Jyoti Greens Phase 2

UPRERARegistered

Jyoti Greens Phase 2 is a RERA-registered residential project by NAVSHEEL STANDARD CONSTRUCTIONS in Taudhakpur, Kanpur Nagar (RERA ID UPRERAPRJ124107). Registered with a completion deadline of 21 May 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0.33%Q3'24
0.33%Q4'24
0.33%Q1'25
0.33%Q2'25
0.33%Q3'25
0.33%Q4'25
0.33%Q1'26
0.33%Q2'26

Construction stayed at 0.33% across 9 consecutive filed quarters (Apr–Jun 2024 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ124107
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryKanpur Development Authority
Proposed start22 May 2024
Project duration60 months
AddressArazi No.115(Part), 112(Part), 114(Part), 109(Part), 110(Part), 113(Part), 128(Part), 111(Part)., Taudhakpur, Kanpur, Kanpur Nagar
TehsilKanpur
Applicant typePartnership Firm
Applicant address35 Cantt. Kanpur UP 208001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Plotted Resi development / Plotted Housing/03811/KDA/LD/22-23/0904/09122022

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 Jul 2025
Original completion21 May 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,25,500
Sanctioning authorityKanpur Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Prasoon Jalota
License CA/2006/39219
24/18-b, Karachi Khana, Kanpur
Engineer
Omkar Verma
8/14 Indira Nagar Lucknow 226016
Contractor
Brij Lal S/o Pyare lal
Araji no. 1612, kasyap nagar, kalyanpur, kanpur nagar UP 208017
Sr.Development work declared to RERA
1Demarcation of Plots
We have total 135 plots of Different sizes varrying from 90.00 Sqmtr. to 128.99 Sqmtr. The plots shall be demarcated by fixing pillars or flags.
2Boundary Wall
2 m high and 115mm thick Brick work and rcc work in column and beam. on the open sides of the site plan but no boundry wall behind plots.
3Road Work
From the main entrance gate CC road is under construction on the base of compact soil, GSB aggregrate and PCC. road through out the project. Whose width starts from 7.5mtr.
4Footpaths
We would not provide any footpath
5Water Supply Including Drinking Water Facilities
We will provide 01 nos. of pump with OWT through underground pipelines.
6Sewer System
Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force.
7Drain
Storm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
We will provide open green area with the different activities and the green area will have seasonal flowers and common ametenies. It will also have benches and seating.
9Tree Planting
Adequte trees shall be planted for asthetics and utility Value in the green area
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and common service like External lighting, Fountain, STP, Pump room etc. Adequte street lights shall be installed.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
We will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 21 May 2029.

Sanctioned by Kanpur Development Authority · 24,036 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Plotted Resi development / Plotted Housing/03811/KDA/LD/22-23/0904/0912202222 May 202421 May 202921 May 203221 May 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Part of Arazi no. 109, 110, 111, 112, 113, 114, 115, 12837400.86Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 13793
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 13303
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 14113
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 8420
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 12881
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 15807
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5602
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2616
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6796
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 11987
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1422-1427
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 155
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Land Details
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 2293
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Reply to Objection Letter
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New17 Jan 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New17 Jan 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New17 Jan 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New17 Jan 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New19 Jun 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New19 Jun 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New19 Jun 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New17 Jan 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Jan 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New17 Jan 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New17 Jan 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New17 Jan 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New17 Jan 2025 ↗

Quarterly progress reports

9 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

9 quarterly progress reports are on file with UPRERA, covering 2024-Q1 to 2026-Q1.

QuarterConstructionCertificates
2024-Q10.33%CA ↗ · Arch ↗ · Eng ↗
2024-Q20.33%CA ↗ · Arch ↗ · Eng ↗
2024-Q30.33%CA ↗ · Arch ↗ · Eng ↗
2024-Q40.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q10.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q20.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q30.33%CA ↗ · Arch ↗ · Eng ↗
2025-Q40.33%CA ↗ · Arch ↗ · Eng ↗
2026-Q10.33%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameNAVSHEEL STANDARD CONSTRUCTIONS
RolePromoter · current
RERA IDUPRERAPRM117014
PANAAGFN4028D
CIN / TANKNPN01404E
Registered address35 Cantt. Kanpur UP 208001
RERA contact
Registered since2020
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameNAVSHEEL STANDARD CONSTRUCTIONS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
Address127/219-A Juhi Kalan, Kidwai Nagar Kanpur Kanpur UP 208014
RERA contact
Legal nameRAKESH KUMAR GARG
RoleCo-promoter
Applicant typeIndividual
Address35 Cariappa road Cantonment, Kanpur Nagar, Uttar Pradesh 208004
RERA contact
Legal nameRAJIV KISHORE BHARTIYA
RoleCo-promoter
Applicant typeIndividual
AddressFlat No 602 and 603, Imperial Galaxy Aparment, 7/127, Swarup Nagar, Kanpur, Pincode:- 208002
RERA contact

Nearby projects

Kanpur Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Navsheel Standard Constructions Collection Account For Jyoti Greens Phase 2BankICICI Bank LtdBranchMonika Tower, Halsey Road, KanpurBranch address46/144 , Monika Tower, Halsey Road, Kanpur 208001Branch districtKanpur NagarA/C no.IFSCICIC0006957Branch emailprakash.pandey@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Navsheel Standard Constructions Separate Account For Jyoti Greens Phase 2BankICICI Bank LtdBranchMonika Tower, Halsey Road, KanpurBranch address46/144 , Monika Tower, Halsey Road, Kanpur 208001Branch districtKanpur Nagar, Uttar PradeshA/C no.IFSCICIC0006957
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Navsheel Standard Constructions Transaction Account For Jyoti Greens Phase 2BankICICI Bank LtdBranchMonika Tower, Halsey Road, KanpurBranch address46/144 , Monika Tower, Halsey Road, Kanpur 208001Branch districtKanpur Nagar, Uttar PradeshA/C no.IFSCICIC0006957
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Jyoti Greens Phase 2

Is Jyoti Greens Phase 2 RERA registered?

Yes. Jyoti Greens Phase 2 is registered with UPRERA under registration number UPRERAPRJ124107, registered on 16 Jul 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Jyoti Greens Phase 2?

The completion date filed with UPRERA is 21 May 2029. No completion certificate is on record yet.

Who is the builder of Jyoti Greens Phase 2?

NAVSHEEL STANDARD CONSTRUCTIONS is the promoter entity that filed Jyoti Greens Phase 2 with UPRERA (promoter RERA ID UPRERAPRM117014). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Jyoti Greens Phase 2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Jyoti Greens Phase 2 located?

Jyoti Greens Phase 2 is registered in Taudhakpur, Kanpur Nagar, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗