Timeline Bar
Registered14 Aug 2017
Promised31 Dec 2024
Today4 Aug 2026
Timeline
Promised completion31 Dec 2024
Revised completion—
Actual completion—
Possession delay19 mo delay
Registration & Cost Details
Registration fee (in ₹)₹60,000
Project cost (in ₹ Lakhs)₹7,500 Lakhs
Project duration91 months
Project categoryCommercial
Locality—
Original start date15 May 2013
Proposed start date4 Dec 2017
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8826190022
Emailinfo@ufgrp.com
Coordinator8826192111
AddressB-117, Sector 67, Noida 201301
No promoter data available.
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 5 | 5000 | — |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| I5566 | 7 Dec 2007 | — | — |
Frequently Asked Questions
What is the RERA registration number of Unnati Fortune World - Phase 1?
The RERA registration number of Unnati Fortune World - Phase 1 is UPRERAPRJ10900, as recorded on the UP-RERA portal.
What is the RERA status of Unnati Fortune World - Phase 1?
As reported by UP-RERA, the status of Unnati Fortune World - Phase 1 is "Registered".
Where is Unnati Fortune World - Phase 1 located?
As reported to UP-RERA, Unnati Fortune World - Phase 1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will Unnati Fortune World - Phase 1 be completed?
The latest completion date reported to UP-RERA for Unnati Fortune World - Phase 1 is 31 Dec 2024.
Is Unnati Fortune World - Phase 1 delayed?
Measured against the latest completion date reported to UP-RERA, Unnati Fortune World - Phase 1 is 19 months beyond that date.