Estanzo

Timeline Bar

Registered14 Aug 2017
Promised14 Dec 2022
Completed30 Oct 2025

Timeline

Promised completion14 Dec 2022
Revised completion14 Dec 2022
Actual completion30 Oct 2025
Possession delay35 mo delay

Registration & Cost Details

Registration fee (in ₹)₹73,000
Project cost (in ₹ Lakhs)₹750 Lakhs
Project duration101 months
Project categoryResidential
Locality
Original start date15 Jan 2015
Proposed start date15 Jan 2015

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9837093003
Emailbaijnathagarwalsteels@gmail.com
Coordinator9837068326
AddressS 9 MARUTI PLAZA SANJAY PALACE AGRA

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
164\BFT\08\14-1523 Jan 201522 Jan 202014 Dec 202222 Jan 2023

Land Parcels

Khasra No.AreaPlot Type
762 MAUJA ROHTA13630
762 MAUJA ROHTA13630Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
223124 Feb 2012

Frequently Asked Questions

What is the RERA registration number of SHREE DWARIKA?

The RERA registration number of SHREE DWARIKA is UPRERAPRJ9609, as recorded on the UP-RERA portal.

What is the RERA status of SHREE DWARIKA?

As reported by UP-RERA, the status of SHREE DWARIKA is "Registered".

Where is SHREE DWARIKA located?

As reported to UP-RERA, SHREE DWARIKA is located at Agra, Agra, Uttar Pradesh.

Is SHREE DWARIKA completed?

As reported to UP-RERA, SHREE DWARIKA was completed on 30 Oct 2025.

Is SHREE DWARIKA delayed?

Measured against the latest completion date reported to UP-RERA, SHREE DWARIKA is 35 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026