Estanzo

Timeline Bar

Registered29 Jul 2017
Promised30 Sept 2018
Today29 Jul 2026

Timeline

Promised completion30 Sept 2018
Revised completion30 Sept 2018
Actual completion
Possession delay94 mo delay

Registration & Cost Details

Registration fee (in ₹)₹70,500
Project cost (in ₹ Lakhs)₹820 Lakhs
Project duration19 months
Project categoryResidential
Locality
Original start date24 Mar 2017
Proposed start date24 Mar 2017

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9837089161
Emailashok.k.garg@gmail.com
Coordinator9837089161
Address37 Chippi Tank, Opp. M. Prakash Nursing Home Meerut 250002 UP

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
75024 Mar 201723 Mar 202230 Sept 2018
75024 Mar 201723 Mar 202230 Sept 2018
75024 Mar 201723 Mar 202230 Sept 2018

Land Parcels

Khasra No.AreaPlot Type
222M1390
223M3670
2247970
222M1390Khasra
223M3670Khasra
2247970Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
233512 Mar 2012

Frequently Asked Questions

What is the RERA registration number of SOUTH EXTENSION COLONY?

The RERA registration number of SOUTH EXTENSION COLONY is UPRERAPRJ4375, as recorded on the UP-RERA portal.

What is the RERA status of SOUTH EXTENSION COLONY?

As reported by UP-RERA, the status of SOUTH EXTENSION COLONY is "Registered".

Where is SOUTH EXTENSION COLONY located?

As reported to UP-RERA, SOUTH EXTENSION COLONY is located at Meerut, Meerut, Uttar Pradesh.

When will SOUTH EXTENSION COLONY be completed?

The latest completion date reported to UP-RERA for SOUTH EXTENSION COLONY is 30 Sept 2018.

Is SOUTH EXTENSION COLONY delayed?

Measured against the latest completion date reported to UP-RERA, SOUTH EXTENSION COLONY is 94 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026