TIRUPATI TOWER is a RERA-registered residential project by HISPAN DEVELOPERS PRIVATE LIMITED in Varanasi (RERA ID UPRERAPRJ9382). Registered with a completion deadline of 31 Mar 2018.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ9382 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Varanasi Development Authority |
| Proposed start | 20 Jul 2013 |
| Original start | 20 Jul 2013 |
| Project duration | 57 months |
| Address | Varanasi, Varanasi |
| Tehsil | Varanasi |
| Applicant type | Company |
| Applicant address | C.27/274-A-A1,101, 1st FLOOR, JAI SINGH BUILDING-2, MALDAHIYA , VARANASI |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
49/12 Group Housing
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 11 Aug 2017 |
| Original completion | 31 Mar 2018 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹19,500 |
| Sanctioning authority | Varanasi Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | — | 5,034 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| TIRUPATI TOWER-1 · OTHER | 1 | — | 5,034 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots EAST- BACHA MAURYA, WEST- ROAD (BENIPUR AKTHA ROAD), NORTH- MUNNA LAL GUPTA & BROTHERS, SOUTH- RAMJATAN & AMAR NATH |
| 2 | Boundary Wall YES |
| 3 | Road Work YES |
| 4 | Footpaths YES |
| 5 | Water Supply Including Drinking Water Facilities YES |
| 6 | Sewer System YES |
| 7 | Drain YES |
| 8 | Parks YES |
| 9 | Tree Planting YES |
| 10 | Design For Electric Supply Including Street Lighting YES |
| 11 | Community Buildings YES |
| 12 | Treatment and Disposal System of Sewage and Sullage water NO |
| 13 | Solid Waste Management And Disposal System NO |
| 14 | Water Conservation System YES |
| 15 | Energy Management System Including Use of Renewable Energy YES |
| 16 | Fire Protection And Fire Safety System YES |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services YES |
| 18 | Emergency Evacuation Services YES |
| 19 | Other Miscellaneous Work YES |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 19 Jul 2018.
Sanctioned by Varanasi Development Authority · 2,872 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 49/12 Group Housing | 20 Jul 2013 | 19 Jul 2018 | 18 Jul 2018 | 31 Mar 2018 |
| Document | File |
|---|---|
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
Land & documents
6 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 121 | 78 Dismil | — |
| 21/1,22/2,23 | 2872 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 12 Aug 2008.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 3245/ 373 - 482/ 1897/1 | 12 Aug 2008 | self | — |
| Khatauni extract · 1419-1424 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 31 Jan 2019 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 31 Jan 2019 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 31 Jan 2019 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 11 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | OVER HEAD TANK |
| Fire safety (as filed with RERA) | AVAILABLE |
| Health service | GYM |
| Renewable energy | YES |
| Other facilities | 3 LIFT |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | HISPAN DEVELOPERS PRIVATE LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM13084 |
| PAN | AACCH0432N |
| CIN / TAN | U45400UP2008PTC035336 |
| Name of chairman | ANIL AGRAWAL |
| Registered address | C.27/274-A-A1,101, 1st FLOOR, JAI SINGH BUILDING-2, MALDAHIYA , VARANASI |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Varanasi
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | CURRENT ACCOUNTBankUNION BANK OF INDIABranchHATHUA MARKET, CHETGANJ, VARANASIA/C no.IFSCUBIN0540803 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
Common questions about TIRUPATI TOWER
Is TIRUPATI TOWER RERA registered?
Yes. TIRUPATI TOWER is registered with UPRERA under registration number UPRERAPRJ9382, registered on 11 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for TIRUPATI TOWER?
The completion date filed with UPRERA is 31 Mar 2018. No completion certificate is on record yet.
Who is the builder of TIRUPATI TOWER?
HISPAN DEVELOPERS PRIVATE LIMITED is the promoter entity that filed TIRUPATI TOWER with UPRERA (promoter RERA ID UPRERAPRM13084). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does TIRUPATI TOWER have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is TIRUPATI TOWER located?
TIRUPATI TOWER is registered in Varanasi, as filed with UPRERA.
What configurations are available in TIRUPATI TOWER?
The unit plan filed with UPRERA lists OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗