Registered14 Aug 2017
Promised31 Dec 2019
Today3 Aug 2026

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹16,500
Project cost (in ₹ Lakhs)₹2,200 Lakhs
Project duration83 months
Project categoryResidential
Locality
Original start date11 Aug 2014
Proposed start date11 Aug 2014

Inventory

Total units54
Unit TypeUnitsCarpet Area (sqm)
3 BHK45113.14–141.84
4 BHK9174.89

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9415202708
Emailbalajiinfracare@gmail.com
Coordinator9415202708
AddressSA 15/146, K, MAVAIYA , ASHAPUR, SARNATH VARANASI 221007 UP IN

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
18011 Aug 201410 Aug 201931 Dec 201910 Aug 2022

Land Parcels

Khasra No.AreaPlot Type
25010503
25114616
38/9G-S135.69Plot
B 38/9-G-R-1185.87Plot
B 38/9-G-R , B 38/9 G-T271.93Plot
B 38/9-12-P-1-T253.07Plot
B 38/9-12-P-R253.07Plot
B 38/9-12-P-R-A252.79Plot
B 38/9-12-P-1-S177.14Plot
B 38/9-12-P675.09Plot
B 38/9-M-5K38.85Plot
B 38/9-M-5 , B 38/9-M-690.99Plot

Approved Unit Plan

Unit plan rows on file54
Total flats (sum of rows)54
BlocksLAV-KUSH
Floor types3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
74716 Oct 2012
74706 Oct 2012
82716 Nov 2012
303830 Apr 2012
303630 Apr 2012
303530 Apr 2012
303930 Apr 2012
303730 Apr 2012
404818 May 2013
404618 May 2013

Frequently Asked Questions

What is the RERA registration number of LAV KUSH APPARTMENT?

The RERA registration number of LAV KUSH APPARTMENT is UPRERAPRJ10155, as recorded on the UP-RERA portal.

What is the RERA status of LAV KUSH APPARTMENT?

As reported by UP-RERA, the status of LAV KUSH APPARTMENT is "Registered".

Where is LAV KUSH APPARTMENT located?

As reported to UP-RERA, LAV KUSH APPARTMENT is located at Varanasi, Varanasi, Uttar Pradesh.

When will LAV KUSH APPARTMENT be completed?

The latest completion date reported to UP-RERA for LAV KUSH APPARTMENT is 31 Dec 2019.

Is LAV KUSH APPARTMENT delayed?

Measured against the latest completion date reported to UP-RERA, LAV KUSH APPARTMENT is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026