Jaypee Greens Kosmos - A (Phase II), Noida

UPRERARegistered

Jaypee Greens Kosmos - A (Phase II), Noida is a RERA-registered residential project by Jaypee Infratech Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ3853). Registered with a completion deadline of 29 Sept 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
95%Q3'25
98%Q4'25
98%Q1'26
96%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ3853
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start8 Apr 2009
Original start8 Apr 2009
Project duration210 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressSector - 128, Noida - 201304, Uttar Pradesh (India)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    Noida/Sr.T.P./III-254/472

  3. valid to

    Permit revalidated

    Noida/Sr.T.P./III-254/472

  4. Building permit sanctioned

    Noida/Sr.T.P./III-254/472

  5. Registered with RERA

  6. to

    Extension granted

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. 6 completion certificates filed

  9. Completion certificate filed

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Jul 2017
Original completion31 Mar 2019
Revised completion29 Sept 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary13 Mar 2024
Registration fee₹3,73,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors2,143 · 19 · 21 (units from plan)
  • 2 BHK1,210 56%
  • 3 BHK768 36%
  • 4 BHK160 7%
  • 1 BHK5 <1%
ConfigurationUnitsCarpet area
2 BHK1,21058-58
3 BHK76879-107
4 BHK160130
1 BHK530
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
KM004 · 2 BHK, OTHER1813458-58
KM005 · 3 BHK, OTHER1810379-85
KM010 · 3 BHK, OTHER1810179-85
KM019 · 3 BHK, OTHER1810179-85
KM020 · 3 BHK, OTHER1810179-85
KM021 · 3 BHK, OTHER1810179-85
KM022 · 3 BHK, OTHER1810179-85
KM023 · 4 BHK, OTHER2180130
KM024 · 3 BHK, OTHER2180107
KM025 · 3 BHK, OTHER2180107
KM026 · 4 BHK, OTHER2180130
KM035 · 2 BHK, OTHER1813858-58
KM036 · 2 BHK, OTHER1813458-58
KM037 · 2 BHK, OTHER1813458-58
KM043 · 1 BHK, 2 BHK, OTHER1813530-58
KM044 · 2 BHK, 1 BHK, OTHER1813530-58
KM045 · 2 BHK, 1 BHK, OTHER1813530-58
KM046 · 2 BHK, 1 BHK, OTHER1813530-58
KM047 · 2 BHK, 1 BHK, OTHER1813530-58
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
M/s ARCOP ASSOCIATES PVT. LTD
License Mr Nitin Gupta (CA/93/15869)
A-15, Pamposh Enclave, G.K-1, Outer Ring Road, New Delhi-110048
Engineer
Appointed by Jaiprakash Associates Limited
Jaypee Greens, Sector 128, Noida
Contractor
M/s JAIPRAKASH ASSOCIATES LIMITED
Jaypee Greens, Sector 128, Noida
Sr.Development work declared to RERA
1Demarcation of Plots
As per Location Plan
2Boundary Wall
Boundary wall Constructed / partly constructed at overall Township Level (Jaypee Greens Wishtown, Noida)
3Road Work
As per Location Plan
4Footpaths
As per Location Plan
5Water Supply Including Drinking Water Facilities
As per Development Plan
6Sewer System
As per Development Plan
7Drain
As per Development Plan
8Parks
As per Development Plan
9Tree Planting
As per Noida Authority Norms
10Design For Electric Supply Including Street Lighting
As per Noida Authority Norms
11Community Buildings
As per Sanctioned Layout Plan
12Treatment and Disposal System of Sewage and Sullage water
As per Sanctioned Layout Plan
13Solid Waste Management And Disposal System
To be provided at township level (Jaypee Greens Wish Town) after occupation of Buildings, as per Noida Authority Norms
14Water Conservation System
Rain Water Harvesting, STP effluent to be used for irrigation and flushing
15Energy Management System Including Use of Renewable Energy
As per Environment Impect Assessment Authority Advice
16Fire Protection And Fire Safety System
As per Fire Department Norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per Sanctioned Layout Plan
18Emergency Evacuation Services
As per Fire Department Norms
19Other Miscellaneous Work
As per Sanctioned Layout Plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 7 Oct 2021. 1 of them carries a revalidation, valid to 29 Sept 2026.

Sanctioned by Noida Authority · 73,579 sqm of land · an approved plan of 19 blocks and 2143 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Noida/Sr.T.P./III-254/4721 Nov 20117 Oct 2021—31 Mar 2019—
Noida/Sr.T.P./III-254/47231 Oct 201630 Sept 202129 Sept 202631 Mar 201931 Oct 2016
valid to 29 Sept 2026
Plans and approvals filed with RERA
DocumentFile
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 29 Sept 2026.

#Granted fromExtended uptoNote
131 Mar 201929 Sept 2026—

Land & documents

13 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-35,36,37,3873579Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

3 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 16 Feb 2008.

Registry no.DateTypeArea
196516 Feb 2008self—
819730 Jun 2009self—
18188 Feb 2010self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 1965
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 8197
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 1818
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New2 Jun 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New2 Jun 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New2 Jun 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old28 Jul 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old28 Jul 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old28 Jul 2017 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old16 Apr 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old16 Apr 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old16 Apr 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old17 Apr 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
Old17 Apr 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old17 Apr 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAvailable
Fire safety (as filed with RERA)BH-109/CFO/GBN-10(1)\25 Jan.05,2011
Other facilitiesas per approved Layout Plan of Wishtown Noida

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q295%CA ↗ · Arch ↗ · Eng ↗
2025-Q398%CA ↗ · Arch ↗ · Eng ↗
2025-Q498%CA ↗ · Arch ↗ · Eng ↗
2026-Q196%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameJaypee Infratech Limited
RolePromoter · current
RERA IDUPRERAPRM6253
PANAABCJ9042R
CIN / TANL45203UP2007PLC033119
Name of chairmanSh. Manoj Gaur
Registered addressSector - 128, Noida - 201304, Uttar Pradesh (India)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
JIL REAL ESTATE COLLECTIONKOSMOS A A/CBankIDBI BankBranchIDBI Bank JhandewalanA/C no.IFSCIBKL0000127
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

7 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)297 (Under Registration - 9 ) → 298 (Under Registration - 10 )
changed in Estanzo’s record
19 Oct 2026
Promoter’s complaints tally (all their projects)296 (Under Registration - 8 ) → 297 (Under Registration - 9 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)296 (Under Registration - 9 ) → 296 (Under Registration - 8 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)295 (Under Registration - 8 ) → 296 (Under Registration - 9 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)295 (Under Registration - 9 ) → 295 (Under Registration - 8 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)295 (Under Registration - 10 ) → 295 (Under Registration - 9 )
changed in Estanzo’s record
5 Sept 2026
Promoter’s complaints tally (all their projects)294 (Under Registration - 11 ) → 295 (Under Registration - 10 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 19 Oct 2026 · 7 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Jaypee Greens Kosmos - A (Phase II), Noida

Is Jaypee Greens Kosmos - A (Phase II), Noida RERA registered?

Yes. Jaypee Greens Kosmos - A (Phase II), Noida is registered with UPRERA under registration number UPRERAPRJ3853, registered on 28 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has Jaypee Greens Kosmos - A (Phase II), Noida been completed?

UPRERA still lists Jaypee Greens Kosmos - A (Phase II), Noida as Registered, so it is not shown as completed here. A completion certificate dated 13 Mar 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Jaypee Greens Kosmos - A (Phase II), Noida?

Jaypee Infratech Limited is the promoter entity that filed Jaypee Greens Kosmos - A (Phase II), Noida with UPRERA (promoter RERA ID UPRERAPRM6253). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Jaypee Greens Kosmos - A (Phase II), Noida more time to complete?

UPRERA's record carries 1 completion extension for Jaypee Greens Kosmos - A (Phase II), Noida, the latest running to 29 Sept 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Jaypee Greens Kosmos - A (Phase II), Noida have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Jaypee Greens Kosmos - A (Phase II), Noida located?

Jaypee Greens Kosmos - A (Phase II), Noida is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Jaypee Greens Kosmos - A (Phase II), Noida?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, 4 BHK, 1 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Jaypee Greens Kosmos - A (Phase II), Noida?

The approved unit plan filed with UPRERA runs from 30 to 130 m² of carpet area (about 322 to 1,404 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Jaypee Greens Kosmos - A (Phase II), Noida?

The approved unit plan describes 19 blocks and 2,143 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Jaypee Greens Kosmos - A (Phase II), Noida?

About 118 units per acre: 2,143 planned units across 18.18 acres (73,579 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗