Mayfair Residency

UPRERARegistered

Mayfair Residency is a RERA-registered residential project by SUPER CITY DEVELOPERS PVT LTD in Gautam Budh Nagar (RERA ID UPRERAPRJ852). Registered with a completion deadline of 31 Dec 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2025
Quarters shown are calendar quarters. UP-RERA files them by financial year.
53%Q3'23
53.33%Q4'23
64.82%Q1'24
67%Q2'24
67%Q3'24
68%Q4'24
69%Q1'25
69%Q2'25

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ852
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start14 Aug 2017
Project duration137 months
AddressPatwari, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant address330,G.T. ROAD, SHAHDARA, DELHI - 110032
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    BP-2633/44/CPA-6064

  2. valid to

    Permit revalidated

    BP-2633/44/GDJ-9433

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. Extension granted (2)

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Permit revalidated (2)

  8. 2 building permits sanctioned

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered14 Aug 2017
Original completion31 Dec 2018
Revised completion31 Dec 2028
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,25,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors1,052 · 12 · 18 (units from plan)
  • 2 BHK502 48%
  • 3 BHK437 42%
  • 4 BHK98 9%
  • 5 BHK15 1%
ConfigurationUnitsCarpet area
3 BHK43767-83
2 BHK50252-83
4 BHK98111
5 BHK15131
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 3 BHK187367-83
B · 2 BHK187252
C · 2 BHK, 3 BHK1810852-83
D · 3 BHK187667
E · 3 BHK, 2 BHK1810852-83
F · 2 BHK, 3 BHK1810852-67
G · 4 BHK, 5 BHK1677111-131
H · 2 BHK187252
I · 3 BHK, 2 BHK1810852-83
J · 3 BHK187267-83
K · 3 BHK, 2 BHK1810752-83
L · 3 BHK, 4 BHK187183-111
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
DEEPAK MEHTA & ASSOCIATES
License COA/87/10840
PLOT NO 16 ABHISHEK PLAZA MAYUR VIHAR PH 2 DELHI 110091
Engineer
VINOD K MEHTA
NITI KHAND INDIRAPURAM
Contractor
M HAZRAT ALI CONSTRUCTION
KHASRA NO 547 CHIJARSI COLONY NOIDA(UP)
Sr.Development work declared to RERA
1Demarcation of Plots
As per lease plan
2Boundary Wall
Brick work ,RCC Columns & P beams with m.s Raillings and permanent furnishing on boundary wall
3Road Work
Cement concrete road with laying of pavers on top.
4Footpaths
R.C.C and as per landscape architect plan
5Water Supply Including Drinking Water Facilities
Underground tank of adequate capacity, overhead tanks in each tower, drinking water supply by GNIDA and as per M.E.P consultant
6Sewer System
Design sewer system with hume pipes and as per M.E.P consultant
7Drain
Drain system as per M.E.P consultant drawing
8Parks
As per landscape consultant
9Tree Planting
Sufficient plantation as per landscape consultant
10Design For Electric Supply Including Street Lighting
As per consultant drawing uploaded & services approved by M.E.P consultant
11Community Buildings
Club house as per plan
12Treatment and Disposal System of Sewage and Sullage water
STP provided as per EC norms and M.E.P consultant
13Solid Waste Management And Disposal System
As per consultant drawing sewerage system planned garbage recycle machine as per M.E.P consultant
14Water Conservation System
Rain water harvesting pits as per drawing issued by the consultant
15Energy Management System Including Use of Renewable Energy
Led light in common area
16Fire Protection And Fire Safety System
Manual fire alarm system as per N.B.C and as per provisional sanction
17Social Infrastructure And Other Public Amenities Including Public Health Services
Social Infrastructure & Other Public Health Services in Progress
18Emergency Evacuation Services
Staircase in each tower as per sanction plan
19Other Miscellaneous Work
Commercial space within complex
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 16 Dec 2024. All 3 carry a revalidation, the latest valid to 15 Dec 2029.

Sanctioned by Greater Noida Authority · 24,000 sqm of land · an approved plan of 12 blocks and 1052 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
BP-2633/44/CPA-606414 Dec 201313 Dec 201811 Dec 202431 Dec 202212 Dec 2014
valid to 11 Dec 2019
as BP-2633/44/GDJ-9433
BP-2633/44/CPA-606416 Dec 201916 Dec 202431 Dec 202831 Dec 202216 Dec 2019
valid to 15 Dec 2029
BP-2633/44/CPA-606416 Dec 201916 Dec 201912 Aug 202931 Dec 202216 Dec 2019
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 31 Dec 2028.

#Granted fromExtended uptoNote
131 Dec 201831 Dec 2022—
231 Dec 201831 Dec 2028—

Land & documents

12 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
163TECH ZONE 4—
GH07 B24000Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 11 Feb 2011.

Registry no.DateTypeArea
PROP/BRS-03/2010/172611 Feb 2011Own—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 7983
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Nov 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Nov 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Nov 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old27 Jul 2017 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old27 Jul 2017 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old27 Jul 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old27 Jul 2017 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old27 Jul 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterGNIDA WATER
Fire safety (as filed with RERA)YES
Other facilitiesATM,SHOP

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

21 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

21 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q453%CA ↗ · Eng ↗
2023-Q154%CA ↗ · Eng ↗
2023-Q253%CA ↗ · Eng ↗
2023-Q353.33%CA ↗ · Eng ↗
2023-Q464.82%CA ↗ · Eng ↗
2024-Q167%CA ↗ · Eng ↗
2024-Q267%CA ↗ · Eng ↗
2024-Q368%CA ↗ · Eng ↗
2024-Q469%CA ↗ · Eng ↗
2025-Q169%CA ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSUPER CITY DEVELOPERS PVT LTD
RolePromoter · current
RERA IDUPRERAPRM1153
PANAABCI5062L
CIN / TANDELS42406A
Name of chairmanDEEPAK MIGLANI
Registered address330,G.T. ROAD, SHAHDARA, DELHI - 110032
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameAVINYA REALTECH INDIA PVT LIMITED-MILAN GROUP
RoleCo-promoter
Applicant typePartnership Firm
Address115A MAIN VIKAS MARG NEW DELHI 110092
RERA contact

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
CURRENT ACCOUNTBankKARNATAKA BANKBranchSAVITA VIHARA/C no.IFSCKARB0000544
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

10 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)232 (Under Registration - 2 ) → 233 (Under Registration - 2 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)231 (Under Registration - 1 ) → 232 (Under Registration - 2 )
changed in Estanzo’s record
5 Oct 2026
Promoter’s complaints tally (all their projects)231 (Under Registration - 2 ) → 231 (Under Registration - 1 )
changed in Estanzo’s record
3 Oct 2026
Promoter’s complaints tally (all their projects)231 (Under Registration - 3 ) → 231 (Under Registration - 2 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)231 (Under Registration - 4 ) → 231 (Under Registration - 3 )
changed in Estanzo’s record
19 Sept 2026
Promoter’s complaints tally (all their projects)230 (Under Registration - 3 ) → 231 (Under Registration - 4 )
changed in Estanzo’s record
15 Sept 2026
Promoter’s complaints tally (all their projects)229 (Under Registration - 2 ) → 230 (Under Registration - 3 )
changed in Estanzo’s record
5 Sept 2026
Promoter’s complaints tally (all their projects)229 (Under Registration - 3 ) → 229 (Under Registration - 2 )
changed in Estanzo’s record
1 Sept 2026
Promoter’s complaints tally (all their projects)229 (Under Registration - 4 ) → 229 (Under Registration - 3 )
changed in Estanzo’s record
23 Aug 2026
Promoter’s complaints tally (all their projects)228 (Under Registration - 3 ) → 229 (Under Registration - 4 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 10 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Mayfair Residency

Is Mayfair Residency RERA registered?

Yes. Mayfair Residency is registered with UPRERA under registration number UPRERAPRJ852, registered on 14 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Mayfair Residency?

The completion date filed with UPRERA is 31 Dec 2028. No completion certificate is on record yet.

Who is the builder of Mayfair Residency?

SUPER CITY DEVELOPERS PVT LTD is the promoter entity that filed Mayfair Residency with UPRERA (promoter RERA ID UPRERAPRM1153). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Mayfair Residency more time to complete?

UPRERA's record carries 2 completion extensions for Mayfair Residency, the latest running to 31 Dec 2028. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Mayfair Residency have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Mayfair Residency located?

Mayfair Residency is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Mayfair Residency?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK, 4 BHK and 5 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Mayfair Residency?

The approved unit plan filed with UPRERA runs from 52 to 131 m² of carpet area (about 561 to 1,408 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Mayfair Residency?

The approved unit plan describes 12 blocks and 1,052 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Mayfair Residency?

About 177 units per acre: 1,052 planned units across 5.93 acres (24,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗