Estanzo

Timeline Bar

Promised28 Feb 2012
Registered29 Jul 2017
Today4 Aug 2026

Timeline

Promised completion28 Feb 2012
Revised completion28 Feb 2012
Actual completion
Possession delay173 mo delay

Registration & Cost Details

Registration fee (in ₹)₹3,66,000
Project cost (in ₹ Lakhs)₹0 Lakhs
Project duration17 months
Project categoryResidential
Locality
Original start date22 Oct 2010
Proposed start date22 Oct 2010

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9650169966
Emailrera.jal@jalindia.co.in
Coordinator9650222583
AddressSector - 128, Noida - 201304, Uttar Pradesh (India)

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
SDZ-01/855/201421 Feb 201420 Feb 201928 Feb 2012

Land Parcels

Khasra No.AreaPlot Type
GH-K,L,M,N72184Plot

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1162025 Sept 2009
1162225 Sept 2009
1842521 Jul 2010
1842021 Jul 2010

Frequently Asked Questions

What is the RERA registration number of Jaypee Greens Krowns, SDZ, YEW?

The RERA registration number of Jaypee Greens Krowns, SDZ, YEW is UPRERAPRJ5445, as recorded on the UP-RERA portal.

What is the RERA status of Jaypee Greens Krowns, SDZ, YEW?

As reported by UP-RERA, the status of Jaypee Greens Krowns, SDZ, YEW is "Registered".

Where is Jaypee Greens Krowns, SDZ, YEW located?

As reported to UP-RERA, Jaypee Greens Krowns, SDZ, YEW is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Jaypee Greens Krowns, SDZ, YEW be completed?

The latest completion date reported to UP-RERA for Jaypee Greens Krowns, SDZ, YEW is 28 Feb 2012.

Is Jaypee Greens Krowns, SDZ, YEW delayed?

Measured against the latest completion date reported to UP-RERA, Jaypee Greens Krowns, SDZ, YEW is 173 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026