SAVY VILLE DE is a RERA-registered residential project by ASCENT BUILDTECH PVT. LTD. in Ghaziabad (RERA ID UPRERAPRJ10792). Registered with a completion deadline of 27 Mar 2023. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ10792 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Ghaziabad Development Authority |
| Proposed start | 1 Jul 2015 |
| Original start | 1 Sept 2013 |
| Project duration | 93 months |
| Address | Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Company |
| Applicant address | 39 G, POCKET A-1, MAYUR VIHAR, PHASE -III, DELHI-110092 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
82/ZONE-1/G.H./13-14
Registered with RERA
- valid to
Permit revalidated
562/PARVARTAN ZONE1/2018
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 15 Aug 2017 |
| Original completion | 30 Dec 2020 |
| Revised completion | 27 Mar 2023 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,06,500 |
| Sanctioning authority | Ghaziabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK240 66%
- 2 BHK122 34%
- STUDIO1 <1%
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 122 | 50-68 |
| STUDIO | 1 | 17 |
| 3 BHK | 240 | 66-86 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| B1 · 2 BHK, STUDIO, 3 BHK | 15 | 89 | 17-67 |
| B2 · 3 BHK, 2 BHK | 15 | 119 | 50-66 |
| C · 3 BHK, 2 BHK | 15 | 155 | 65-86 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots PROPOSED & 55% COMPLETED |
| 2 | Boundary Wall PROPOSED & 50% COMPLETED |
| 3 | Road Work PROPOSED & 50% COMPLETED |
| 4 | Footpaths PROPOSED & 50% COMPLETED |
| 5 | Water Supply Including Drinking Water Facilities PROPOSED IN TOWER C & COMPLETED IN TOWER B1B2 |
| 6 | Sewer System PROPOSED IN TOWER C & COMPLETED IN TOWER B1B2 |
| 7 | Drain PROPOSED |
| 8 | Parks PROPOSED IN BETWEEN THE SOCIETY & WORK IS IN PROGRESS |
| 9 | Tree Planting PROPOSED |
| 10 | Design For Electric Supply Including Street Lighting PROPOSED |
| 11 | Community Buildings PROPOSED IN GROUND FLOOR OF TOWER C |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP IS OPERATIONAL |
| 13 | Solid Waste Management And Disposal System ORGANIC WASTE CONVERTER IS PROPOSED |
| 14 | Water Conservation System PROPOSED |
| 15 | Energy Management System Including Use of Renewable Energy NA |
| 16 | Fire Protection And Fire Safety System PROPOSED & COMPLETED IN TOWER B1B2 |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services AS PER NORMS |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 9 May 2019. It carries a revalidation, valid to 4 Jan 2023.
Sanctioned by Ghaziabad Development Authority · 20,247 sqm of land · an approved plan of 3 blocks and 363 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 82/ZONE-1/G.H./13-14 | 9 May 2014 | 9 May 2019 | 4 Jan 2023 | 30 Dec 2020 | 4 Jan 2018 valid to 4 Jan 2023 as 562/PARVARTAN ZONE1/2018 |
| Document | File |
|---|---|
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
UPRERA’s record carries 3 completion extensions for this project, the latest running to 27 Mar 2023.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 30 Dec 2020 | 29 Jun 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 29 Jun 2021 | 28 Jun 2022 | — |
| 3 | 28 Jun 2022 | 27 Mar 2023 | — |
Land & documents
14 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 990 | 13344 | — |
| 992 | 1410.25 | — |
| 993 | 1270 | — |
| 994 | 1300 | — |
| 995 | 1300 | — |
| 996 | 1629 | — |
5 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 25 Nov 2005.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 2194 | 1 Apr 2008 | self | — |
| 5038 | 30 Jun 2008 | self | — |
| 9595 | 25 Nov 2005 | self | — |
| 1128 | 12 Feb 2007 | self | — |
| 1128 | 12 Feb 2007 | self | — |
| Registry document · 9595 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Electricity supply plan How the project proposed to supply power, as filed at registration. | Old | 14 Aug 2017 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | Old | 14 Aug 2017 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | Old | 14 Aug 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 14 Aug 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 14 Aug 2017 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | Old | 14 Aug 2017 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | Old | 14 Aug 2017 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | Old | 14 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AS PER NORMS |
| Fire safety (as filed with RERA) | AS PER NORMS |
| Renewable energy | AS PER NORMS |
| Other facilities | IGL PIPELINE |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
1 filed report
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
1 quarterly progress report is on file with UPRERA, for 2022-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | ASCENT BUILDTECH PVT. LTD. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM4236 |
| PAN | AAGCA9322G |
| CIN / TAN | U74120DL2008PTC175481 |
| Name of chairman | SURESH GOGIA |
| Registered address | 39 G, POCKET A-1, MAYUR VIHAR, PHASE -III, DELHI-110092 |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | ASCENT BUILDTECH PVT LTDBankORIENTAL BANK OF COMMERCEBranchVASUNDHARA ENCLAVE DELHIA/C no.IFSCORBC0100844 |
What has changed on this record
2 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Default-on-QPR flag | false → true changed in Estanzo’s record | 16 Aug 2026 |
| RERA status | abeyance → registered changed in Estanzo’s record | 16 Aug 2026 |
| RERA status | changed in Estanzo’s record · 16 Aug 2026 |
Common questions about SAVY VILLE DE
Is SAVY VILLE DE RERA registered?
Yes. SAVY VILLE DE is registered with UPRERA under registration number UPRERAPRJ10792, registered on 15 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for SAVY VILLE DE?
The completion date filed with UPRERA is 27 Mar 2023. No completion certificate is on record yet.
Who is the builder of SAVY VILLE DE?
ASCENT BUILDTECH PVT. LTD. is the promoter entity that filed SAVY VILLE DE with UPRERA (promoter RERA ID UPRERAPRM4236). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Why does SAVY VILLE DE show "default on QPR"?
UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.
Has UPRERA granted SAVY VILLE DE more time to complete?
UPRERA's record carries 3 completion extensions for SAVY VILLE DE, the latest running to 27 Mar 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does SAVY VILLE DE have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is SAVY VILLE DE located?
SAVY VILLE DE is registered in Ghaziabad, as filed with UPRERA.
What configurations are available in SAVY VILLE DE?
The unit plan filed with UPRERA lists 2 BHK, STUDIO and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in SAVY VILLE DE?
The approved unit plan filed with UPRERA runs from 17 to 86 m² of carpet area (about 187 to 924 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in SAVY VILLE DE?
The approved unit plan describes 3 blocks and 363 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is SAVY VILLE DE?
About 73 units per acre: 363 planned units across 5.00 acres (20,247 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗