Timeline Bar

Registered2 Jul 2019
Promised20 May 2024
Revised18 Nov 2024
Today4 Aug 2026

Timeline

Promised completion20 May 2024
Revised completion18 Nov 2024
Actual completion
Possession delay21 mo delay

Registration & Cost Details

Registration fee (in ₹)₹34,000
Project cost (in ₹ Lakhs)₹3,050 Lakhs
Project duration66 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jun 2019

Inventory

Total units131
Unit TypeUnitsCarpet Area (sqm)
2 BHK3076.39
3 BHK10186.05–98.66

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8400002160
Emailinfo@jeethomesolutions.com
Coordinator8400415554
Addressmata vaishno colony. vill- Domari , ramnagar, Varanasi , U.P.

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
29/17 G. H./ VINYAS21 May 201920 May 202419 May 202420 May 2027
29/17 G. H./ VINYAS

Revalidated: 29/17 G. H./ VINYAS (21 May 2019)

21 May 201920 May 2024

Revalidated upto: 20 May 2027

18 Nov 202419 Dec 2029

Land Parcels

Khasra No.AreaPlot Type
003181580Khasra
005021400Khasra
003452820Khasra

Approved Unit Plan

Unit plan rows on file61
Total flats (sum of rows)131
BlocksT-4 / AVYAKTA
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of JEET RIVERA - AVYAKTA (T-4)?

The RERA registration number of JEET RIVERA - AVYAKTA (T-4) is UPRERAPRJ499586, as recorded on the UP-RERA portal.

What is the RERA status of JEET RIVERA - AVYAKTA (T-4)?

As reported by UP-RERA, the status of JEET RIVERA - AVYAKTA (T-4) is "Registered".

Where is JEET RIVERA - AVYAKTA (T-4) located?

As reported to UP-RERA, JEET RIVERA - AVYAKTA (T-4) is located at Chandauli, Chandauli, Uttar Pradesh.

When will JEET RIVERA - AVYAKTA (T-4) be completed?

The latest completion date reported to UP-RERA for JEET RIVERA - AVYAKTA (T-4) is 18 Nov 2024.

Is JEET RIVERA - AVYAKTA (T-4) delayed?

Measured against the latest completion date reported to UP-RERA, JEET RIVERA - AVYAKTA (T-4) is 21 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026