Promised6 Nov 2018
Registered27 Feb 2019
Completed17 Apr 2019

Timeline

Promised completion6 Nov 2018
Revised completion6 Nov 2018
Actual completion17 Apr 2019
Possession delay5 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,32,500
Project cost (in ₹ Lakhs)₹1,000 Lakhs
Project duration13 months
Project categoryResidential
Locality
Original start date
Proposed start date6 Nov 2017

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile9935541056
Emailkahlonsehkariawassamitiltd@gmail.com
Coordinator7755877033
AddressVILLAGE BARAULI KHALILABAD, PARGANA BIJNOUR, P.O. UTTRATIA, LUCKNOW

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
23627 Sept 201827 Apr 20226 Nov 201827 Apr 2022

Land Parcels

Khasra No.AreaPlot Type
440/3130Khasra
63710880Khasra
7401260Khasra
318MI13430Khasra
506/210120Khasra

Frequently Asked Questions

What is the RERA registration number of KAHLON GARDEN CITY II?

The RERA registration number of KAHLON GARDEN CITY II is UPRERAPRJ979582, as recorded on the UP-RERA portal.

What is the RERA status of KAHLON GARDEN CITY II?

As reported by UP-RERA, the status of KAHLON GARDEN CITY II is "Registered".

Where is KAHLON GARDEN CITY II located?

As reported to UP-RERA, KAHLON GARDEN CITY II is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

Is KAHLON GARDEN CITY II completed?

As reported to UP-RERA, KAHLON GARDEN CITY II was completed on 17 Apr 2019.

Is KAHLON GARDEN CITY II delayed?

Measured against the latest completion date reported to UP-RERA, KAHLON GARDEN CITY II is 5 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026