project has been planned and shall be Constructed on three sides (front, rear & one side) as this project is internally connected by other Group housing."
3Road Work
"The Approach Road to the project is Completed. The Internal Roads Connecting the Towers have been Planned as per Submission Drawings and the same shall be Constructed before completion of Project."
4Footpaths
The Pedestrian Foot Paths with Kerb Stone as per Landscape Plan have been Planned and the same will be Constructed before completion of Project.
5Water Supply Including Drinking Water Facilities
"The Pipe Lines for Water Supply has been laid and Completed at Township Level. The Drinking Water is being Supplied through Water Centres after necessary treatments. The Tapping Points for Towers are available and the same shall be Connected as and when reqired for Completion of Works."
6Sewer System
"The Pipe Lines for Sewer System have been laid and Completed at Township Level. The Sewage will be treated at Sewerage Treatment Plant. The Tapping Points for these Towers are available and the same shall be Connected as and when reqired before Completion of Works. "
7Drain
"The Drainage System has been laid and Completed at Township Level. The Drainage Water is being Collected in Lakes of Golf Courses. The Tapping Points for these Towers are available and the same shall be Connected as and when reqired before Completion of Works."
8Parks
"Parks / Play Fields are Planned at Township Level and are not applicable at tower levels. "
9Tree Planting
"Tree Planting as per Approved Landscape Plan at Township Level is Complete. The Tree Planting at Tower Levels will be done as and when reqired before Completion of Project."
10Design For Electric Supply Including Street Lighting
"The Electric Supply from Grid Sub Station as Planned for Wish Town is complete. Tapping Points for this Project is available and the same shall be Connected as and when reqired before Completion of Works."
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
"The Sewage will be treated at Sewerage Treatment Plant. The Sullage will be Converted into Compost. The Sullage Water after necessary treatment will be Supplied for Flushing, Irrigation and Landscaping. "
13Solid Waste Management And Disposal System
"The Solid Waste collected from door to door apartments will be Transferred to Segrigation Centres planned / constructed at Sewerage Treatment Plant at Township level. The Segregated waste is being transported through facility management maintenance company to the identified sites of Noida Authority for necessary disposal."
14Water Conservation System
Treated Water from Sewerage Treatment Plant is being used for irrigation and flushing.
15Energy Management System Including Use of Renewable Energy
As per Approved Environment Impact Assessment Authority Advice
16Fire Protection And Fire Safety System
The Fire Station with all the infrastructure facilities and staff has been provided at Township level. Towers and basements are being provided with all the provisions of Fire Protection & Safety System as laid down in respective fire approval from the fire department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
At township level, 500 hundred Bed Super Speciality Hospital, Jaypee Institute of Information & Technology, Jaypee Public School, Temples, Convenient Shopping facilities, Club facilities etc. have already been provided
18Emergency Evacuation Services
Fire Escape Staircases are provided in Tower and Basements as per Norms laid down in respective fire approval of the fire Department.
19Other Miscellaneous Work
At Township Level Sewerage Treatment Plant & Service Centres, Electric Sub station with DG Power Backup, Fire Station, Parks & Playgrounds have been provided.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 30 Apr 2028. 1 of them carries a revalidation.

Sanctioned by Noida Authority · 11,508 sqm of land · an approved plan of 2 blocks and 124 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Submitted vide lettter No. JIL/GHP/NOIDA/749 Apr 20128 Apr 20178 Apr 202229 Dec 2021—
Noida/cap/2023/III-285/12341 May 202330 Apr 202830 Apr 203329 Dec 20211 May 2023
Plans and approvals filed with RERA
DocumentFile
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 29 Dec 2021.

#Granted fromExtended uptoNote
130 Jun 202129 Dec 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-811508Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 12 Jan 2006.

Registry no.DateTypeArea
A4624912 Jan 2006other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · A46429
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 1656/1657
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 1656/1657
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · A46249
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New7 Jun 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New8 Jun 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 May 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New31 May 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New31 May 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old28 Jul 2017 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old28 Jul 2017 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old17 Apr 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old17 Apr 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old17 Apr 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old17 Apr 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
Old17 Apr 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old17 Apr 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAvailable
Fire safety (as filed with RERA)BH-12/CFO/GBN-09/09 June 12, 2009
Other facilitiesas per approved Layout Plan of Wishtown Noida

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.

QuarterConstructionCertificates
2020-Q112%CA ↗ · Arch ↗ · Eng ↗
2020-Q212%CA ↗ · Arch ↗ · Eng ↗
2020-Q312%CA ↗ · Arch ↗ · Eng ↗
2020-Q412%CA ↗ · Arch ↗ · Eng ↗
2021-Q112%CA ↗ · Arch ↗ · Eng ↗
2021-Q212%CA ↗ · Arch ↗ · Eng ↗
2021-Q312%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2021-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAdani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited)
RolePromoter · current
RERA IDUPRERAPRM6273
PANAABCB1562A
CIN / TANL14106UP1995PLC019017
Name of chairmanSh. Manoj Gaur
Registered addressSector - 128, Noida - 201304, Uttar Pradesh (India)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Jaiprakash Associates Limited-BMRBankICICI BankBranchExpress Trade Tower 2A/C no.IFSCICIC0001579
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)1347 (Under Registration - 1 ) → 1347 (Under Registration - 0 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 16 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Jaypee Greens Boomerang Residences, Noida

Is Jaypee Greens Boomerang Residences, Noida RERA registered?

Yes. Jaypee Greens Boomerang Residences, Noida is registered with UPRERA under registration number UPRERAPRJ3872, registered on 28 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Jaypee Greens Boomerang Residences, Noida?

The completion date filed with UPRERA is 29 Dec 2021. No completion certificate is on record yet.

Who is the builder of Jaypee Greens Boomerang Residences, Noida?

Adani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited) is the promoter entity that filed Jaypee Greens Boomerang Residences, Noida with UPRERA (promoter RERA ID UPRERAPRM6273). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Jaypee Greens Boomerang Residences, Noida more time to complete?

UPRERA's record carries 1 completion extension for Jaypee Greens Boomerang Residences, Noida, the latest running to 29 Dec 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Jaypee Greens Boomerang Residences, Noida have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Jaypee Greens Boomerang Residences, Noida located?

Jaypee Greens Boomerang Residences, Noida is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Jaypee Greens Boomerang Residences, Noida?

The unit plan filed with UPRERA lists OTHER and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Jaypee Greens Boomerang Residences, Noida?

The approved unit plan filed with UPRERA runs from 141 to 601 m² of carpet area (about 1,513 to 6,466 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Jaypee Greens Boomerang Residences, Noida?

The approved unit plan describes 2 blocks and 124 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Jaypee Greens Boomerang Residences, Noida?

About 44 units per acre: 124 planned units across 2.84 acres (11,508 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗