Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ451261
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start22 Oct 2019
Project duration57 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typePartnership Firm
Applicant addressNo 137, Manas Enclave, Indiranagar, Lucknow 226016
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MAP-20181008184958653

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Dec 2019
Original completion31 Dec 2023
Revised completion30 Jun 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹19,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors42 · 1 · 6 (units from plan)
  • 2 BHK26 62%
  • 3 BHK10 24%
  • PENTHOUSE4 10%
  • 4 BHK2 5%
ConfigurationUnitsCarpet area
2 BHK2678
3 BHK1095
4 BHK2155
PENTHOUSE4117
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Park Square · 2 BHK, 3 BHK, 4 BHK, PENTHOUSE64278-155
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Pragesh Khanna
License CA/2004/34072
Vastu Srajan, Omaxe Heights, Gomtinagar, Lucknow
Engineer
Pankaj Srivastava
Anpee Tech Engineers, 3rd Floor, Shriram Tower, Hazratganj, Lucknow
Contractor
Anwarul Haque
B130, Sec C, Mahanagar Lucknow
Sr.Development work declared to RERA
1Demarcation of Plots
FOUNDATION WORK IS UNDER PROCESS
2Boundary Wall
BOUNDARY WALL IS ALREADY THERE IN THE PREMISES.
3Road Work
Internal roads will be of approx. 20ft. width.
4Footpaths
There will be no footpaths.
5Water Supply Including Drinking Water Facilities
Proper water supply facility is provided through internal boring. The project is registered with jal kal vibhaag.
6Sewer System
Proper sewer system facility is provided through septic tank.
7Drain
Proper drain facility is provided through septic tank.
8Parks
No Parks faclility is available.
9Tree Planting
Lawns and Planting will be done.
10Design For Electric Supply Including Street Lighting
Electricity will be supplied through Transformer with capicity of 252 KW and same has been sanctioned by Madhyanchal Vidyut Vitran Nigam Ltd.
11Community Buildings
There no provision for the community building in the project.
12Treatment and Disposal System of Sewage and Sullage water
There is no facility for the Treatment and Disposal System of Sewage and Sullage water.
13Solid Waste Management And Disposal System
There is no facility for the Solid Waste Management And Disposal System
14Water Conservation System
For water conservation water recharge pits will be made as per layout plan.
15Energy Management System Including Use of Renewable Energy
There is no facility for the Energy Management System Including Use of Renewable Energy
16Fire Protection And Fire Safety System
various measures have taken for fire safety system like- 1. 6"/4" Dia suction deliver connection 2. Electric Pump 900 LPM 3. Disel Pump Cap 900 LPM 4. Electric Jocky Pump 180 LPM 5. Under ground and terrace tank for fire fighting 6. Fire extinguisher 7. Auto sprinkler
17Social Infrastructure And Other Public Amenities Including Public Health Services
Mini Bsketball Court and toddler swimming pool.
18Emergency Evacuation Services
For Emergency Evacuation service separate stair will be provided.
19Other Miscellaneous Work
Other Miscellaneous work will be done as per need of the project.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 10 Jan 2024.

Sanctioned by Lucknow Development Authority · 2,864 sqm of land · an approved plan of 1 block and 42 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MAP-2018100818495865322 Oct 201910 Jan 202410 Jan 202631 Dec 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Jun 2024.

#Granted fromExtended uptoNote
131 Dec 202330 Jun 2024Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4202864Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 201900821019170
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New14 Nov 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New20 Nov 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New20 Nov 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New20 Nov 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New20 Nov 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New30 Nov 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New30 Nov 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Nov 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New14 Dec 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New20 Nov 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 Nov 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New20 Nov 2019 ↗

Quarterly progress reports

12 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

12 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMJ LIFESPACES LLP
RolePromoter · current
RERA IDUPRERAPRM102072
PANABJFM4317Q
CIN / TANLKNM09619B
Registered addressNo 137, Manas Enclave, Indiranagar, Lucknow 226016
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
MJ LIFESPACES LLPBankINDUSAND BANKBranchMUNSHIPULIYA BRANCHA/C no.IFSCINDB0000750
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Park Square

Is Park Square RERA registered?

Yes. Park Square is registered with UPRERA under registration number UPRERAPRJ451261, registered on 24 Dec 2019. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Park Square?

The completion date filed with UPRERA is 30 Jun 2024. No completion certificate is on record yet.

Who is the builder of Park Square?

MJ LIFESPACES LLP is the promoter entity that filed Park Square with UPRERA (promoter RERA ID UPRERAPRM102072). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Park Square more time to complete?

UPRERA's record carries 1 completion extension for Park Square, the latest running to 30 Jun 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Park Square have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Park Square located?

Park Square is registered in Lucknow, as filed with UPRERA.

What configurations are available in Park Square?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, 4 BHK and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Park Square?

The approved unit plan filed with UPRERA runs from 78 to 155 m² of carpet area (about 835 to 1,670 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Park Square?

The approved unit plan describes 1 block and 42 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Park Square?

About 59 units per acre: 42 planned units across 0.71 acres (2,864 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗