Rajniwas Residency is a RERA-registered residential project by Rajniwas Realtors LLP in Prayagraj (RERA ID UPRERAPRJ6245). Registered with a completion deadline of 29 Jun 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ6245 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Allahabad Development Authority |
| Proposed start | 1 Jan 2016 |
| Original start | 3 Feb 2014 |
| Project duration | 66 months |
| Address | Allahabad **, Prayagraj |
| Tehsil | Allahabad ** |
| Applicant type | Partnership Firm |
| Applicant address | Rajniwas Residency Apartments, 22 Sarojini Naidu Marg, Allahabad 211001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
128/1 Pra a (Bhavan) Zone 1/Revised/10-11
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 10 Aug 2017 |
| Original completion | 31 Dec 2019 |
| Revised completion | 29 Jun 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 24 Jul 2021 |
| Registration fee | ₹21,000 |
| Sanctioning authority | Allahabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK28 56%
- 4 BHK14 28%
- 1 BHK4 8%
- 2 BHK4 8%
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 14 | 165-223 |
| 3 BHK | 28 | 109-130 |
| 1 BHK | 4 | 40 |
| 2 BHK | 4 | 85 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| B · 4 BHK, 3 BHK | 6 | 36 | 109-166 |
| D · 1 BHK, 2 BHK, 3 BHK | 4 | 12 | 40-122 |
| Tower C · OTHER, 4 BHK | 3 | 2 | 223 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots NA |
| 2 | Boundary Wall MADE |
| 3 | Road Work To be completed within time |
| 4 | Footpaths NA |
| 5 | Water Supply Including Drinking Water Facilities Boring of tubewell completed. Overhead tanks to be completed within time |
| 6 | Sewer System 70% completed. Balance to be completed within time |
| 7 | Drain To be completed within time |
| 8 | Parks To be completed within time |
| 9 | Tree Planting To be completed within time |
| 10 | Design For Electric Supply Including Street Lighting To be completed within time |
| 11 | Community Buildings To be completed within time |
| 12 | Treatment and Disposal System of Sewage and Sullage water To be completed within time |
| 13 | Solid Waste Management And Disposal System To be completed within time |
| 14 | Water Conservation System To be completed within time |
| 15 | Energy Management System Including Use of Renewable Energy To be completed within time |
| 16 | Fire Protection And Fire Safety System To be completed within time |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services To be completed within time |
| 18 | Emergency Evacuation Services To be completed within time |
| 19 | Other Miscellaneous Work To be completed within time |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 2 Feb 2019.
Sanctioned by Allahabad Development Authority · 3,200 sqm of land · an approved plan of 3 blocks and 50 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 128/1 Pra a (Bhavan) Zone 1/Revised/10-11 | 3 Feb 2014 | 2 Feb 2019 | 2 Feb 2022 | 31 Dec 2019 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 29 Jun 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Dec 2019 | 30 Dec 2020 | — |
| 2 | 30 Dec 2020 | 29 Jun 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
15 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| Nazul Bhukhand Sankhya 15 Thornhill Road, Settleme | 6150 | — |
| Bahi Sankhya 1 Zild Sankhya 6158, page no. 201 to | 3146.289 | Plot |
| Lease deed · Bahi Sankhya 1 Zild Sankhya 6158, page no. 201 to 226 on serial no. 5130 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 28 Jul 2018 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 25 Jul 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 26 Jul 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 26 Jul 2018 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 26 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 28 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 31 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 31 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 31 Jul 2018 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | Yes, as per norms |
| Fire safety (as filed with RERA) | Yes, As per norms |
| Renewable energy | Yes, Solar water heating will be installed |
| Other facilities | Community hall, swimming pool, central lawn |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
6 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Rajniwas Realtors LLP |
| Role | Promoter · current |
| RERA ID | UPRERAPRM3993 |
| PAN | AANFR2459K |
| CIN / TAN | AAA-4446 |
| Registered address | Rajniwas Residency Apartments, 22 Sarojini Naidu Marg, Allahabad 211001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Prayagraj
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Rajniwas Realtors LLPBankCentral Bank of IndiaBranchZero RoadA/C no.IFSCCBIN0281377 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about Rajniwas Residency
Is Rajniwas Residency RERA registered?
Yes. Rajniwas Residency is registered with UPRERA under registration number UPRERAPRJ6245, registered on 10 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Rajniwas Residency been completed?
UPRERA still lists Rajniwas Residency as Registered, so it is not shown as completed here. A completion certificate dated 24 Jul 2021 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Rajniwas Residency?
Rajniwas Realtors LLP is the promoter entity that filed Rajniwas Residency with UPRERA (promoter RERA ID UPRERAPRM3993). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Rajniwas Residency more time to complete?
UPRERA's record carries 2 completion extensions for Rajniwas Residency, the latest running to 29 Jun 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Rajniwas Residency have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Rajniwas Residency located?
Rajniwas Residency is registered in Prayagraj, as filed with UPRERA.
What configurations are available in Rajniwas Residency?
The unit plan filed with UPRERA lists 4 BHK, 3 BHK, OTHER, 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Rajniwas Residency?
The approved unit plan filed with UPRERA runs from 40 to 223 m² of carpet area (about 431 to 2,397 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Rajniwas Residency?
The approved unit plan describes 3 blocks and 50 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Rajniwas Residency?
About 63 units per acre: 50 planned units across 0.79 acres (3,200 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗