ONE FNG

UPRERARegistered

ONE FNG is a RERA-registered commercial project by SS TECHNOPARK PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ279516). Registered with a completion deadline of 13 Aug 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
25%Q3'25
26%Q4'25
38.75%Q1'26
45.22%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ279516
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Sept 2023
Project duration60 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant address2nd Floor, Plot No.2 AND 3, A Block Market, Savitri Bhawan, Preet Vihar, Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2023/06/01/9053

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered26 Oct 2023
Original completion13 Aug 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹5,96,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors1,407 · 7 · 40 (units from plan)
Homes · commercial units1,116 · 291 (shops and offices filed in the same plan)
  • OTHER1,116 79%
  • SHOP291 21%
ConfigurationUnitsCarpet area
OTHER1,1166-217
SHOP29112-163
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
F1 · OTHER, SHOP64719-52
F2 · OTHER, SHOP42526-72
F3 · OTHER, SHOP46422-160
F4 · OTHER, SHOP47512-158
F5 · OTHER, SHOP64120-636
Tower A (South Wing) · OTHER, SHOP407526-217
Tower B · OTHER, SHOP1844028-215
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 1,130 m² for a SHOP, 1,130 m² for a SHOP, 636.39 m² for a SHOP and 2 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ACPL Ravi Kumar Garg
License CA/2013/58473
E- 24, South Extention 1, Block E, New Delhi-110049
Engineer
Vintech Consultants
C-35, Pamposh Enclave, Greater Kailash1, New Delhi-110048
Contractor
Jindal Steel and Power Limited
Plot No. 2, Sector 32 Gurugram 122001
Sr.Development work declared to RERA
1Demarcation of Plots
THE PROJECT LAND WILL BE DEMARCATED BY ITS BOUNDARY WALL TO THE EXACT SHAPE, SIZE AND ORIENTATION AS PER SANCTION MAP BY NOIDA DEVELOPMENT AUTHORITY.
2Boundary Wall
A 2 M High boundary wall of brick and plaster will be construction with deep foundation to be earthquake resistant. the wall will be plaster and painted as per aesthetics.
3Road Work
A pavement Quality concrete will be laid in thickness of + 200 mm on top of compacted dry lean concrete/ coarse grained sub- base .
4Footpaths
An M-15 grade of paver block/ inter locking tiles will be laid in the project for walking areas. Tiles will be 3 to 4 inch thick and the colour patters will be lasting and visible at all hours.
5Water Supply Including Drinking Water Facilities
A protable water supply through the concerned Government Authority will be delivered to the water tank of 10000 L capacity on terrace.
6Sewer System
The Sewage will be collected through a soil pipe arrangement U- bends and inspection chambers leading to the septic tank of the project, from where the sewage will be disposed to the STP System.
7Drain
A surface drain with specs of 150 mm CC sub-base over compacted earth topped with 20 mm of cement mortar to the size of 150 x 75 laid in slope of 1 to 300 leading to GT.
8Parks
Green park will be maintained in the project as per approved plan by Noida Development Authority . the park will have footpath, sitting area and small play area for kids.
9Tree Planting
The trees will be planted at suitable location of the project and along the boundary wall. the tree section will be done to ensure no hindrance in the service for future.
10Design For Electric Supply Including Street Lighting
Electrical layout and capacity will be installed to suffice the domestic use of the project. the load sanction will be taken form the Vidyut Vibhag.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
Centralised STP to treat the Seweage.
13Solid Waste Management And Disposal System
Project shall have waste segregation area and OWC for treatment.
14Water Conservation System
Rain water harvesting system duel flush System.
15Energy Management System Including Use of Renewable Energy
Solar panel LED light and VFD panels shall be used for efficient energy management.
16Fire Protection And Fire Safety System
Fire alarm system provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable.
18Emergency Evacuation Services
As Per Approved Building Plan
19Other Miscellaneous Work
As Per Approved Building Plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

7 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1BOP REALTY PRIVATE LIMITEDUPRERAAGT10206
2BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
3INVESTOXPERT ADVISORS PVT LTDUPRERAAGT21108
4ORANGE DOOR INFRA PRIVATE LIMITEDUPRERAAGT15693
5RAVS INFRATECH PRIVATE LIMITEDUPRERAAGT20392
6REDMAPLE BUILDIKO PRIVATE LIMITEDUPRERAAGT14395
7SQRFT INFRATECH PRIVATE LIMITEDUPRERAAGT24591
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 13 Aug 2028.

Sanctioned by Noida Authority · 58,536 sqm of land · an approved plan of 7 blocks and 1407 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2023/06/01/905314 Aug 202313 Aug 202813 Aug 203113 Aug 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Plot No. 1, Sector 142 Noida G.B. Nagar58535.75Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · Noida/ Institutional/2016/3040
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Registry document · LAND SEARCH REPORT
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Lease deed · 5314-5423
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 7146
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New30 Aug 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New26 Aug 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New26 Aug 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New26 Aug 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New26 Aug 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New26 Aug 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New26 Aug 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New26 Aug 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New26 Aug 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Sept 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Aug 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Aug 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New15 Sept 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q2 to 2026-Q2.

QuarterConstructionCertificates
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q225%CA ↗ · Arch ↗ · Eng ↗
2025-Q326%CA ↗ · Arch ↗ · Eng ↗
2025-Q438.75%CA ↗ · Arch ↗ · Eng ↗
2026-Q145.22%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSS TECHNOPARK PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM252984
PANAAKCS1958G
CIN / TANDELA40953D
Name of chairmanSANCHIT BHUTANI
Registered address2nd Floor, Plot No.2 AND 3, A Block Market, Savitri Bhawan, Preet Vihar, Delhi-110092
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SS TECHNOPARK PRIVATE LIMITED COLLECTION ACCOUNT FOR ONE FNGBankICICI BANKBranchICICI Bank, Sector 137 Noida 201301Branch addressICICI BANK LTD, 104,PLOT NO-GH 07A, VIVANTE, SECTOR 137, NOIDA 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICICI0003451
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SS TECHNOPARK PRIVATE LIMITED SEPARATE ACCOUNT FOR ONE FNGBankICICI BANKBranchICICI BANK LTD, SECTOR 137 NOIDA 201301Branch addressICICI BANK LTD. 104, PLOT NO GH-07A, GULSHAN VIVANTE, SECTOR 137, NOIDA 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0003451
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SS TECHONARK PRIVATE LIMITED RERA TRANSACTION ACCOUNT FOR ONE FNGBankICICI BANKBranchICICI BANK LTD, SECTOR 137 NOIDA 201301Branch addressICICI BANK LTD, 104, PLOY NO GH 07A, GULSHAN VIVANTE, SECTOR 137, NOIDA 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0003451
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ONE FNG

Is ONE FNG RERA registered?

Yes. ONE FNG is registered with UPRERA under registration number UPRERAPRJ279516, registered on 26 Oct 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ONE FNG?

The completion date filed with UPRERA is 13 Aug 2028. No completion certificate is on record yet.

Who is the builder of ONE FNG?

SS TECHNOPARK PRIVATE LIMITED is the promoter entity that filed ONE FNG with UPRERA (promoter RERA ID UPRERAPRM252984). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ONE FNG have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ONE FNG located?

ONE FNG is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in ONE FNG?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in ONE FNG?

The approved unit plan filed with UPRERA runs from 6 to 217 m² of carpet area (about 65 to 2,337 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in ONE FNG?

The approved unit plan describes 7 blocks and 1,407 units of which 1,116 are homes and 291 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is ONE FNG?

About 97 units per acre: 1,407 planned units across 14.46 acres (58,536 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗