Timeline Bar

Registered31 Jul 2017
Promised31 Dec 2021
Revised30 Jun 2022
Today4 Aug 2026

Timeline

Promised completion31 Dec 2021
Revised completion30 Jun 2022
Actual completion
Possession delay49 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,00,000
Project cost (in ₹ Lakhs)₹21,000 Lakhs
Project duration96 months
Project categoryResidential
Locality
Original start date1 Apr 2016
Proposed start date1 Apr 2016

Inventory

Total units348
Unit TypeUnitsCarpet Area (sqm)
3 BHK348103.492–125.88

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8800691111
Emailhelpdesk@sethigroup.in
Coordinator8800691111
Address2nd Floor, Angel Mega Mall, Kaushambhi, Ghaziabad

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q144.3%
2020-Q244.3%
2020-Q344.3%
2020-Q444.3%
2021-Q144.3%
2021-Q244.3%
2021-Q344.3%
2021-Q444.3%
2022-Q1
2022-Q244.3%
2022-Q344.3%
2022-Q444.3%
2023-Q144.3%
2023-Q244.3%
2023-Q346.5%
2023-Q448.4%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1426/80422 Apr 202022 Apr 202030 Jun 202230 Jun 2022

Land Parcels

Khasra No.AreaPlot Type
SC-1/A-456652.5Plot

Approved Unit Plan

Unit plan rows on file87
Total flats (sum of rows)348
BlocksA, B, L, M
Floor types3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
DOCUMENT NO. 4372 RECORDED IN BAHI NO. 1 AND JILD17 Apr 2013

Frequently Asked Questions

What is the RERA registration number of SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN?

The RERA registration number of SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN is UPRERAPRJ6357, as recorded on the UP-RERA portal.

What is the RERA status of SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN?

As reported by UP-RERA, the status of SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN is "Registered".

Where is SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN located?

As reported to UP-RERA, SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN be completed?

The latest completion date reported to UP-RERA for SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN is 30 Jun 2022.

Is SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN delayed?

Measured against the latest completion date reported to UP-RERA, SETHI VENICE PHASE I (TOWER A , B , L , M , CONVEN is 49 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026