TULSI WINGS

UPRERARegistered

TULSI WINGS is a RERA-registered residential project by SHRI YAMUNA INFRAESTATE PRIVATE LIMITED in MAUZA SUNRAKH BANGER, DISTRICT MATHURA, Mathura (RERA ID UPRERAPRJ962074). Registered with a completion deadline of 3 Nov 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Oct–Dec 2025
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0%Q1'25
0%Q2'25
0%Q3'25
3%Q4'25

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ962074
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMathura-Vrindavan Development Authority
Proposed start15 Jan 2025
Project duration58 months
AddressKHASRA NO. 291 & 292 MAUZA SUNRAKH BANGER, VRINDAVAN, DISTRICT MATHURA, MAUZA SUNRAKH BANGER, DISTRICT MATHURA, Mathura, Mathura
TehsilMathura
Applicant typeCompany
Applicant addressPART of PLOT NO. 73, 74, KHASRA NO. 64, 65/1, 65/2, &66KA, MAUZA VRINDAVAN KHADAR, VRINDAVAN -281121
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MVDA/BP/24-25/0325

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered7 Mar 2025
Original completion3 Nov 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹28,000
Sanctioning authorityMathura-Vrindavan Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors135 · 1 · 11 (units from plan)
ConfigurationUnitsCarpet area
1 BHK13546-46
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tulsi Wings · OTHER, 1 BHK1113546-46
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Nitin Khaitan
License CA/2013/59227
Street No. 9, Bholanath Nagar, Shahdara, Delhi, 110032
Engineer
Sonu Sharma
Rukmani Vihar, Mathura 281004
Contractor
Shri Yamuna Infraestate Private Limited
Govind Ghera, Vrindaban
Sr.Development work declared to RERA
1Demarcation of Plots
The project land will be clearly demarcated on land with the project boundary wall. The building lines and the setbacks from the periphery to the building line will be maintained as per the byelaws.
2Boundary Wall
A 8 feet high boundary wall will be constructed for the project. The foundation of the boundary wall will be earthquake resistant. The wall will be constructed in brick and mortar with reinforced columns at specified intervals. The wall will be plastered and painted.
3Road Work
The concrete road will be constructed in the project. The 200mm CC Layer will be laid over DLC and GSB. The surface texturing will be done to ensure antiskid paving surface.
4Footpaths
The interlocking paver blocks will be laid to the minimum width of 1m. The M-20 paver block of the depth 60-80mm will be laid for the footpath. The footpath will be on the periphery of the parks and at all suitable locations to encourage walking by the residents.
5Water Supply Including Drinking Water Facilities
The ground water will be pumped to the underground water take of minimum 10,000 kl. Thereon the water will be pumped to the terrace tanks. From terrace tanks the water will be supplied to each unit and common areas of the project. The pipe line will be rust free PVC pipes of sufficient diameter to cater the domestic requirements of the project.
6Sewer System
The sewer system, Vertical and horizontal will be installed in the project to cater for the domestic and common area sewer. The soil pipes will be installed along with the syphon and inspection chambers at all floor levels. The sewer line will be led to the chambers at the ground level. Thereon the sewer will be lead to the STP.
7Drain
The sub surface drain and storm water drains will be constructed in the project. The roof top will be catered for the RWH. The water for domestic drain will be separately catered and will be connected to ground drainage system leading to the outlet as per local norms and guidelines.
8Parks
The parks will be constructed as per the landscape plan. The lush green parks will be developed in the project along with amenities for the kids and elders.
9Tree Planting
The trees suitable to the local soil will be planted in the project along the parks periphery and boundary wall. The trees will also be planted at all suitable locations.
10Design For Electric Supply Including Street Lighting
Separate transformers will be installed for the project as per the approved load/ sanctioned load by DVVNL. The ISI marked electric lines (majorly concealed) will lead to all the individual units through distribution boxes. The street and common lighting will ensure that the common areas are always sufficiently lit.
11Community Buildings
Not Applicable.
12Treatment and Disposal System of Sewage and Sullage water
An STP will be installed in the project. The multi chamber STP will be sufficient to cater for the needs of the project. The sewerage will go through the stage treatments of screening, sedimentation and biological treatment. The waste water will be brought to the safe levels before being disposed.
13Solid Waste Management And Disposal System
The waste chute along with multiple garbage bins will be installed at all floors and at all suitable locations of the project. The domestic waste will be collected as per the category and will be disposed at the pre defined locations by the local administrative body.
14Water Conservation System
The rain water harvesting pits will be constructed/ installed in the project to arrest the terrace water and the surface water. The same will be lead to collection chambers and will move through the multi stage filteration system. The collected filtered water will be led through the perforated pipe of 100 dia. to the ground water. The part of this water will be used for the parks etc.
15Energy Management System Including Use of Renewable Energy
Although not specified in the project, the usage of green technologies along with the LED lights will be installed in the project.
16Fire Protection And Fire Safety System
The installations of fire extinguishers will be done at all the required locations of the project. A separate water tank will be constructed for the purpose of fire fighting. The fire hydrants, sprinklers and alarm systems will be put in place. The building will have the emergency exit to ensure safe egress of the residents from the building in case of fire.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable.
18Emergency Evacuation Services
The stairwell will be developed in a manner to create safe passage in case of emergency in the building. The riser will be constructed considering the old age and youngsters.
19Other Miscellaneous Work
As per the project requirements.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 3 Nov 2029.

Sanctioned by Mathura-Vrindavan Development Authority · 4,509 sqm of land · an approved plan of 1 block and 135 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MVDA/BP/24-25/03254 Nov 20243 Nov 20293 Nov 20303 Nov 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

23 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
2912955Khasra
2921554.36Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 18338
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 6433
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
General body resolution
The resolution authorising an apartment owners’ association to act as the registering entity.
not reported—
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New11 Feb 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New30 Dec 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 Feb 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Dec 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New30 Dec 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New30 Dec 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New30 Dec 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New30 Dec 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Dec 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New11 Feb 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New11 Feb 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New11 Feb 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New31 Dec 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New31 Dec 2024 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2025-Q3.

QuarterConstructionCertificates
2024-Q40%CA ↗ · Arch ↗ · Eng ↗
2025-Q10%CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q33%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSHRI YAMUNA INFRAESTATE PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM319527
PANAATCS9895D
CIN / TANLKNS14322A
Name of chairmanDASHRATH GUPTA
Registered addressPART of PLOT NO. 73, 74, KHASRA NO. 64, 65/1, 65/2, &66KA, MAUZA VRINDAVAN KHADAR, VRINDAVAN -281121
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Mathura

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Shri Yamuna Infraestate Private Limited Tulsi Wings Collection AccountBankICICI Bank LtdBranchVrindabanBranch addressCommon Building Near Balaji Ashram, Rati Ram Road, Vrindavan, Mathura, U.P -281121Branch districtMathuraA/C no.IFSCICIC0001017Branch emailhimanshu.garg4@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Shri Yamuna Infraestate Private Limited Tulsi Wings Separate AccountBankICICI Bank LtdBranchVrindabanBranch addressCommon Building Near Balaji Ashram, Rati Ram Road, Vrindavan, Mathura U.P -281121Branch districtMathura, Uttar PradeshA/C no.IFSCICIC0001017
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Shri Yamuna Infraestate Private Limited Tulsi Wings Transaction AccountBankICICI Bank LtdBranchVrindabanBranch addressCommon Building Near Balaji Ashram, Rati Ram Road, Vrindavan, Mathura, U.P -281121Branch districtMathura, Uttar PradeshA/C no.IFSCICIC0001017
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about TULSI WINGS

Is TULSI WINGS RERA registered?

Yes. TULSI WINGS is registered with UPRERA under registration number UPRERAPRJ962074, registered on 7 Mar 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for TULSI WINGS?

The completion date filed with UPRERA is 3 Nov 2029. No completion certificate is on record yet.

Who is the builder of TULSI WINGS?

SHRI YAMUNA INFRAESTATE PRIVATE LIMITED is the promoter entity that filed TULSI WINGS with UPRERA (promoter RERA ID UPRERAPRM319527). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does TULSI WINGS have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is TULSI WINGS located?

TULSI WINGS is registered in MAUZA SUNRAKH BANGER, DISTRICT MATHURA, Mathura, as filed with UPRERA.

What configurations are available in TULSI WINGS?

The unit plan filed with UPRERA lists OTHER and 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in TULSI WINGS?

The approved unit plan filed with UPRERA runs from 46 to 46 m² of carpet area (about 496 to 496 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in TULSI WINGS?

The approved unit plan describes 1 block and 135 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is TULSI WINGS?

About 121 units per acre: 135 planned units across 1.11 acres (4,509 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗