Millenium Square is a RERA-registered commercial project by KVG Realtech Pvt. Ltd. in Lucknow (RERA ID UPRERAPRJ6842). Registered with a completion deadline of 26 Jan 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ6842 |
| Project category | Commercial |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 30 Jul 2015 |
| Original start | 21 Jan 2013 |
| Project duration | 66 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Company |
| Applicant address | 9 B, ATMA RAM HOUSE, TOLSTOY MARG, CONNAUGHT PLACE, NEW DELHI-110001. |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
38580
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 4 Aug 2017 |
| Original completion | 27 Jul 2020 |
| Revised completion | 26 Jan 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 2 Apr 2022 |
| Registration fee | ₹70,000 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | — | 1,424-2,745 |
| OTHER | — | 1,024 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| 1 · SHOP, OTHER | 8 | — | 1,024-2,745 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Not Applicable as we are selling plots |
| 2 | Boundary Wall Although the project is being build within the gated community of Sushant Golf city, the boundry wall for commercial project are not required, still for the safety of our customer, the same is being constructed |
| 3 | Road Work In the Scope of Ansal API |
| 4 | Footpaths In the Scope of Ansal API |
| 5 | Water Supply Including Drinking Water Facilities Completed |
| 6 | Sewer System The work in our scope has been completed but the same is pending at Ansal API |
| 7 | Drain Completed |
| 8 | Parks Not in our scope |
| 9 | Tree Planting Completed |
| 10 | Design For Electric Supply Including Street Lighting The design of Electric Supply is final and the work is under progress |
| 11 | Community Buildings In the Scope of Ansal API |
| 12 | Treatment and Disposal System of Sewage and Sullage water Completed |
| 13 | Solid Waste Management And Disposal System In the Scope of Ansal API |
| 14 | Water Conservation System Completed |
| 15 | Energy Management System Including Use of Renewable Energy Completed |
| 16 | Fire Protection And Fire Safety System Completed |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Completed |
| 18 | Emergency Evacuation Services Completed |
| 19 | Other Miscellaneous Work Completed |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 29 Jul 2020.
Sanctioned by Lucknow Development Authority · 5,907 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 38580 | 30 Jul 2015 | 29 Jul 2020 | 29 Jul 2020 | 27 Jul 2020 |
UPRERA’s record carries 1 completion extension for this project, running to 26 Jan 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 27 Jul 2020 | 26 Jan 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
3 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 619 & 623 & 624 & 632 (Vill.Harihar Pur ) | 5906.75 sq. mt | — |
| 619 & 623 & 624 & 632 (Vill.Harihar Pur ) | 5907 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 14 Oct 2015.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 19600 | 14 Oct 2015 | self | — |
| Registry document · IN-UP01401173044210N The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | Yes |
| Fire safety (as filed with RERA) | Yes |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
5 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
5 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | 100% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | KVG Realtech Pvt. Ltd. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM2994 |
| PAN | AAECK1263C |
| CIN / TAN | U70200DL2010PTC209025 |
| Registered address | 9 B, ATMA RAM HOUSE, TOLSTOY MARG, CONNAUGHT PLACE, NEW DELHI-110001. |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Current AccountBankVijaya BankBranchGokhale MargA/C no.IFSCVIJB0007161 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about Millenium Square
Is Millenium Square RERA registered?
Yes. Millenium Square is registered with UPRERA under registration number UPRERAPRJ6842, registered on 4 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Millenium Square been completed?
UPRERA still lists Millenium Square as Registered, so it is not shown as completed here. A completion certificate dated 2 Apr 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Millenium Square?
KVG Realtech Pvt. Ltd. is the promoter entity that filed Millenium Square with UPRERA (promoter RERA ID UPRERAPRM2994). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Millenium Square more time to complete?
UPRERA's record carries 1 completion extension for Millenium Square, the latest running to 26 Jan 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Millenium Square have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Millenium Square located?
Millenium Square is registered in Lucknow, as filed with UPRERA.
What configurations are available in Millenium Square?
The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Millenium Square?
The approved unit plan filed with UPRERA runs from 1,024 to 2,745 m² of carpet area (about 11,018 to 29,547 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗