Timeline Bar
Registered15 Aug 2017
Promised30 Jun 2018
Revised30 Dec 2018
Completed17 Jun 2022
Timeline
Promised completion30 Jun 2018
Revised completion30 Dec 2018
Actual completion17 Jun 2022
Possession delay42 mo delay
Registration & Cost Details
Registration fee (in ₹)₹33,000
Project cost (in ₹ Lakhs)₹9,93,57,430 Lakhs
Project duration26 months
Project categoryCommercial
Locality—
Original start date1 Nov 2016
Proposed start date1 Nov 2016
Inventory
Total units131
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 131 | 4.62–224.5 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9999659788
EmailADARSHJC7@GMAIL.COM
Coordinator9999659788
Address6, Pratap Nagar, Street no.10, Mayur Vihar, Phase-I, Delhi-110092
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 39412 | 25 Jan 2016 | 24 Jan 2021 | 30 Dec 2018 | 24 Jan 2024 |
| 39412 | 25 Jan 2016 | 24 Jan 2021 | 30 Dec 2018 | 24 Jan 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| C.P.4/1, RATTAN KHAND, SHARDA NAGAR, YOJNA, RAI BA | 2291 SQ. MTRS. | — |
| CP- 4/1, Rattan Khand | 2291 | Plot |
Approved Unit Plan
Unit plan rows on file73
Total flats (sum of rows)131
Total shops131
Blocks1
Floor typesSHOP
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 18304 | 12 Oct 2012 | — | — |
Frequently Asked Questions
What is the RERA registration number of SQUARE ONE?
The RERA registration number of SQUARE ONE is UPRERAPRJ11550, as recorded on the UP-RERA portal.
What is the RERA status of SQUARE ONE?
As reported by UP-RERA, the status of SQUARE ONE is "Registered".
Where is SQUARE ONE located?
As reported to UP-RERA, SQUARE ONE is located at Lucknow, Lucknow, Uttar Pradesh.
Is SQUARE ONE completed?
As reported to UP-RERA, SQUARE ONE was completed on 17 Jun 2022.
Is SQUARE ONE delayed?
Measured against the latest completion date reported to UP-RERA, SQUARE ONE is 42 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.