Timeline Bar
Registered14 Aug 2017
Promised14 Dec 2022
Completed30 Oct 2025
Timeline
Promised completion14 Dec 2022
Revised completion14 Dec 2022
Actual completion30 Oct 2025
Possession delay35 mo delay
Registration & Cost Details
Registration fee (in ₹)₹73,000
Project cost (in ₹ Lakhs)₹750 Lakhs
Project duration101 months
Project categoryResidential
Locality—
Original start date15 Jan 2015
Proposed start date15 Jan 2015
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9837093003
Emailbaijnathagarwalsteels@gmail.com
Coordinator9837068326
AddressS 9 MARUTI PLAZA SANJAY PALACE AGRA
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 164\BFT\08\14-15 | 23 Jan 2015 | 22 Jan 2020 | 14 Dec 2022 | 22 Jan 2023 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 762 MAUJA ROHTA | 13630 | — |
| 762 MAUJA ROHTA | 13630 | Khasra |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 2231 | 24 Feb 2012 | — | — |
Frequently Asked Questions
What is the RERA registration number of SHREE DWARIKA?
The RERA registration number of SHREE DWARIKA is UPRERAPRJ9609, as recorded on the UP-RERA portal.
What is the RERA status of SHREE DWARIKA?
As reported by UP-RERA, the status of SHREE DWARIKA is "Registered".
Where is SHREE DWARIKA located?
As reported to UP-RERA, SHREE DWARIKA is located at Agra, Agra, Uttar Pradesh.
Is SHREE DWARIKA completed?
As reported to UP-RERA, SHREE DWARIKA was completed on 30 Oct 2025.
Is SHREE DWARIKA delayed?
Measured against the latest completion date reported to UP-RERA, SHREE DWARIKA is 35 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026