Registered7 Mar 2025
Today3 Aug 2026
Promised31 Dec 2026
Timeline
Promised completion31 Dec 2026
Revised completion31 Dec 2026
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹64,000
Project cost (in ₹ Lakhs)₹650 Lakhs
Project duration30 months
Project categoryResidential
LocalityHariharpur
Original start date—
Proposed start date1 Jul 2024
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9415019390
EmailVachasa@yahoo.com
Coordinator9415019390
Helpline9415019390
Address22, New Berry Road, Near Times of India Hazratganj Lucknow
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| Plotted Resi development/ Plotted Housing/ 11936/ LDA/LD/22-23/2330/03052024 | 29 Jun 2024 | 28 Jun 2029 | 31 Dec 2026 | 28 Jun 2032 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 92, 93, 94 & 105 | 11763.23 | Khasra |
Frequently Asked Questions
What is the RERA registration number of Kanti Niketan?
The RERA registration number of Kanti Niketan is UPRERAPRJ266590, as recorded on the UP-RERA portal.
What is the RERA status of Kanti Niketan?
As reported by UP-RERA, the status of Kanti Niketan is "Registered".
Where is Kanti Niketan located?
As reported to UP-RERA, Kanti Niketan is located at Khasra No. 92, 93, 94 & 105, Village- Hariharpur, Pargana- Bijnaur, District- Lucknow, Hariharpur, Lucknow, Lucknow, Uttar Pradesh.
When will Kanti Niketan be completed?
The latest completion date reported to UP-RERA for Kanti Niketan is 31 Dec 2026.
Is Kanti Niketan delayed?
Measured against the latest completion date reported to UP-RERA, Kanti Niketan is on time.