Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ16264
Project categoryResidential
Registration typeNew
RERA statusCompleted
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start22 May 2018
Project duration89 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressASPIRE 2-701, SUPERTECH EMERALD COURT, SECTOR 93B, NOIDA, (U.P.)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/(BP)-3259(S)/B8/REC/FTS-3280

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Permit revalidated (2)

  5. Building permit sanctioned

    3259(S)/5381

  6. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. to

    Extension granted

  9. to

    Extension granted

  10. to

    Extension granted

  11. Completion certificate filed

  12. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Completed.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 May 2018
Original completion31 May 2022
Revised completion30 Sept 2025
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary25 Aug 2025
Registration fee₹31,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors46 · 1 · 11 (units from plan)
  • 4 BHK30 65%
  • VILLA10 22%
  • OTHER4 9%
  • PENTHOUSE2 4%
ConfigurationUnitsCarpet area
VILLA10356-360
OTHER4258-262
4 BHK30203-288
PENTHOUSE2343
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
PAGE- C1/C2/C3/C4/C5 · VILLA, OTHER, 4 BHK, PENTHOUSE1146203-360
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MODARCHINDIA
License CA/98/22706
PLOT NO.:-B-99 FIRST FLOOR, SECTOR-63 NOIDA
Engineer
OPTIMUM DESIGN PVT LTD
B-24, SEC-67, NOIDA
Contractor
TO BE DECIDED
NA
Sr.Development work declared to RERA
1Demarcation of Plots
AS PER PLAN
2Boundary Wall
AS PER PLAN
3Road Work
AS PER PLAN
4Footpaths
AS PER PLAN
5Water Supply Including Drinking Water Facilities
Municipal water shall be used as prime source along with Ground water . Provision of RO in kitchen for drinking purpose
6Sewer System
Soil & Waste from Toilet & Kitchen will be collected in single network of sewer pipe laid under ground with manhole & connected to Centralized STP of JP Greens
7Drain
Separate line for rain water with harvesting pit & Other line for soil & waste
8Parks
AS PER PLAN
9Tree Planting
AS PER PLAN
10Design For Electric Supply Including Street Lighting
Efficient & Effective design of substation with 100% Power back up &  street light in walk way and parks
11Community Buildings
AS PER PLAN
12Treatment and Disposal System of Sewage and Sullage water
Sewer water treatment through Centralized STP of Jaypee Greens Township with their disposal arrangement
13Solid Waste Management And Disposal System
AS PER PLAN
14Water Conservation System
VFD based hydro pneumatic pumps used with sensor , treated STP water used for flushing & Horticulture
15Energy Management System Including Use of Renewable Energy
Pumps &  equipment selected on best energy efficient point . Photoelectric senor used for external and common area light with provision of solar energy
16Fire Protection And Fire Safety System
Internal & external hydrant  system ,basement sprinkler ,MCP & Fire Extinguishers in all floors . As per Fire norms NBC -2016
17Social Infrastructure And Other Public Amenities Including Public Health Services
AS PER PLAN
18Emergency Evacuation Services
AS PER PLAN
19Other Miscellaneous Work
AS PER PLAN
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 6 Aug 2023. 2 of them carry a revalidation, the latest valid to 7 Aug 2028.

Sanctioned by Greater Noida Authority · 5,206 sqm of land · an approved plan of 1 block and 46 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/(BP)-3259(S)/B8/REC/FTS-32809 Jun 20159 Jun 2022—31 May 2022—
—8 Jun 20208 Jun 202530 Nov 20227 Aug 2018
valid to 6 Aug 2023
as PLG/(BP)3259(S)/5381
3259(S)/53817 Aug 20186 Aug 202317 Dec 20295 Aug 20247 Aug 2018
valid to 7 Aug 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 4 completion extensions for this project, the latest running to 30 Sept 2025.

#Granted fromExtended uptoNote
131 May 202230 Nov 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Nov 20226 Aug 2023—
36 Aug 20235 Aug 2024—
45 Aug 202430 Sept 2025—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-8 (LAND 1)5206Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 20029
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—

Quarterly progress reports

22 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

22 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q279.56%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q2. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHOME AND SOUL INFRATECH PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM2392
PANAACCV8946M
CIN / TANU45208DL2008PTC184425
Name of chairmanRAHUL RASTOGI (DIRECTOR)
Registered addressASPIRE 2-701, SUPERTECH EMERALD COURT, SECTOR 93B, NOIDA, (U.P.)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Home & Soul Infratech Private Limited-Page 3 ResidencesBankIDBI BANKBranchVaishaliA/C no.IFSCIBKL0000178
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

4 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)55 (Under Registration - 3 ) → 56 (Under Registration - 4 )
changed in Estanzo’s record
19 Oct 2026
Promoter’s complaints tally (all their projects)54 (Under Registration - 2 ) → 55 (Under Registration - 3 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)54 (Under Registration - 3 ) → 54 (Under Registration - 2 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)53 (Under Registration - 2 ) → 54 (Under Registration - 3 )
changed in Estanzo’s record
9 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 19 Oct 2026 · 4 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about PAGE THREE RESIDENCES

Is PAGE THREE RESIDENCES RERA registered?

Yes. PAGE THREE RESIDENCES is registered with UPRERA under registration number UPRERAPRJ16264, registered on 22 May 2018. Estanzo reproduces that filing; it does not verify the work behind it.

Has PAGE THREE RESIDENCES been completed?

UPRERA lists PAGE THREE RESIDENCES as completed, with a completion certificate dated 25 Aug 2025, against a filed deadline of 30 Sept 2025.

Who is the builder of PAGE THREE RESIDENCES?

HOME AND SOUL INFRATECH PRIVATE LIMITED is the promoter entity that filed PAGE THREE RESIDENCES with UPRERA (promoter RERA ID UPRERAPRM2392). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted PAGE THREE RESIDENCES more time to complete?

UPRERA's record carries 4 completion extensions for PAGE THREE RESIDENCES, the latest running to 30 Sept 2025. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does PAGE THREE RESIDENCES have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PAGE THREE RESIDENCES located?

PAGE THREE RESIDENCES is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in PAGE THREE RESIDENCES?

The unit plan filed with UPRERA lists VILLA, OTHER, 4 BHK and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in PAGE THREE RESIDENCES?

The approved unit plan filed with UPRERA runs from 203 to 360 m² of carpet area (about 2,185 to 3,875 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in PAGE THREE RESIDENCES?

The approved unit plan describes 1 block and 46 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is PAGE THREE RESIDENCES?

About 36 units per acre: 46 planned units across 1.29 acres (5,206 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗