KABIR NAGAR DEVPUR PARA MULTISTORIED is a RERA-registered residential project by Lucknow Development Authority in Lucknow (RERA ID UPRERAPRJ7120). Registered with a completion deadline of 30 Sept 2020.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ7120 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 1 Mar 2014 |
| Original start | 1 Mar 2014 |
| Project duration | 79 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Competent authority |
| Applicant address | Lucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated (2)
4 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Permit revalidated (2)
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 31 Jul 2017 |
| Original completion | 31 Mar 2019 |
| Revised completion | 30 Sept 2020 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 28 Dec 2024 |
| Registration fee | ₹7,04,000 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK1,520 99%
- SHOP10 1%
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 10 | 23-31 |
| 3 BHK | 1,520 | 63-73 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| MIG- (1) · OTHER, SHOP, 3 BHK | 21 | 153 | 23-63 |
| MIG- (2) · OTHER, SHOP, 3 BHK | 21 | 153 | 23-63 |
| MIG- (3) · OTHER, SHOP, 3 BHK | 21 | 153 | 23-63 |
| MIG- (4) · OTHER, SHOP, 3 BHK | 21 | 153 | 23-63 |
| MIG- (5) · OTHER, SHOP, 3 BHK | 21 | 153 | 23-64 |
| MIG- (6) · SHOP, 3 BHK, OTHER | 21 | 153 | 23-63 |
| SMIG- (1) · OTHER, SHOP, 3 BHK | 21 | 153 | 31-73 |
| SMIG- (2) · OTHER, SHOP, 3 BHK | 21 | 153 | 31-73 |
| SMIG- (3) · OTHER, SHOP, 3 BHK | 21 | 153 | 31-73 |
| SMIG- (4) · OTHER, SHOP, 3 BHK | 21 | 153 | 31-73 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots DONE |
| 2 | Boundary Wall DONE |
| 3 | Road Work IN PROCESS |
| 4 | Footpaths WORK IN PROGRESS |
| 5 | Water Supply Including Drinking Water Facilities WORK IN PROGRESS |
| 6 | Sewer System WORK IN PROGRESS |
| 7 | Drain WORK IN PROGRESS |
| 8 | Parks WORK IN PROGRESS |
| 9 | Tree Planting WORK IN PROGRESS |
| 10 | Design For Electric Supply Including Street Lighting BEING DONE BY LESA |
| 11 | Community Buildings AREA/PLOT RESERVED |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP PROPOSED |
| 13 | Solid Waste Management And Disposal System WORK IN PROGRESS |
| 14 | Water Conservation System WORK IN PROGRESS |
| 15 | Energy Management System Including Use of Renewable Energy UNDER CONSIDERATION |
| 16 | Fire Protection And Fire Safety System AS PER GOVERNMENT NORMS |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services PROPOSED (PLOT RESERVED) |
| 18 | Emergency Evacuation Services YES (STAIRCASE) |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
4 permits
An approval and the date it runs to - not proof the work matching it was done.
4 sanctioning permits are on record with UPRERA, the latest valid to 28 Sept 2018. All 4 carry a revalidation, the latest valid to 28 Sept 2021.
Sanctioned by Lucknow Development Authority · 37,003 sqm of land · an approved plan of 10 blocks and 1530 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 28/09/2013 | 28 Sept 2013 | 28 Sept 2018 | 28 Sept 2021 | 31 Mar 2020 | 28 Sept 2018 valid to 28 Sept 2021 as 28-09-2013 | |
| 28/09/2013 | 28 Sept 2013 | 28 Sept 2018 | 28 Sept 2021 | 31 Mar 2020 | 28 Sept 2018 valid to 28 Sept 2021 as 28-09-2013 | |
| 28/09/2013 | 28 Sept 2013 | 28 Sept 2018 | 28 Sept 2021 | 31 Mar 2020 | 28 Sept 2013 valid to 28 Sept 2021 | |
| LDA/VC/110225 | 28 Sept 2013 | 13 May 2018 | 30 Sept 2020 | 30 Sept 2020 | 28 Sept 2013 valid to 30 Sept 2020 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 30 Sept 2020.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Mar 2019 | 31 Mar 2020 | — |
| 2 | 31 Mar 2020 | 30 Sept 2020 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
18 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 2131 | 25300 | Khasra |
| 2205 | 10120 | Khasra |
| 2746 | 75900 | Khasra |
| 2855 | 20240 | Khasra |
| 2599 | 16450 | Khasra |
| Allotment letter from the authority · 796/KA0TE0/2000 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 2 Jan 2019 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 11 Jan 2019 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 1 Feb 2019 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 1 Feb 2019 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 1 Feb 2019 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 1 Feb 2019 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 31 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 31 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 31 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 31 Jul 2018 ↗ |
Quarterly progress reports
2 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
2 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Lucknow Development Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM10102 |
| PAN | AAALL0016F |
| CIN / TAN | LKNL00280A |
| Registered address | Lucknow Development Authority, Vipin Khand, Gomti Nagar, Lucknow |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Devpur-ParaBankIDBI BankBranchIDBI Bank 565k/183, Sneh Nagar, Alambagh, LucknowA/C no.IFSCIBKL0000276 |
What has changed on this record
8 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 584 (Under Registration - 5 ) → 584 (Under Registration - 4 ) changed in Estanzo’s record | 13 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 583 (Under Registration - 4 ) → 584 (Under Registration - 5 ) changed in Estanzo’s record | 21 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 583 (Under Registration - 5 ) → 583 (Under Registration - 4 ) changed in Estanzo’s record | 19 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 583 (Under Registration - 7 ) → 583 (Under Registration - 5 ) changed in Estanzo’s record | 9 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 582 (Under Registration - 7 ) → 583 (Under Registration - 7 ) changed in Estanzo’s record | 7 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 580 (Under Registration - 5 ) → 582 (Under Registration - 7 ) changed in Estanzo’s record | 31 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 579 (Under Registration - 5 ) → 580 (Under Registration - 5 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 578 (Under Registration - 4 ) → 579 (Under Registration - 5 ) changed in Estanzo’s record | 16 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 13 Oct 2026 · 8 movements on record |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about KABIR NAGAR DEVPUR PARA MULTISTORIED
Is KABIR NAGAR DEVPUR PARA MULTISTORIED RERA registered?
Yes. KABIR NAGAR DEVPUR PARA MULTISTORIED is registered with UPRERA under registration number UPRERAPRJ7120, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has KABIR NAGAR DEVPUR PARA MULTISTORIED been completed?
UPRERA still lists KABIR NAGAR DEVPUR PARA MULTISTORIED as Registered, so it is not shown as completed here. A completion certificate dated 28 Dec 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of KABIR NAGAR DEVPUR PARA MULTISTORIED?
Lucknow Development Authority is the promoter entity that filed KABIR NAGAR DEVPUR PARA MULTISTORIED with UPRERA (promoter RERA ID UPRERAPRM10102). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted KABIR NAGAR DEVPUR PARA MULTISTORIED more time to complete?
UPRERA's record carries 2 completion extensions for KABIR NAGAR DEVPUR PARA MULTISTORIED, the latest running to 30 Sept 2020. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does KABIR NAGAR DEVPUR PARA MULTISTORIED have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is KABIR NAGAR DEVPUR PARA MULTISTORIED located?
KABIR NAGAR DEVPUR PARA MULTISTORIED is registered in Lucknow, as filed with UPRERA.
What configurations are available in KABIR NAGAR DEVPUR PARA MULTISTORIED?
The unit plan filed with UPRERA lists OTHER, SHOP and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in KABIR NAGAR DEVPUR PARA MULTISTORIED?
The approved unit plan filed with UPRERA runs from 23 to 73 m² of carpet area (about 246 to 786 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in KABIR NAGAR DEVPUR PARA MULTISTORIED?
The approved unit plan describes 10 blocks and 1,530 units of which 1,520 are homes and 10 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is KABIR NAGAR DEVPUR PARA MULTISTORIED?
About 167 units per acre: 1,530 planned units across 9.14 acres (37,003 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗