Registered11 Aug 2017
Revised19 Dec 2022
Promised31 Dec 2022
Today4 Aug 2026

Timeline

Promised completion31 Dec 2022
Revised completion19 Dec 2022
Actual completion
Possession delay43 mo delay

Registration & Cost Details

Registration fee (in ₹)₹49,500
Project cost (in ₹ Lakhs)₹7005-78 Lakhs
Project duration66 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jan 2018

Inventory

Total units126
Unit TypeUnitsCarpet Area (sqm)
2 BHK2173.45
3 BHK4288.77
4 BHK63104.99

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile8130631318
Emailrera@irwo.net
Coordinator9415245828
AddressRailway Offices complex shivaji Bridge, behind shanker market New Delhi 110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2
2020-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
SANCTION AWAITED4 Aug 201719 Dec 202219 Dec 2022
56620 Dec 201719 Dec 202219 Dec 2022
56620 Dec 201719 Dec 202219 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
452950
465930
452950Khasra
465930Khasra

Approved Unit Plan

Unit plan rows on file33
Total flats (sum of rows)126
BlocksBLOCK-1
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2111319 Nov 2013

Frequently Asked Questions

What is the RERA registration number of RAIL VIHAR GROUP HOUSING SCHEME PHASE IV?

The RERA registration number of RAIL VIHAR GROUP HOUSING SCHEME PHASE IV is UPRERAPRJ8170, as recorded on the UP-RERA portal.

What is the RERA status of RAIL VIHAR GROUP HOUSING SCHEME PHASE IV?

As reported by UP-RERA, the status of RAIL VIHAR GROUP HOUSING SCHEME PHASE IV is "Registered".

Where is RAIL VIHAR GROUP HOUSING SCHEME PHASE IV located?

As reported to UP-RERA, RAIL VIHAR GROUP HOUSING SCHEME PHASE IV is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

When will RAIL VIHAR GROUP HOUSING SCHEME PHASE IV be completed?

The latest completion date reported to UP-RERA for RAIL VIHAR GROUP HOUSING SCHEME PHASE IV is 19 Dec 2022.

Is RAIL VIHAR GROUP HOUSING SCHEME PHASE IV delayed?

Measured against the latest completion date reported to UP-RERA, RAIL VIHAR GROUP HOUSING SCHEME PHASE IV is 43 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026