RRPS -04/2020 is a RERA-registered residential project by Yamuna Expressway Industrial devlopment Authority in Gautam Budh Nagar (RERA ID UPRERAPRJ205883). Registered with a completion deadline of 31 Dec 2025.
RERA status as reported: Registered.Construction progress
Construction stayed at 0% across 18 consecutive filed quarters (Jan–Mar 2021 to Apr–Jun 2025). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ205883 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Yamuna Expressway Authority |
| Proposed start | 1 Jan 2021 |
| Project duration | 60 months |
| Address | Gautam Budh Nagar |
| Applicant type | Competent authority |
| Applicant address | 1st Floor , Commercial Complex , Block-P2, Sec- Omega 1, Greater Noida - 201308 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
PLNG/DS-05/N-94
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 18 Aug 2020 |
| Original completion | 31 Dec 2025 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹10,44,000 |
| Sanctioning authority | Yamuna Expressway Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots After development work , Authority will demarcate the all plots. |
| 2 | Boundary Wall After Development work , Authority will provide boundary wall in that sector. |
| 3 | Road Work Authority will provide roads in front of every plots in that whole sector . As per norms Authority will provide roads of bituminous concrete. |
| 4 | Footpaths Authority will provide footpaths in the plots in that whole sector . |
| 5 | Water Supply Including Drinking Water Facilities Authority will provide water facilities through Over Head Tank (OHT) in every plots in that whole sector. |
| 6 | Sewer System Authority will provide a chamber and manhole in plots in that whole sector. |
| 7 | Drain Authority will provide a better drainage system in that whole sector. |
| 8 | Parks Authority will provide a parks according to the layout plan and plant the trees in that whole sector. |
| 9 | Tree Planting Authority will provide a parks according to the layout plan and plant the trees in that whole sector. |
| 10 | Design For Electric Supply Including Street Lighting Authority will provide Electricity in that whole sector. |
| 11 | Community Buildings Authority has a shopping complex in that sector 22-D. |
| 12 | Treatment and Disposal System of Sewage and Sullage water 2 MLD STP work is in progress In that sector. |
| 13 | Solid Waste Management And Disposal System Authority manages all types of solid waste and gives better disposal system. |
| 14 | Water Conservation System UGR Work is in progress to provide water supply in that whole sector. |
| 15 | Energy Management System Including Use of Renewable Energy it is possible only when development work in that sector will complete. |
| 16 | Fire Protection And Fire Safety System Provision as per norms. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Provision as per norms. |
| 18 | Emergency Evacuation Services Provision as per norms. |
| 19 | Other Miscellaneous Work nill |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 31 Dec 2025.
Sanctioned by Yamuna Expressway Authority · 2,07,728 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| PLNG/DS-05/N-94 | 22 Jan 2020 | 31 Dec 2025 | 31 Dec 2025 | 31 Dec 2025 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
Land & documents
21 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| Block-C, D, Sector-22D | 207728 | Plot |
| Allotment letter from the authority · PLNG/DS-05/N-94 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Khatauni extract · 1422-1427 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 16 Aug 2020 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 13 Aug 2020 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 13 Aug 2020 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 16 Aug 2020 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 16 Aug 2020 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 16 Aug 2020 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 16 Aug 2020 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 16 Aug 2020 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 17 Aug 2020 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 13 Aug 2020 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 17 Aug 2020 ↗ |
Quarterly progress reports
18 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
18 quarterly progress reports are on file with UPRERA, covering 2020-Q4 to 2025-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Yamuna Expressway Industrial devlopment Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM14529 |
| PAN | AAALT0341D |
| CIN / TAN | MRTT00283D |
| Registered address | 1st Floor , Commercial Complex , Block-P2, Sec- Omega 1, Greater Noida - 201308 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | YAMUNA EXPRESSWAY INDUSTRIAL DEVELOPMENT AUTHORITYBankICICIBranchOMEGA - ONEA/C no.IFSCICIC0002183 |
What has changed on this record
6 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 337 (Under Registration - 1 ) → 338 (Under Registration - 2 ) changed in Estanzo’s record | 15 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 0 ) → 337 (Under Registration - 1 ) changed in Estanzo’s record | 3 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 1 ) → 336 (Under Registration - 0 ) changed in Estanzo’s record | 23 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 336 (Under Registration - 3 ) → 336 (Under Registration - 1 ) changed in Estanzo’s record | 21 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 335 (Under Registration - 2 ) → 336 (Under Registration - 3 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 334 (Under Registration - 1 ) → 335 (Under Registration - 2 ) changed in Estanzo’s record | 16 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 15 Oct 2026 · 6 movements on record |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about RRPS -04/2020
Is RRPS -04/2020 RERA registered?
Yes. RRPS -04/2020 is registered with UPRERA under registration number UPRERAPRJ205883, registered on 18 Aug 2020. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for RRPS -04/2020?
The completion date filed with UPRERA is 31 Dec 2025. No completion certificate is on record yet.
Who is the builder of RRPS -04/2020?
Yamuna Expressway Industrial devlopment Authority is the promoter entity that filed RRPS -04/2020 with UPRERA (promoter RERA ID UPRERAPRM14529). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does RRPS -04/2020 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is RRPS -04/2020 located?
RRPS -04/2020 is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗