STALLION VALLEY is a RERA-registered real-estate project in Barabanki (RERA ID UPRERAPRJ10164). Its RERA-registered completion deadline (12 May 2019) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ10164 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 13 May 2017 |
| Original start | 13 May 2017 |
| Project duration | 24 |
| Address | Nawabganj, Barabanki |
| RERA registered | 13 Aug 2017 |
| Promised completion | 12 May 2019 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹1,25,000 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 191 | 6 May 2017 | 5 May 2022 | 12 May 2019 |
| Khasra | Area | Type |
|---|---|---|
| 1245, 1249 | 16307 sq ft | — |
| 1352, 1200, 1208, 1225, 1294, 1309, 1310, 1348, 13 | 23810 sq ft | — |
| 1281 | 29924 sq ft | — |
| 1168, 1314, 1329, 1332 | 7535 sq ft | — |
| 1317, 1318 | 19946 sq ft | — |
| 1299 | 12831 sq ft | — |
| 1246 | 7104 sq ft | — |
| 1278 | 7481 sq ft | — |
| 1220 | 8315 sq ft | — |
| 1246 | 7104 sq ft | — |
| 1192, 1200, 1225, 1309, 1348, 1349, 1293, 1339, 13 | 13078 sq ft | — |
| 1192, 1200, 1225, 1309, 1348, 1339, 1340 | 14930 sq ft | — |
| 1316 | 30139 sq ft | — |
| 1157 | 8181 sq ft | — |
| 1194, 1197 | 9042 sq ft | — |
| 1224 | 3767 sq ft | — |
| 1249, 1317, 1318 | 15984 sq ft | — |
| 1278 | 7427 sq ft | — |
| 1152, 1153, 1154, 1156 | 10979 sq ft | — |
| 1278 | 3784 sq ft | — |
| 1281 | 2780 | Khasra |
| 1168 | 1720 | Khasra |
| 1314 | 1630 | Khasra |
| 1329 | 1260 | Khasra |
| 1332 | 1060 | Khasra |
| 1317 | 2500 | Khasra |
| 1318 | 280 | Khasra |
| 1299 | 1192 | Khasra |
| 1246 | 660 | Khasra |
| 1220 | 772 | Khasra |
| 1246 | 660 | Khasra |
| 1192 | 1380 | Khasra |
| 1200 | 600 | Khasra |
| 1225 | 890 | Khasra |
| 1309 | 710 | Khasra |
| 1348 | 320 | Khasra |
| 1349 | 80 | Khasra |
| 1293 | 1260 | Khasra |
| 1339 | 40 | Khasra |
| 1340 | 360 | Khasra |
| 1316 | 2800 | Khasra |
| 1157 | 760 | Khasra |
| 1194 | 1010 | Khasra |
| 1197 | 2020 | Khasra |
| 1224 | 1350 | Khasra |
| 1152 | 2600 | Khasra |
| 1153 | 520 | Khasra |
| 1154 | 2000 | Khasra |
| 1156 | 1000 | Khasra |
| 1278 | 690 | Khasra |
| 1278 | 695 | Khasra |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 15210 | 26 Aug 2016 | — | — |
| 13475 | 29 Jul 2016 | — | — |
| 12480 | 15 Jul 2016 | — | — |
| 5147 | 18 Mar 2015 | — | — |
| 2190 | 3 Feb 2016 | — | — |
| 14934 | 23 Aug 2016 | — | — |
| 1815 | 29 Jan 2016 | — | — |
| 16116 | 27 Aug 2015 | — | — |
| 21625 | 8 Dec 2015 | — | — |
| 11109 | 10 Jun 2015 | — | — |
| 7161 | 13 Apr 2016 | — | — |
| 1286 | 21 Jan 2016 | — | — |
| 10042 | 30 May 2016 | — | — |
| 13937 | 29 Jul 2015 | — | — |
| 2223 | 5 Feb 2015 | — | — |
| 664 | 12 Jan 2016 | — | — |
| 12008 | 2 Jul 2016 | — | — |
| 2223 | 5 Feb 2015 | — | — |
| 12702 | 6 Jul 2015 | — | — |
| 7825 | 22 Jun 2017 | — | — |
Yes. STALLION VALLEY is registered with UPRERA under registration number UPRERAPRJ10164, registered on 13 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
STALLION VALLEY is 87 months past the completion date filed with UPRERA (12 May 2019), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
STALLION VALLEY is registered in Barabanki, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗