Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ2513
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start11 Oct 2013
Original start11 Oct 2013
Project duration102 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant address308-309, 3rd Floor, Salcon Aurum, Plot No.4 Jasola District Centr, Sukhdev Vihar, South Delhi NEW DELHI-110025
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    116/MP/Zone-3/17

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. Completion certificate filed

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Jul 2017
Original completion30 Mar 2021
Revised completion29 Mar 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary12 Mar 2022
Registration fee₹1,29,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors970 · 7 · 20 (units from plan)
Homes · commercial units950 · 20 (shops and offices filed in the same plan)
  • 2 BHK836 86%
  • 3 BHK114 12%
  • SHOP20 2%
ConfigurationUnitsCarpet area
2 BHK83646-65
3 BHK11468-77
SHOP205-40
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 2 BHK1920946-61
B · 2 BHK1920946-61
C · 2 BHK1915246-65
D · 2 BHK1915255-65
E · 3 BHK, 2 BHK1915255-77
F · 3 BHK145668-75
G · 3 BHK, SHOP6405-75
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Deepak Mehta and Associates
License COA/87/10840
Plot No.16, Abhishek Plaza, Mayur Vihar Phase 2, Delhi
Engineer
KEEN Associates Pvt Ltd.
H-53, Sector 63, Noida
Contractor
Ralhan Construction Pvt Ltd.
S-44, Greater Kailash 2, New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
Done.
2Boundary Wall
Yes. Completed
3Road Work
Internal Roads within boundry of the project to be constructed by us. External roads in scope of the Ghaziabad Development Authority (GDA)
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
Yes.
6Sewer System
Yes. External sewerage system in scope of GDA
7Drain
Internal Drains completed. External drainage system in scope of GDA
8Parks
Yes.
9Tree Planting
Yes as per norms
10Design For Electric Supply Including Street Lighting
Yes for the common areas
11Community Buildings
Club
12Treatment and Disposal System of Sewage and Sullage water
Yes. External system and final disposal in scope of GDA
13Solid Waste Management And Disposal System
Garbage collection and disposal as per norms. (Part of Maintenance)
14Water Conservation System
Yes. Provision of Rain Water Harvesting
15Energy Management System Including Use of Renewable Energy
Single point electric connection from UPPCL and further distribution through Prepaid Metering System
16Fire Protection And Fire Safety System
As per norms.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Multipurpose Hall, Gym, Indoor Games etc.
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

3 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1GAURAV JAINUPRERAAGT11716
2Hem Raj SinghUPRERAAGT13355
3Vaibhav NarayanUPRERAAGT11713
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 30 Mar 2022.

Sanctioned by Ghaziabad Development Authority · 24,843 sqm of land · an approved plan of 7 blocks and 970 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
116/MP/Zone-3/1731 Mar 201730 Mar 202230 Mar 202530 Mar 2021
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 29 Mar 2022.

#Granted fromExtended uptoNote
130 Mar 202129 Sept 2021Six months extension in view of force majeure caused by covid-19 pandemic
229 Sept 202129 Mar 2022—

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
145, 199, 14328483—
143631Khasra
14519979Khasra
1994230Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

5 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 5 Mar 2012.

Registry no.DateTypeArea
23385 Mar 2012self—
23325 Mar 2012self—
316923 Mar 2012self—
778917 Jun 2015self—
779017 Jun 2015self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 3169
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2338
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2332
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7790
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7789
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New5 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Jul 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New6 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New6 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New6 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old26 Oct 2017 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old26 Oct 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterYes
Fire safety (as filed with RERA)Yes
Renewable energyAs per code

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSG ESTATES PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM1978
PANAAACS2843L
CIN / TANDELS05587B
Name of chairmanSUBHASH GUPTA
Registered address308-309, 3rd Floor, Salcon Aurum, Plot No.4 Jasola District Centr, Sukhdev Vihar, South Delhi NEW DELHI-110025
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
SG Estates Ltd.BankHDFC BankBranch209-214, Kailash Building, 26, KG Marg, New DelhiA/C no.IFSCHDFC0000003
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about SG Grand

Is SG Grand RERA registered?

Yes. SG Grand is registered with UPRERA under registration number UPRERAPRJ2513, registered on 28 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has SG Grand been completed?

UPRERA still lists SG Grand as Registered, so it is not shown as completed here. A completion certificate dated 12 Mar 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of SG Grand?

SG ESTATES PRIVATE LIMITED is the promoter entity that filed SG Grand with UPRERA (promoter RERA ID UPRERAPRM1978). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted SG Grand more time to complete?

UPRERA's record carries 2 completion extensions for SG Grand, the latest running to 29 Mar 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does SG Grand have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SG Grand located?

SG Grand is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in SG Grand?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SG Grand?

The approved unit plan filed with UPRERA runs from 5 to 77 m² of carpet area (about 51 to 826 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SG Grand?

The approved unit plan describes 7 blocks and 970 units of which 950 are homes and 20 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SG Grand?

About 158 units per acre: 970 planned units across 6.14 acres (24,843 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗