SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB

UPRERARegistered

SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB is a RERA-registered residential project by Sunworld Residency Private Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ11625). Registered with a completion deadline of 23 Jan 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
12.13%Q4'24
12.13%Q1'25
12.13%Q2'25
15.24%Q3'25
16.17%Q4'25
17.78%Q1'26
44.8%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ11625
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start20 Jan 2017
Original start20 Jan 2017
Project duration157 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegd. - GH-01/C SECTOR - 168, NOIDA, Gautam Buddha Nagar, UP 201305
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. 2 building permits sanctioned

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. valid to

    Permit revalidated

    NOIDA/MU.VA.NI/III-268/1274

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered15 Aug 2017
Original completion31 Dec 2021
Revised completion23 Jan 2030
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹60,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors357 · 5 · 32 (units from plan)
  • 3 BHK190 53%
  • 4 BHK93 26%
  • 5 BHK58 16%
  • OTHER12 3%
  • PENTHOUSE4 1%
ConfigurationUnitsCarpet area
5 BHK58258-357
4 BHK93155-330
PENTHOUSE4302-355
3 BHK190118-218
OTHER120-565
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CLUB · OTHER22457-565
T5 · 5 BHK, OTHER30600-357
T7 · 4 BHK, PENTHOUSE, OTHER26520-355
T8 · 4 BHK, PENTHOUSE, OTHER26530-355
T9 · 3 BHK32190118-218
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
R.N. Gupta & Associates
License CA/76/2361
E-1, Sector-55, Noida
Engineer
CE. CON. Engg.
HS-25, Second Floor, Kailash Colony Market, New Delhi-48
Sr.Development work declared to RERA
1Demarcation of Plots
NA
2Boundary Wall
YES
3Road Work
YES
4Footpaths
YES
5Water Supply Including Drinking Water Facilities
YES
6Sewer System
YES
7Drain
YES
8Parks
YES
9Tree Planting
YES
10Design For Electric Supply Including Street Lighting
YES
11Community Buildings
YES
12Treatment and Disposal System of Sewage and Sullage water
YES
13Solid Waste Management And Disposal System
YES
14Water Conservation System
YES
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
YES
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 20 Jan 2022. 1 of them carries a revalidation, valid to 19 Jan 2027.

Sanctioned by Noida Authority · 10,957 sqm of land · an approved plan of 5 blocks and 357 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
NOIDA/MU VA NI/III-268/95420 Jan 201720 Jan 202220 Jan 202731 Dec 2021—
NOIDA/MU VA NI/III-268/95420 Jan 201719 Jan 202223 Jan 203030 Jun 202224 Jan 2025
valid to 19 Jan 2027
as NOIDA/MU.VA.NI/III-268/1274
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 23 Jan 2030.

#Granted fromExtended uptoNote
131 Dec 202130 Jun 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Jun 202223 Jan 2030—

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
PLOT NO-GH-01/C10957—
GH-01/C40221Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 15 Aug 2017.

Registry no.DateTypeArea
12315 Aug 2017self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 5947
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New24 Jan 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New24 Jan 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New24 Jan 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New24 Jan 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New24 Jan 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New24 Jan 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 Jan 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New24 Jan 2020 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New28 Jan 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New24 Jan 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Jan 2020 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old15 Aug 2017 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old15 Aug 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking wateras per sanction plan
Fire safety (as filed with RERA)as per sanction plan
Health serviceas per sanction plan
Renewable energyas per sanction plan
Other facilitiesas per sanction plan

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

26 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

26 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q212.13%CA ↗ · Arch ↗ · Eng ↗
2022-Q312.13%CA ↗ · Arch ↗ · Eng ↗
2022-Q412.13%CA ↗ · Arch ↗ · Eng ↗
2023-Q112.13%CA ↗ · Arch ↗ · Eng ↗
2023-Q212.13%CA ↗ · Arch ↗ · Eng ↗
2023-Q312.13%CA ↗ · Arch ↗ · Eng ↗
2023-Q412.13%CA ↗ · Arch ↗ · Eng ↗
2024-Q112.13%CA ↗ · Arch ↗ · Eng ↗
2024-Q212.13%CA ↗ · Arch ↗ · Eng ↗
2024-Q312.13%CA ↗ · Arch ↗ · Eng ↗
2024-Q412.13%CA ↗ · Arch ↗ · Eng ↗
2025-Q112.13%CA ↗ · Arch ↗ · Eng ↗
2025-Q215.24%CA ↗ · Arch ↗ · Eng ↗
2025-Q316.17%CA ↗ · Arch ↗ · Eng ↗
2025-Q417.78%CA ↗ · Arch ↗ · Eng ↗
2026-Q144.8%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSunworld Residency Private Limited
RolePromoter · current
RERA IDUPRERAPRM6829
PANAAECB1359G
CIN / TANU70200UP2010PTC099023
Name of chairmanMr. ANIL AERY KUMAR Mr. RAGHUVIR Mr. DHARAMVEER SINGH
Registered addressRegd. - GH-01/C SECTOR - 168, NOIDA, Gautam Buddha Nagar, UP 201305
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameNIMBUS PROJECTS LIMITED
RoleCo-promoter
Applicant typeCompany
Address1001-1006, 10TH FLOOR, NARAIN MANZIL, 23, BARAKHAMBA ROAD, NEW DELHI-110001
RERA contact

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
NIMBUS PROJECTS LTD COLLECTION A/C FOR SUNWORLD ARISTA PH-2 T 5,7,8,9 CLUBBankICICI BANK LTDBranchICICI BANK LTD , SECTOR-168, NOIDABranch addressGH-1C, GROUND FLOOR, TOWER-10, SUNWORLD ARISTA, SECTOR-168, EXPRESSWAY NOIDA, GB NAGAR, NOIDA, UTTAR PRADESH-201305Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005707Branch emailHanuman.pandey[at]icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
NIMBUS PROJECTS LTD SEPARATE BANK A/C FOR SUNWORLD ARISTA PH-2 T 5,7,8,9 CLUBBankICICI BANK LTDBranchICICI BANK LTD, SECTOR-168, NOIDABranch addressGH-1C, GROUND FLOOR, TOWER-10,SUNWORLD ARISTA, SECTOR-168, EXPRESSWAY NOIDA, GB NAGAR, NOIDA, UTTAR PRADESH-201305Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005707Branch emailhanuman.pandey[at]icicibank.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
NIMBUS PROJECTS LTD RERA TRANSACTION A/C FOR SUNWORLD ARISTA PH-2 T 5,7,8,9 CLUBBankICICI BANK LTDBranchICICI BANK LTD, SECTOR-168, NOIDABranch addressGH-1C, GROUND FLOOR, TOWER-10, SUNWORLD ARISTA, SECTOR-168, EXPRESSWAY NOIDA, GB NAGAR, NOIDA, UTTAR PRADESH-201305Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0005707Branch emailHanuman.pandey[at]icicibank.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB

Is SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB RERA registered?

Yes. SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB is registered with UPRERA under registration number UPRERAPRJ11625, registered on 15 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

The completion date filed with UPRERA is 23 Jan 2030. No completion certificate is on record yet.

Who is the builder of SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

Sunworld Residency Private Limited is the promoter entity that filed SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB with UPRERA (promoter RERA ID UPRERAPRM6829). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB more time to complete?

UPRERA's record carries 2 completion extensions for SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB, the latest running to 23 Jan 2030. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB located?

SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

The unit plan filed with UPRERA lists 5 BHK, 4 BHK, PENTHOUSE, 3 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

The approved unit plan filed with UPRERA runs from 118 to 565 m² of carpet area (about 1,267 to 6,078 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

The approved unit plan describes 5 blocks and 357 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SUNWORLD ARISTA (PH-2 T-5,7,8,9), CLUB?

About 132 units per acre: 357 planned units across 2.71 acres (10,957 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗