Estanzo

Timeline Bar

Registered10 Aug 2017
Promised30 Sept 2020
Today3 Aug 2026

Timeline

Promised completion30 Sept 2020
Revised completion30 Sept 2020
Actual completion
Possession delay70 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,02,000
Project cost (in ₹ Lakhs)₹15,549 Lakhs
Project duration97 months
Project categoryResidential
Locality
Original start date16 Jul 2008
Proposed start date16 Mar 2013

Inventory

Total units357
Unit TypeUnitsCarpet Area (sqm)
1 BHK9242.441
2 BHK20160.339–100.944
3 BHK57118.45–152.88
4 BHK7152.72–223.91

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810658227
Emailsushantaquapolisrera@gmail.com
Coordinator9560377433
Address115, Ansal Bhawan, 16, KG Marg, New Delhi - 110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
487/ZONE5/GH/201628 Mar 201727 Mar 202230 Sept 202027 Mar 2025

Land Parcels

Khasra No.AreaPlot Type
10433549Khasra
10383361.40Khasra
10421440.60Khasra
10384802Khasra
12654344.90Khasra
1266620.70Khasra
12641241.40Khasra

Approved Unit Plan

Unit plan rows on file192
Total flats (sum of rows)357
BlocksB2B, D09, D11, S3B
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9?

The RERA registration number of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 is UPRERAPRJ5463, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9?

As reported by UP-RERA, the status of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 is "Registered".

Where is SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 located?

As reported to UP-RERA, SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 be completed?

The latest completion date reported to UP-RERA for SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 is 30 Sept 2020.

Is SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 is 70 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026