Timeline Bar
Registered20 Mar 2026
Today4 Aug 2026
Promised11 Dec 2030
Timeline
Promised completion11 Dec 2030
Revised completion11 Dec 2030
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹1,65,500
Project cost (in ₹ Lakhs)₹913 Lakhs
Project duration59 months
Project categoryResidential
LocalityMAUJA AKBARPUR BANGER
Original start date—
Proposed start date15 Jan 2026
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile8859796209
Emailgovind02agrawal@gmail.com
Coordinator9897676006
Address01, Guru Kripa Villas, Saray Aazmabad, Near Kusum Vatika,Mathura,281004
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| Plotted Resi development/Plotted Housing/07665/MVDA/LD/25-26/0512/12122025 | 12 Dec 2025 | 11 Dec 2030 | 11 Dec 2030 | 10 Dec 2033 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 153(Mi),155/2, Mauja Akbarpur, mathura | 6959 | Khasra |
| 168/2,155/2,153/1, Mauja Akbarpur, Mathura | 2260 | Khasra |
| 153/1(Mi), 155/2, Mauja Akbarpur, Mathura | 3349.50 | Khasra |
| 165(Mi), Mauja Akbarpur, Mathura | 1092 | Khasra |
| 166 , Mauja Akbnarpur, Mathura | 2470 | Khasra |
| 166, Mauja Akbarpur, Mathura | 2470 | Khasra |
| 166, Mauja Akbarpur, Mathura | 2470 | Khasra |
| 167, Mauja Akbarpur, Mathura | 6880 | Khasra |
| 168/2, Mauja Akbarpur, Mathura | 5750.50 | Khasra |
| 168/2,Mauja Akbarpur, Mathura | 5750.50 | Khasra |
| 169(Mi), Mauja Akbarpur, Mathura | 2140 | Khasra |
Frequently Asked Questions
What is the RERA registration number of RESIDENCY HIGHWAY?
The RERA registration number of RESIDENCY HIGHWAY is UPRERAPRJ116197, as recorded on the UP-RERA portal.
What is the RERA status of RESIDENCY HIGHWAY?
As reported by UP-RERA, the status of RESIDENCY HIGHWAY is "Registered".
Where is RESIDENCY HIGHWAY located?
As reported to UP-RERA, RESIDENCY HIGHWAY is located at RESIDENCY HIGHWAY , KHASRA NO. 155/2, 165, 166, 167, 168/2, 169(Mi), MAUJA AKBARPUR BANGER, Chhata, Mathura, Uttar Pradesh.
When will RESIDENCY HIGHWAY be completed?
The latest completion date reported to UP-RERA for RESIDENCY HIGHWAY is 11 Dec 2030.
Is RESIDENCY HIGHWAY delayed?
Measured against the latest completion date reported to UP-RERA, RESIDENCY HIGHWAY is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026