Timeline Bar

Registered28 Jul 2017
Promised31 Mar 2021
Today4 Aug 2026

Timeline

Promised completion31 Mar 2021
Revised completion31 Mar 2021
Actual completion
Possession delay64 mo delay

Registration & Cost Details

Registration fee (in ₹)₹56,500
Project cost (in ₹ Lakhs)₹1,17,53,67,968 Lakhs
Project duration93 months
Project categoryResidential
Locality
Original start date1 Jan 2013
Proposed start date1 Jan 2014

Inventory

Total units397985
Unit TypeUnitsCarpet Area (sqm)
3 BHK21100576.593–77.73
OTHER18698082.71–84.48

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8586928776
Emailrera_2017@imperiastructures.in
Coordinator964303550/011-46469999
AddressA-25, Mohan Co-operative Industrial Estate Mathura Road, New Delhi-110044

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q427.1%
2021-Q127.1%
2021-Q227.1%
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Niyojan/BP-15/9148 May 20147 May 201931 Mar 20216 May 2021

Land Parcels

Khasra No.AreaPlot Type
GH-F310242
GH-F320234Plot

Approved Unit Plan

Unit plan rows on file314
Total flats (sum of rows)397985
Blocks1, 2, 3
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
108643 May 2013
108643 May 2013

Frequently Asked Questions

What is the RERA registration number of Mirage Phase I?

The RERA registration number of Mirage Phase I is UPRERAPRJ3142, as recorded on the UP-RERA portal.

What is the RERA status of Mirage Phase I?

As reported by UP-RERA, the status of Mirage Phase I is "Registered".

Where is Mirage Phase I located?

As reported to UP-RERA, Mirage Phase I is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Mirage Phase I be completed?

The latest completion date reported to UP-RERA for Mirage Phase I is 31 Mar 2021.

Is Mirage Phase I delayed?

Measured against the latest completion date reported to UP-RERA, Mirage Phase I is 64 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026