Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ5766
Project categoryCommercial
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start5 Jan 2013
Original start5 Jan 2013
Project duration113 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant address2nd Floor Super Shopping Centre, Faizabad Road, Lucknow
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    *

  3. Registered with RERA

  4. 2 building permits sanctioned

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  9. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered10 Aug 2017
Original completion5 Dec 2021
Revised completion4 Jun 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary1 Apr 2022
Registration fee₹81,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors301 · 1 · 18 (units from plan)
Homes · commercial units299 · 2 (shops and offices filed in the same plan)
  • 1 BHK273 91%
  • 2 BHK26 9%
  • SHOP2 1%
ConfigurationUnitsCarpet area
SHOP21,735-1,968
1 BHK27328-57
2 BHK2667-75
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Skyline Plaza III · OTHER, SHOP, 1 BHK, 2 BHK1830128-75
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
*
License *
*
Engineer
AK GUPTA
GOMTINAGAR
Sr.Development work declared to RERA
1Demarcation of Plots
Done
2Boundary Wall
Done
3Road Work
Done
4Footpaths
Done
5Water Supply Including Drinking Water Facilities
Done
6Sewer System
NA
7Drain
Done
8Parks
NA
9Tree Planting
NA
10Design For Electric Supply Including Street Lighting
NA
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
NA
13Solid Waste Management And Disposal System
NA
14Water Conservation System
NA
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
Done
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
To be done
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 30 Jul 2025.

Sanctioned by Lucknow Development Authority · 7,092 sqm of land · an approved plan of 1 block and 301 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 4 Jun 2022.

#Granted fromExtended uptoNote
15 Dec 20214 Jun 2022Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

3 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1258, 12597092Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · na
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old30 Jul 2017 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old30 Jul 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterUnder construction
Fire safety (as filed with RERA)Under construction
Health serviceUnder construction
Renewable energyUnder construction
Other facilitiesUnder construction

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameKunal Infraproject Pvt Ltd
RolePromoter · current
RERA IDUPRERAPRM11012
PANAAECK7570J
CIN / TANLKNK06595B
Name of chairmanRobin Goel
Registered address2nd Floor Super Shopping Centre, Faizabad Road, Lucknow
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
KUNAL INFRAPROJECT PVT LTDBankBANK OF INDIABranchPATRAKARPURAM LUCKNOWA/C no.IFSCBKID0006838
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Skyline Plaza 3

Is Skyline Plaza 3 RERA registered?

Yes. Skyline Plaza 3 is registered with UPRERA under registration number UPRERAPRJ5766, registered on 10 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has Skyline Plaza 3 been completed?

UPRERA still lists Skyline Plaza 3 as Registered, so it is not shown as completed here. A completion certificate dated 1 Apr 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Skyline Plaza 3?

Kunal Infraproject Pvt Ltd is the promoter entity that filed Skyline Plaza 3 with UPRERA (promoter RERA ID UPRERAPRM11012). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Skyline Plaza 3 more time to complete?

UPRERA's record carries 1 completion extension for Skyline Plaza 3, the latest running to 4 Jun 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Skyline Plaza 3 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Skyline Plaza 3 located?

Skyline Plaza 3 is registered in Lucknow, as filed with UPRERA.

What configurations are available in Skyline Plaza 3?

The unit plan filed with UPRERA lists OTHER, SHOP, 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Skyline Plaza 3?

The approved unit plan filed with UPRERA runs from 28 to 1,968 m² of carpet area (about 301 to 21,183 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Skyline Plaza 3?

The approved unit plan describes 1 block and 301 units of which 299 are homes and 2 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Skyline Plaza 3?

About 172 units per acre: 301 planned units across 1.75 acres (7,092 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗