NEOTOWN PHASE-2

UPRERARegistered

NEOTOWN PHASE-2 is a RERA-registered residential project by PATEL ADVANCE JV in Gautam Budh Nagar (RERA ID UPRERAPRJ7256). Registered with a completion deadline of 31 Dec 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
21.42%Q4'24
22.42%Q1'25
24.4%Q2'25
26%Q3'25
28.41%Q4'25
28.6%Q1'26
28.62%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7256
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start15 Feb 2017
Original start15 Feb 2017
Project duration143 months
AddressPlot No. GH03, Sector TECH ZONE-IV, Greater Noida, Gautam Budh Nagar, U.P. – 201306, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typePartnership Firm
Applicant addressRegistered Office Address- S-406, Lower Ground Floor, Greater Kailash-II, New Delhi - 110048, Corporate Office Address- GH-03, Techzone-4, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh - 201310, Site Address- GH-03, Techzone-4, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh - 201310
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. valid to

    Permit revalidated

    PLG/BP/SM-19-Aug-2025:25906

  6. Building permit sanctioned

    PLG/BP/2565/8489

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  9. to

    Extension granted

  10. to

    Extension granted

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion14 Mar 2022
Revised completion31 Dec 2028
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹80,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors292 · 3 · 25 (units from plan)
  • 2 BHK146 50%
  • 3 BHK140 48%
  • PENTHOUSE6 2%
ConfigurationUnitsCarpet area
2 BHK14656
3 BHK14069-80
PENTHOUSE666-94
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
J-1 · 2 BHK, PENTHOUSE2514856-66
J-2 · 3 BHK, PENTHOUSE187079-94
L · 3 BHK, PENTHOUSE197469-85
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
GIAN P. MATHUR & ASSOCIATES PVT. LTD.
License CA NO. 8015769
C-55, EAST OF KAILASH,NEW DELHI-110065
Engineer
OPTIMUM DESIGN PVT. LTD.
B-24,SEC-67,NOIDA-201301
Sr.Development work declared to RERA
1Demarcation of Plots
east side - Plot of other, North side - Plot of other, South - Road, West - Road
2Boundary Wall
Boundary wall – combination of RCC and Brick Work
3Road Work
All internal roads in concrete paver blocks
4Footpaths
Footpath in stone, stamp concrete and grass
5Water Supply Including Drinking Water Facilities
Water supply from Authority
6Sewer System
Sewer line with required slope and adequate manholes
7Drain
Adequate catch basin and manholes are provided for surface drain
8Parks
Green area is provided
9Tree Planting
Variety of trees and shrubs are to be planted
10Design For Electric Supply Including Street Lighting
Sufficient lighting as per service and landscape consultant
11Community Buildings
Community buildings with various amenities will be provided
12Treatment and Disposal System of Sewage and Sullage water
stp is proposed
13Solid Waste Management And Disposal System
as per authority
14Water Conservation System
Rain water harvesting
15Energy Management System Including Use of Renewable Energy
na
16Fire Protection And Fire Safety System
As per fire fighting Norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
club, community center, Gym,etc
18Emergency Evacuation Services
fire staircase in each tower/blocks
19Other Miscellaneous Work
na
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

3 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2SMC Real Estate Advisors Private LimitedUPRERAAGT10113
3SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

4 permits

An approval and the date it runs to - not proof the work matching it was done.

4 sanctioning permits are on record with UPRERA, the latest valid to 22 Nov 2026. 3 of them carry a revalidation, the latest valid to 28 Nov 2030.

Sanctioned by Greater Noida Authority · 15,067 sqm of land · an approved plan of 3 blocks and 292 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/BP/2565/848924 Nov 201623 Nov 202123 Nov 202614 Mar 2022—
PLG/BP/2565/848924 Nov 201623 Nov 202122 Nov 202613 Sept 202224 Nov 2016
valid to 22 Nov 2026
as PLG/BP/SM-19-Aug-2025:25906
PLG/BP/2565/848924 Nov 201623 Nov 202122 Nov 202613 Sept 202224 Nov 2016
valid to 22 Nov 2026
as PLG/BP/SM-19-Aug-2025:25906
PLG/BP/2565/848923 Nov 202122 Nov 202627 Nov 203522 Nov 202623 Nov 2021
valid to 28 Nov 2030
as PLG/BP/SM-19-Aug-2025:25906
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 31 Dec 2028.

#Granted fromExtended uptoNote
114 Mar 202213 Sept 2022Six months extension in view of force majeure caused by covid-19 pandemic
213 Sept 202222 Nov 2026—
322 Nov 202631 Dec 2028—

Land & documents

8 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-03, TECHZONE-IV, GREATER NOIDA WEST95970Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 6 Aug 2010.

Registry no.DateTypeArea
PAGE NO. 137 TO 172, BOOK NO. 1 , JILD NO. 7238, S6 Aug 2010self—
22186, JILD NO.1 TO 7448, PAGE NO. 293 TO 30813 Oct 2010self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 19809
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 22186
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New15 Sept 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New15 Sept 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New15 Sept 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New15 Sept 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New15 Sept 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New15 Sept 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterPROVIDED BY GNIDA
Fire safety (as filed with RERA)APPROVED VIDE LETTER NO. 53/J.D./LUCKNOW-16/344

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

26 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

26 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q313.45%CA ↗ · Arch ↗ · Eng ↗
2022-Q413.45%CA ↗ · Arch ↗ · Eng ↗
2023-Q113.45%CA ↗ · Arch ↗ · Eng ↗
2023-Q213.45%CA ↗ · Arch ↗ · Eng ↗
2023-Q313.45%CA ↗ · Arch ↗ · Eng ↗
2023-Q418.61%CA ↗ · Arch ↗ · Eng ↗
2024-Q124.2%CA ↗ · Arch ↗ · Eng ↗
2024-Q221.33%CA ↗ · Arch ↗ · Eng ↗
2024-Q321.42%CA ↗ · Arch ↗ · Eng ↗
2024-Q422.42%CA ↗ · Arch ↗ · Eng ↗
2025-Q124.4%CA ↗ · Arch ↗ · Eng ↗
2025-Q226%CA ↗ · Arch ↗ · Eng ↗
2025-Q328.41%CA ↗ · Arch ↗ · Eng ↗
2025-Q428.6%CA ↗ · Arch ↗ · Eng ↗
2026-Q128.62%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePATEL ADVANCE JV
RolePromoter · current
RERA IDUPRERAPRM13448
PANAALFP7744D
CIN / TANDELP16709A
Registered addressRegistered Office Address- S-406, Lower Ground Floor, Greater Kailash-II, New Delhi - 110048, Corporate Office Address- GH-03, Techzone-4, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh - 201310, Site Address- GH-03, Techzone-4, Greater NOIDA (West), Gautam Buddha Nagar, Uttar Pradesh - 201310
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PATEL ADVANCE JV COLLECTION PHASE 2 A/C NEOTOWNBankAXIS BANK LIMITEDBranchSECTOR-51, NOIDA, U.P.Branch addressSECTOR-51, NOIDA, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0001149Branch emailsector51noida.operationsheadataxisbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PATEL ADVANCE JV RERA PHASE 2 A/C NEOTOWNBankAXIS BANK LIMITEDBranchSECTOR-51, NOIDA, U.P.Branch addressSECTOR-51, NOIDA, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0001149Branch emailsector51noida.operationsheadataxisbank.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PATEL ADVANCE JV PHASE 2 A/C NEOTOWNBankAXIS BANK LIMITEDBranchSECTOR-51, NOIDA, U.P.Branch addressSECTOR-51, NOIDA, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0001149Branch emailsector51noida.operationsheadataxisbank.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

7 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
19 Oct 2026
Promoter’s complaints tally (all their projects)235 (Under Registration - 4 ) → 235 (Under Registration - 3 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)235 (Under Registration - 5 ) → 235 (Under Registration - 4 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)234 (Under Registration - 4 ) → 235 (Under Registration - 5 )
changed in Estanzo’s record
13 Sept 2026
Promoter’s complaints tally (all their projects)233 (Under Registration - 3 ) → 234 (Under Registration - 4 )
changed in Estanzo’s record
9 Sept 2026
Revised completion date on file2026-11-22 → 2028-12-31
changed in Estanzo’s record
16 Aug 2026
Completion extension
no. 3
extension 3 to 2028-12-31
newly filed with RERA
16 Aug 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 16 Aug 2026
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 23 Sept 2026 · 4 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about NEOTOWN PHASE-2

Is NEOTOWN PHASE-2 RERA registered?

Yes. NEOTOWN PHASE-2 is registered with UPRERA under registration number UPRERAPRJ7256, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for NEOTOWN PHASE-2?

The completion date filed with UPRERA is 31 Dec 2028. No completion certificate is on record yet.

Who is the builder of NEOTOWN PHASE-2?

PATEL ADVANCE JV is the promoter entity that filed NEOTOWN PHASE-2 with UPRERA (promoter RERA ID UPRERAPRM13448). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted NEOTOWN PHASE-2 more time to complete?

UPRERA's record carries 3 completion extensions for NEOTOWN PHASE-2, the latest running to 31 Dec 2028. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does NEOTOWN PHASE-2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is NEOTOWN PHASE-2 located?

NEOTOWN PHASE-2 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in NEOTOWN PHASE-2?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in NEOTOWN PHASE-2?

The approved unit plan filed with UPRERA runs from 56 to 94 m² of carpet area (about 602 to 1,012 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in NEOTOWN PHASE-2?

The approved unit plan describes 3 blocks and 292 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is NEOTOWN PHASE-2?

About 78 units per acre: 292 planned units across 3.72 acres (15,067 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗