Registered16 Sept 2019
Promised14 May 2024
Completed15 Jan 2025

Timeline

Promised completion14 May 2024
Revised completion14 May 2024
Actual completion15 Jan 2025
Possession delay8 mo delay

Registration & Cost Details

Registration fee (in ₹)₹51,000
Project cost (in ₹ Lakhs)₹2,703 Lakhs
Project duration66 months
Project categoryCommercial
Locality
Original start date
Proposed start date12 Jun 2019

Inventory

Total units332
Unit TypeUnitsCarpet Area (sqm)
SHOP32211.65–81.63
OTHER10272.15–1961.68

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile7080909174
EmailAISSHPRABUILDERS@GMAIL.COM
Coordinator7408050494
AddressUGF 385,395,396,397,398 BALDEV PLAZA GOLGHAR GORAKHPUR 273001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1100.0%
2020-Q2100.0%
2020-Q3100.0%
2020-Q4100.0%
2021-Q1100.0%
2021-Q2100.0%
2021-Q3100.0%
2021-Q4100.0%
2022-Q1100.0%
2022-Q2100.0%
2022-Q3100.0%
2022-Q4100.0%
2023-Q1100.0%
2023-Q2100.0%
2023-Q3100.0%
2023-Q4100.0%
2024-Q1100.0%
2024-Q2100.0%
2024-Q3100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
09/26-4-19-5/22-5-1915 May 201914 May 202414 May 202414 May 2027

Land Parcels

Khasra No.AreaPlot Type
952/24272.34Khasra

Approved Unit Plan

Unit plan rows on file38
Total flats (sum of rows)332
Total shops322
BlocksLKASHMI MULTIPLEX
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of LAKSHMI MULTIPLEX?

The RERA registration number of LAKSHMI MULTIPLEX is UPRERAPRJ541116, as recorded on the UP-RERA portal.

What is the RERA status of LAKSHMI MULTIPLEX?

As reported by UP-RERA, the status of LAKSHMI MULTIPLEX is "Registered".

Where is LAKSHMI MULTIPLEX located?

As reported to UP-RERA, LAKSHMI MULTIPLEX is located at Basti, Basti, Uttar Pradesh.

Is LAKSHMI MULTIPLEX completed?

As reported to UP-RERA, LAKSHMI MULTIPLEX was completed on 15 Jan 2025.

Is LAKSHMI MULTIPLEX delayed?

Measured against the latest completion date reported to UP-RERA, LAKSHMI MULTIPLEX is 8 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026