Jaypee Greens Villa Country Homes - II, SDZ, YEW

UPRERANCLT

Jaypee Greens Villa Country Homes - II, SDZ, YEW is a RERA-registered residential project by Adani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited) in Gautam Budh Nagar (RERA ID UPRERAPRJ5415). RERA status: NCLT (since 3 Jun 2024).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: NCLT.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ5415
Project categoryResidential
Registration typeOngoing
RERA statusNCLTNCLTThe tribunal that hears company insolvency cases. UP-RERA lists projects whose promoter is before it.Read the full entry in the glossary
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryYamuna Expressway Authority
Proposed start5 Oct 2013
Original start5 Oct 2013
Project duration84 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressSector - 128, Noida - 201304, Uttar Pradesh (India)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    SDZ-01/855/2014

  3. Registered with RERA

  4. valid to

    Permit revalidated

    SDZ-01/62542/2018

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  8. NCLT order

Published without a date
UPRERA lists this project as NCLT. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 Jul 2017
Original completion31 Mar 2020
Revised completion30 Sept 2020
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹22,000
Sanctioning authorityYamuna Expressway Authority
NCLT order date3 Jun 2024

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
D&D Department, Jaiprakash Associates Ltd.
License "Ms. Raina Dora CA No. 81/6645"
Jaypee Greens, Sector 128, Noida
Engineer
Structural Department, Jaiprakash Associates Ltd.
"Jaypee Greens, Sector 128, Noida"
Contractor
Jaiprakash Associates Limited
Site Office, Sector -128, Noida 201 304
Sr.Development work declared to RERA
1Demarcation of Plots
"As per location of Plot : NE - 12 M Wide Master Plan Road SE - 30 M Wide Master Plan Road SW - Green NW -12 M Wide Master Plan Road The Plot has been demarcated"
2Boundary Wall
"This Project is part of the Sports City Township. The overall boundary wall / fencing of the Township has been constructed except few Passages. Fencing at the cluster level has been provided."
3Road Work
"The 30 M wide approach road to the project is completed. The internal roads of the cluster as planned are constructed."
4Footpaths
The pedestrian footpaths with Kerb Stone has been planned in the cluster and the same shall be constructed as and when required before the project completion.
5Water Supply Including Drinking Water Facilities
The pipe lines for water supply have been partially laid at Township Level. The drinking water to the project is available and shall be supplied through water centre after necessary treatments, as and when required. The internal water supply lines have been laid out and tapping points at the cluster level shall be connected as and when required.
6Sewer System
The pipe lines for Sewer System have been planned at Township Level. The internal sewerage system at cluster level has been constructed . The tapping points at the cluster level shall be connected as and when required. The facility for treating sewage is available at the Sewage Treatment Plant , presently operational in the township .
7Drain
"The drainage system has been laid out at Township Level . The internal sewerage system at the cluster level has been constructed. The drainage water is being collected in seasonal ponds and lakes of Boulevard. The planned tapping points at the cluster level shall be connected as and when required. "
8Parks
Parks / Play fields are planned at Township Level.
9Tree Planting
Tree planting as per approved landscape plan at township level is complete.
10Design For Electric Supply Including Street Lighting
"The electric supply from Grid Sub Station as planned for the Township is complete. The tapping points for the project are available and the same shall be connected as and when required. "
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
The sewage will be treated at Sewage Treatment Plant. The sullage will be converted into compost. The sullage water after necessary treatment will be supplied for flushing, irrigation and landscaping.
13Solid Waste Management And Disposal System
The solid waste to be collected from door to door at the cluster level after occupancy of residents will be transferred to segregation centres planned at Sewege Treatment Plant at Township level. The segregated waste shall be transported through facility management maintenance company to the identified sites of YEIDA Authority for necessary disposal. Solid waste management agency shall be deployed for collection of any solid waste generated during construction stage.
14Water Conservation System
Treated water from Sewage Treatment Plant shall be used for irrigation and road washing, flushing etc.
15Energy Management System Including Use of Renewable Energy
As per approved environment impact assessment authority advice
16Fire Protection And Fire Safety System
The Fire Station with all the infrastructure facilities and staff is planned at Township level. Fire tender is available at Township level.
17Social Infrastructure And Other Public Amenities Including Public Health Services
At township level, Higher Secondary School (Sardar Patel Vidyalaya), Temples, Cafeteria, Police Outpost, Dispensery facilities etc. have already been provided. World class Formula -1 racing Track is operational within the Township and round the year races , corporate events etc are being hosted and held in Buddh International Circuit. International standard Cricket Stadium with Outfield, spectator stands already made ready and corporate league and other cricket matches are being held at the Cricket Ground.
18Emergency Evacuation Services
Fire tenders, Ambulances, patrolling vehicles are available at Township level.
19Other Miscellaneous Work
At Township Level Sewage Treatment Plant & Service Centres, Electric Grid Sub station with DG Power Backup, Fire tenders and mobile fire saftey equipments, Ambulances ,patrolling vehicles, Boulevard & Parks and Seasonal ponds have been provided.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 20 Feb 2019. It carries a revalidation, valid to 10 Jul 2023.

Sanctioned by Yamuna Expressway Authority · 3,342 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
SDZ-01/855/201421 Feb 201420 Feb 201910 Jul 202830 Sept 202011 Jul 2018
valid to 10 Jul 2023
as SDZ-01/62542/2018
Plans and approvals filed with RERA
DocumentFile
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Sept 2020.

#Granted fromExtended uptoNote
131 Mar 202030 Sept 2020Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-O3342Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 25 Sept 2009.

Registry no.DateTypeArea
1162825 Sept 2009self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 11628
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New6 Jun 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Jun 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Jun 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Jun 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New7 Jun 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New6 Jun 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Jun 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New6 Jun 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New6 Jun 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Jun 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old9 Apr 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old9 Apr 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old9 Apr 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old19 Apr 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAvailable
Fire safety (as filed with RERA)57/JD/LUCKNOW-13/GN/440 31/12/2014
Other facilitiesas per approved Layout Plan of SDZ

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAdani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited)
RolePromoter · current
RERA IDUPRERAPRM6273
PANAABCB1562A
CIN / TANL14106UP1995PLC019017
Name of chairmanSh. Manoj Gaur
Registered addressSector - 128, Noida - 201304, Uttar Pradesh (India)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
JAIPRAKASH ASSOCIATES LTD. - VECHBankICICI BankBranchExpress Trade Tower2A/C no.IFSCICIC0001579
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)1347 (Under Registration - 1 ) → 1347 (Under Registration - 0 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 16 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.

Common questions about Jaypee Greens Villa Country Homes - II, SDZ, YEW

Is Jaypee Greens Villa Country Homes - II, SDZ, YEW RERA registered?

Yes. Jaypee Greens Villa Country Homes - II, SDZ, YEW is registered with UPRERA under registration number UPRERAPRJ5415, registered on 29 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Jaypee Greens Villa Country Homes - II, SDZ, YEW?

The completion date filed with UPRERA is 30 Sept 2020. No completion certificate is on record yet.

Who is the builder of Jaypee Greens Villa Country Homes - II, SDZ, YEW?

Adani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited) is the promoter entity that filed Jaypee Greens Villa Country Homes - II, SDZ, YEW with UPRERA (promoter RERA ID UPRERAPRM6273). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Jaypee Greens Villa Country Homes - II, SDZ, YEW more time to complete?

UPRERA's record carries 1 completion extension for Jaypee Greens Villa Country Homes - II, SDZ, YEW, the latest running to 30 Sept 2020. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Jaypee Greens Villa Country Homes - II, SDZ, YEW have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Jaypee Greens Villa Country Homes - II, SDZ, YEW located?

Jaypee Greens Villa Country Homes - II, SDZ, YEW is registered in Gautam Budh Nagar, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗