Timeline Bar
Registered12 Jun 2019
Promised14 Oct 2023
Today29 Jul 2026
Timeline
Promised completion14 Oct 2023
Revised completion14 Oct 2023
Actual completion—
Possession delay33 mo delay
Registration & Cost Details
Registration fee (in ₹)₹36,000
Project cost (in ₹ Lakhs)₹940 Lakhs
Project duration66 months
Project categoryResidential
Locality—
Original start date—
Proposed start date15 Oct 2018
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9918200008
EmailCSHARSHPAHWA@GMAIL.COM
Coordinator9918128841
Address539K/64 FAIZABAD ROAD, HARI NAGAR LUCKNOW, INDIRA GANDHI UTTAR PRADESH-226016
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 201808227181527540 | 25 Jan 2019 | 14 Oct 2023 | 14 Oct 2023 | 25 Jan 2019 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 201 | 6144 | Khasra |
Frequently Asked Questions
What is the RERA registration number of THE HIVE?
The RERA registration number of THE HIVE is UPRERAPRJ905960, as recorded on the UP-RERA portal.
What is the RERA status of THE HIVE?
As reported by UP-RERA, the status of THE HIVE is "Registered".
Where is THE HIVE located?
As reported to UP-RERA, THE HIVE is located at Lucknow, Lucknow, Uttar Pradesh.
When will THE HIVE be completed?
The latest completion date reported to UP-RERA for THE HIVE is 14 Oct 2023.
Is THE HIVE delayed?
Measured against the latest completion date reported to UP-RERA, THE HIVE is 33 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026