Pushpanjali Upvan Extension is a RERA-registered residential project by P P Buildcon Private Limited in Mathura (RERA ID UPRERAPRJ9822). Registered with a completion deadline of 9 Mar 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ9822 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Mathura-Vrindavan Development Authority |
| Proposed start | 1 Jun 2017 |
| Original start | 1 Oct 2015 |
| Project duration | 46 months |
| Address | Mathura, Mathura |
| Tehsil | Mathura |
| Applicant type | Company |
| Applicant address | 2nd Floor, Pushpanjali Palace, Delhi Gate, Agra-282002 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated (2)
3 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 30 Oct 2017 |
| Original completion | 10 Sept 2020 |
| Revised completion | 9 Mar 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 4 Sept 2025 |
| Registration fee | ₹98,500 |
| Sanctioning authority | Mathura-Vrindavan Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Done |
| 2 | Boundary Wall Done |
| 3 | Road Work Done |
| 4 | Footpaths NA |
| 5 | Water Supply Including Drinking Water Facilities Done |
| 6 | Sewer System Done |
| 7 | Drain Work on Progress |
| 8 | Parks 50% Done |
| 9 | Tree Planting 50% Done |
| 10 | Design For Electric Supply Including Street Lighting Yet to be start |
| 11 | Community Buildings NA |
| 12 | Treatment and Disposal System of Sewage and Sullage water Yet to be start |
| 13 | Solid Waste Management And Disposal System Yet to be start |
| 14 | Water Conservation System Yet to be start |
| 15 | Energy Management System Including Use of Renewable Energy Yet to be start |
| 16 | Fire Protection And Fire Safety System NA |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 10 Sept 2020. 2 of them carry a revalidation.
Sanctioned by Mathura-Vrindavan Development Authority · 18,604 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 151/M-14-15 | 11 Sept 2015 | 10 Sept 2020 | — | 10 Sept 2020 | — | |
| 151/M-14-15 | 11 Sept 2015 | 10 Sept 2020 | 10 Sept 2020 | 10 Sept 2020 | 11 Sept 2015 | |
| 151/M-14-15 | 11 Sept 2015 | 10 Sept 2020 | 10 Sept 2023 | 9 Mar 2021 | 11 Sept 2015 |
| Document | File |
|---|---|
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 9 Mar 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 10 Sept 2020 | 9 Mar 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
5 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 125 | 20720 | — |
| 125k | 10360 | Khasra |
| 125k | 10360 | Khasra |
2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 19 Sept 2013.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 16961 | 19 Sept 2013 | self | — |
| 17079 | 20 Sept 2013 | self | — |
| Sale deed · 16961 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 17079 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 12 Aug 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 12 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | As per Plan |
| Fire safety (as filed with RERA) | As per Plan |
| Health service | Available with in 1-3 Km |
| Renewable energy | As per Plan |
| Other facilities | Park |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | P P Buildcon Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM18610 |
| PAN | AADCP3077G |
| CIN / TAN | U45203UP2003PTC028001 |
| Name of chairman | Mr Mayank Agarwal |
| Registered address | 2nd Floor, Pushpanjali Palace, Delhi Gate, Agra-282002 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Mathura
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | P P Buildcon Private LimitedBankHDFC Bank LimitedBranchSanjay Place, AgraA/C no.IFSCHDFC0000121 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
Common questions about Pushpanjali Upvan Extension
Is Pushpanjali Upvan Extension RERA registered?
Yes. Pushpanjali Upvan Extension is registered with UPRERA under registration number UPRERAPRJ9822, registered on 30 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Pushpanjali Upvan Extension been completed?
UPRERA still lists Pushpanjali Upvan Extension as Registered, so it is not shown as completed here. A completion certificate dated 4 Sept 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Pushpanjali Upvan Extension?
P P Buildcon Private Limited is the promoter entity that filed Pushpanjali Upvan Extension with UPRERA (promoter RERA ID UPRERAPRM18610). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Pushpanjali Upvan Extension more time to complete?
UPRERA's record carries 1 completion extension for Pushpanjali Upvan Extension, the latest running to 9 Mar 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Pushpanjali Upvan Extension have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Pushpanjali Upvan Extension located?
Pushpanjali Upvan Extension is registered in Mathura, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗