ORIZZONTE (RESIDENTIAL) is a RERA-registered residential project by Concept Horizon Infra Private Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ12539). Registered with a completion deadline of 31 Oct 2028.
RERA status as reported: Registered.Construction progress
Construction stayed at 20% across 25 consecutive filed quarters (Apr–Jun 2020 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ12539 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Greater Noida Authority |
| Proposed start | 31 May 2016 |
| Original start | 1 Apr 2015 |
| Project duration | 150 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | 8/11, 1st Floor, Hospital Road, Jangpura Extension, New Delhi- 110014. |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated
1370/002-2/8724
3 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 12 Oct 2017 |
| Original completion | |
| Revised completion | 31 Oct 2028 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,65,500 |
| Sanctioning authority | Greater Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- OTHER836 67%
- 1 BHK206 17%
- 2 BHK200 16%
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 836 | 10-10 |
| 1 BHK | 206 | 24-26 |
| 2 BHK | 200 | 35-44 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| BUNK (RMA) · OTHER | 15 | 421 | 10 |
| RT-1 · OTHER, 1 BHK, 2 BHK | 18 | 224 | 26-44 |
| RT-2 · OTHER, 1 BHK, 2 BHK | 15 | 182 | 24-35 |
| WEB (RMA) · OTHER | 13 | 415 | 10 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Yes |
| 2 | Boundary Wall Partial |
| 3 | Road Work Partial |
| 4 | Footpaths Partial |
| 5 | Water Supply Including Drinking Water Facilities Available |
| 6 | Sewer System In Process |
| 7 | Drain Being Developed |
| 8 | Parks Being Developed |
| 9 | Tree Planting Partial |
| 10 | Design For Electric Supply Including Street Lighting Already There as per MEP Consultant |
| 11 | Community Buildings NA |
| 12 | Treatment and Disposal System of Sewage and Sullage water Being Developed as per MEP Consultant |
| 13 | Solid Waste Management And Disposal System Being Developed as per MEP Consultant |
| 14 | Water Conservation System Being Developed as per MEP Consultant |
| 15 | Energy Management System Including Use of Renewable Energy Being Developed as per MEP Consultant |
| 16 | Fire Protection And Fire Safety System Yes |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Yes |
| 18 | Emergency Evacuation Services Yes |
| 19 | Other Miscellaneous Work Being Developed as per Consultants |
Registered agents
3 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | BOP REALTY PRIVATE LIMITED | UPRERAAGT10206 |
| 2 | Earth Homes Pvt. Ltd | UPRERAAGT11244 |
| 3 | SQUARE YARDS CONSULTING PRIVATE LIMITED | UPRERAAGT10119 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 18 Nov 2019. 1 of them carries a revalidation.
Sanctioned by Greater Noida Authority · 32,032 sqm of land · an approved plan of 4 blocks and 1242 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 1370/002-2/8724 | 19 Nov 2014 | 18 Nov 2019 | 18 Nov 2020 | 17 Nov 2019 | — | |
| 1370/002-2/8724 | 19 Nov 2014 | 18 Nov 2019 | 18 Nov 2020 | 17 Nov 2019 | — | |
| 1370/002-2/8724 | 19 Nov 2014 | 18 Nov 2019 | 17 Nov 2024 | 17 Nov 2019 | 19 Nov 2014 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 31 Oct 2028.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Oct 2028 | — |
Land & documents
23 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 22 | 60180 SQMTR OUT OF WHICH FSI OF 521000 SQFT | — |
| 22 KP-3, GREATER NOIDA | 60180 SQMTR OUT OF WHICH FSI OF 521000 SQFT | Plot |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 7 Jun 2013.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| IN-DL22570552847845L | 7 Jun 2013 | other | — |
| Registry document · IN-DL22570552847845L The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 6 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 6 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 6 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 6 Jul 2018 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 31 Aug 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 31 Aug 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 31 Aug 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 31 Aug 2017 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | Old | 31 Aug 2017 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | Old | 31 Aug 2017 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | Old | 31 Aug 2017 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 31 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | Yes |
| Fire safety (as filed with RERA) | Yes |
| Health service | Health care clinic situated nearby |
| Renewable energy | Yes |
| Other facilities | Club House |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
25 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 20% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Concept Horizon Infra Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM12816 |
| PAN | AAFCC3094C |
| CIN / TAN | U70200DL2013PTC254773 |
| Name of chairman | 1. Jeevesh Sabharwal 2. Nitant Verma |
| Registered address | 8/11, 1st Floor, Hospital Road, Jangpura Extension, New Delhi- 110014. |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Concept Horizon Infra Private LimitedBankPunjab & Sind BankBranchAtta BranchA/C no.IFSCPSIB0000426 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 281 (Under Registration - 0 ) → 282 (Under Registration - 1 ) changed in Estanzo’s record | 13 Oct 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 13 Oct 2026 |
Common questions about ORIZZONTE (RESIDENTIAL)
Is ORIZZONTE (RESIDENTIAL) RERA registered?
Yes. ORIZZONTE (RESIDENTIAL) is registered with UPRERA under registration number UPRERAPRJ12539, registered on 12 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for ORIZZONTE (RESIDENTIAL)?
The completion date filed with UPRERA is 31 Oct 2028. No completion certificate is on record yet.
Who is the builder of ORIZZONTE (RESIDENTIAL)?
Concept Horizon Infra Private Limited is the promoter entity that filed ORIZZONTE (RESIDENTIAL) with UPRERA (promoter RERA ID UPRERAPRM12816). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted ORIZZONTE (RESIDENTIAL) more time to complete?
UPRERA's record carries 1 completion extension for ORIZZONTE (RESIDENTIAL), the latest running to 31 Oct 2028. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does ORIZZONTE (RESIDENTIAL) have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is ORIZZONTE (RESIDENTIAL) located?
ORIZZONTE (RESIDENTIAL) is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in ORIZZONTE (RESIDENTIAL)?
The unit plan filed with UPRERA lists OTHER, 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in ORIZZONTE (RESIDENTIAL)?
The approved unit plan filed with UPRERA runs from 10 to 44 m² of carpet area (about 102 to 474 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in ORIZZONTE (RESIDENTIAL)?
The approved unit plan describes 4 blocks and 1,242 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is ORIZZONTE (RESIDENTIAL)?
About 157 units per acre: 1,242 planned units across 7.92 acres (32,032 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗