Skyline Plaza 3 is a RERA-registered commercial project by Kunal Infraproject Pvt Ltd in Lucknow (RERA ID UPRERAPRJ5766). Registered with a completion deadline of 4 Jun 2022.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ5766 |
| Project category | Commercial |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 5 Jan 2013 |
| Original start | 5 Jan 2013 |
| Project duration | 113 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Company |
| Applicant address | 2nd Floor Super Shopping Centre, Faizabad Road, Lucknow |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
*
Registered with RERA
2 building permits sanctioned
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 10 Aug 2017 |
| Original completion | 5 Dec 2021 |
| Revised completion | 4 Jun 2022 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 1 Apr 2022 |
| Registration fee | ₹81,000 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 1 BHK273 91%
- 2 BHK26 9%
- SHOP2 1%
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 2 | 1,735-1,968 |
| 1 BHK | 273 | 28-57 |
| 2 BHK | 26 | 67-75 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Skyline Plaza III · OTHER, SHOP, 1 BHK, 2 BHK | 18 | 301 | 28-75 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Done |
| 2 | Boundary Wall Done |
| 3 | Road Work Done |
| 4 | Footpaths Done |
| 5 | Water Supply Including Drinking Water Facilities Done |
| 6 | Sewer System NA |
| 7 | Drain Done |
| 8 | Parks NA |
| 9 | Tree Planting NA |
| 10 | Design For Electric Supply Including Street Lighting NA |
| 11 | Community Buildings NA |
| 12 | Treatment and Disposal System of Sewage and Sullage water NA |
| 13 | Solid Waste Management And Disposal System NA |
| 14 | Water Conservation System NA |
| 15 | Energy Management System Including Use of Renewable Energy NA |
| 16 | Fire Protection And Fire Safety System Done |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work To be done |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 30 Jul 2025.
Sanctioned by Lucknow Development Authority · 7,092 sqm of land · an approved plan of 1 block and 301 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| * | 30 Jul 2017 | 29 Jul 2022 | 29 Jul 2022 | 5 Dec 2021 | |
| 43163 | 30 Jul 2020 | 30 Jul 2025 | 29 Jul 2028 | 4 Jun 2022 | |
| 43163 | 30 Jul 2020 | 30 Jul 2025 | 29 Jul 2028 | 3 Jun 2022 |
UPRERA’s record carries 1 completion extension for this project, running to 4 Jun 2022.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 5 Dec 2021 | 4 Jun 2022 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
3 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 1258, 1259 | 7092 | Khasra |
| Registry document · na The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 30 Jul 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 30 Jul 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | Under construction |
| Fire safety (as filed with RERA) | Under construction |
| Health service | Under construction |
| Renewable energy | Under construction |
| Other facilities | Under construction |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
3 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
3 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Kunal Infraproject Pvt Ltd |
| Role | Promoter · current |
| RERA ID | UPRERAPRM11012 |
| PAN | AAECK7570J |
| CIN / TAN | LKNK06595B |
| Name of chairman | Robin Goel |
| Registered address | 2nd Floor Super Shopping Centre, Faizabad Road, Lucknow |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | KUNAL INFRAPROJECT PVT LTDBankBANK OF INDIABranchPATRAKARPURAM LUCKNOWA/C no.IFSCBKID0006838 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about Skyline Plaza 3
Is Skyline Plaza 3 RERA registered?
Yes. Skyline Plaza 3 is registered with UPRERA under registration number UPRERAPRJ5766, registered on 10 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Skyline Plaza 3 been completed?
UPRERA still lists Skyline Plaza 3 as Registered, so it is not shown as completed here. A completion certificate dated 1 Apr 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Skyline Plaza 3?
Kunal Infraproject Pvt Ltd is the promoter entity that filed Skyline Plaza 3 with UPRERA (promoter RERA ID UPRERAPRM11012). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Skyline Plaza 3 more time to complete?
UPRERA's record carries 1 completion extension for Skyline Plaza 3, the latest running to 4 Jun 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Skyline Plaza 3 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Skyline Plaza 3 located?
Skyline Plaza 3 is registered in Lucknow, as filed with UPRERA.
What configurations are available in Skyline Plaza 3?
The unit plan filed with UPRERA lists OTHER, SHOP, 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Skyline Plaza 3?
The approved unit plan filed with UPRERA runs from 28 to 1,968 m² of carpet area (about 301 to 21,183 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Skyline Plaza 3?
The approved unit plan describes 1 block and 301 units of which 299 are homes and 2 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Skyline Plaza 3?
About 172 units per acre: 301 planned units across 1.75 acres (7,092 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗