Estanzo

Timeline Bar

Registered15 Aug 2017
Promised31 Mar 2020
Completed22 Jun 2024

Timeline

Promised completion31 Mar 2020
Revised completion31 Mar 2020
Actual completion22 Jun 2024
Possession delay51 mo delay

Registration & Cost Details

Registration fee (in ₹)₹63,500
Project cost (in ₹ Lakhs)₹6,700 Lakhs
Project duration89 months
Project categoryResidential
Locality
Original start date1 May 2013
Proposed start date1 May 2013

Inventory

Total units302
Unit TypeUnitsCarpet Area (sqm)
2 BHK18772.67–73.32
3 BHK115103.34–104.46

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8126681548
Emailesco.marutibuilders@yahoo.com
Coordinator9837090640
Address15/252/1, FATEHABAD ROAD TAJGANJ AGRA

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1137/BFT/10/10-117 Dec 20127 Dec 201731 Mar 20206 Dec 2020
1137/BFT/10/10-11

Revalidated: 1137/BFT/10/10-11 (7 Dec 2012)

7 Dec 20126 Dec 2017

Revalidated upto: 1 Jan 1900

31 Mar 20206 Dec 2020

Land Parcels

Khasra No.AreaPlot Type
472, 473, 476, 477, 471/2, 47811659
Khasra no. Part(472,473,476,477)11060.59Khasra

Approved Unit Plan

Unit plan rows on file101
Total flats (sum of rows)302
BlocksASHOKA, GULMOHAR
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
827130 Aug 2011
167515 Feb 2012
172416 Feb 2012

Frequently Asked Questions

What is the RERA registration number of MARUTI FOREST?

The RERA registration number of MARUTI FOREST is UPRERAPRJ10947, as recorded on the UP-RERA portal.

What is the RERA status of MARUTI FOREST?

As reported by UP-RERA, the status of MARUTI FOREST is "Registered".

Where is MARUTI FOREST located?

As reported to UP-RERA, MARUTI FOREST is located at Agra, Agra, Uttar Pradesh.

Is MARUTI FOREST completed?

As reported to UP-RERA, MARUTI FOREST was completed on 22 Jun 2024.

Is MARUTI FOREST delayed?

Measured against the latest completion date reported to UP-RERA, MARUTI FOREST is 51 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026