VAIBHAV HERITAGE HEIGHT

UPRERARegistered

VAIBHAV HERITAGE HEIGHT is a RERA-registered residential project by B S BUILDTECH in Gautam Budh Nagar (RERA ID UPRERAPRJ2779). Registered with a completion deadline of 30 Jan 2028. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2024
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'22
—Q2'23
64%Q3'23
64%Q4'23
64%Q1'24

Construction stayed at 64% across 3 consecutive filed quarters (Jul–Sep 2023 to Jan–Mar 2024). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ2779
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start30 Oct 2014
Original start15 Dec 2013
Project duration160 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typePartnership Firm
Applicant addressA-1/B 64, JANAKPURI, DELHI
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Permit revalidated

    8357

  3. 2 building permits sanctioned

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered12 Aug 2017
Original completion29 Oct 2021
Revised completion30 Jan 2028
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,06,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 7 · 25 (from plan)
ConfigurationUnitsCarpet area
OTHER—331
2 BHK—317-342
3 BHK—342-524
4 BHK—524
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, 2 BHK24—331
B · 2 BHK, OTHER24—317
C · OTHER, 2 BHK23—317-317
D · OTHER, 2 BHK24—317-331
E · OTHER, 3 BHK24—342
F · OTHER, 3 BHK, 4 BHK25—524
G · OTHER, 2 BHK23—342
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
NIVEDITA AND UDAY PANDE CONSULTANTS
License CA2006/37536
A-243, OKHLA INDUSTRIAL AREA, PHASE-1, NEW DELHI
Engineer
HIMANSHU SINGHAL
10/49, SUBHASH NAGAR, DELHI-110027
Sr.Development work declared to RERA
1Demarcation of Plots
PLOT DEMARCATED AS PER POSESSION LETTER OF GNIDA
2Boundary Wall
PROPOSAL FOR 2 METRE HEIGHT BOUNDARY WALL
3Road Work
6 MTR WIDE ROAD AS APPROVED
4Footpaths
FOOTPATH ALONG THE PROJECT AS PER APPROVED DRAWING
5Water Supply Including Drinking Water Facilities
OVERHEAD TANK FOR WATER SUPPLY IN EACH BLOCK
6Sewer System
SEWARAGE LINE AND MAINHOLE CONNECTED TO STP OF 525 KLD
7Drain
PROVISION FOR 300 MM DRAINAGE PIPE LINE FOR EFFICIENT REMOVAL OF DRAINAGE
8Parks
PROVISION FOR GREEN AND LAND SCAPED PARK
9Tree Planting
PROPOSAL FOR 200 TREES AROUND PROJECT
10Design For Electric Supply Including Street Lighting
DEDICATED TRANSFORMER INCLUDING POWER BACK UP FOR EFFICIENT SUPPLY OF ELECTRICITY. PROVISION FOR LED STREET LIGHTING
11Community Buildings
PROVISION FOR COMMUNITY HALL AND RECREATIONAL ACTIVITY
12Treatment and Disposal System of Sewage and Sullage water
PROVISION FOR 525 KLD STP TREATMENT PLANT
13Solid Waste Management And Disposal System
PROPOSAL FOR COLLECTION AND DISPOSAL OF SOLID WASTE FROM EAST TOWER BY MECHANICAL MEANS
14Water Conservation System
PROVISION FOR RAIN WATER HARVESTING WITH SUFFICIENT NUMBER OF RECHARGE WELLS
15Energy Management System Including Use of Renewable Energy
AS PER ECBC GUIDELINES
16Fire Protection And Fire Safety System
PROVISION FOR SEPARATE OVERHEAD TANK FOR FIRE PIPELINES, HYDRANTS, AND SPRINKLERS IN EACH TOWER
17Social Infrastructure And Other Public Amenities Including Public Health Services
PROVISION FOR VARIOUS INDOOR AND OUTDOOR SPORTS
18Emergency Evacuation Services
PROVISION FOR FIRE STAIRS IN EACH TOWER
19Other Miscellaneous Work
JOGGING TRACK ETC
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 29 Oct 2021. 1 of them carries a revalidation.

Sanctioned by Greater Noida Authority · 20,265 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
835730 Oct 201429 Oct 2021—29 Oct 2021—
835730 Oct 201430 Oct 201428 Jan 202428 Jan 202430 Oct 2014
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 30 Jan 2028.

#Granted fromExtended uptoNote
129 Oct 202128 Apr 2022Six months extension in view of force majeure caused by covid-19 pandemic
228 Apr 202228 Jan 2024—
328 Jan 202430 Jan 2028—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
405820265.08—
GH01E20265.08Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

4 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 26 Feb 2013.

Registry no.DateTypeArea
405826 Feb 2013self—
405826 Feb 2013self—
405826 Feb 2013self—
405826 Feb 2013self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 4058
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 May 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 May 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 May 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 May 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New31 May 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New31 May 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 May 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 May 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old21 Feb 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old23 Feb 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterYES
Fire safety (as filed with RERA)YES
Health serviceYES
Renewable energyYES
Other facilitiesYES

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2021-Q4 to 2023-Q4.

QuarterConstructionCertificates
2021-Q4—CA ↗ · Arch ↗
2023-Q1—CA ↗
2023-Q264%CA ↗ · Arch ↗ · Eng ↗
2023-Q364%CA ↗ · Arch ↗ · Eng ↗
2023-Q464%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2023-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameB S BUILDTECH
RolePromoter · current
RERA IDUPRERAPRM4910
PANAAKFB6049A
Registered addressA-1/B 64, JANAKPURI, DELHI
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
B.S. BUILDTECHBankBANK OF INDIABranchGHAZIABADA/C no.IFSCBKID0007100
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about VAIBHAV HERITAGE HEIGHT

Is VAIBHAV HERITAGE HEIGHT RERA registered?

Yes. VAIBHAV HERITAGE HEIGHT is registered with UPRERA under registration number UPRERAPRJ2779, registered on 12 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for VAIBHAV HERITAGE HEIGHT?

The completion date filed with UPRERA is 30 Jan 2028. No completion certificate is on record yet.

Who is the builder of VAIBHAV HERITAGE HEIGHT?

B S BUILDTECH is the promoter entity that filed VAIBHAV HERITAGE HEIGHT with UPRERA (promoter RERA ID UPRERAPRM4910). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does VAIBHAV HERITAGE HEIGHT show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted VAIBHAV HERITAGE HEIGHT more time to complete?

UPRERA's record carries 3 completion extensions for VAIBHAV HERITAGE HEIGHT, the latest running to 30 Jan 2028. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does VAIBHAV HERITAGE HEIGHT have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VAIBHAV HERITAGE HEIGHT located?

VAIBHAV HERITAGE HEIGHT is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in VAIBHAV HERITAGE HEIGHT?

The unit plan filed with UPRERA lists OTHER, 2 BHK, 3 BHK and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in VAIBHAV HERITAGE HEIGHT?

The approved unit plan filed with UPRERA runs from 317 to 524 m² of carpet area (about 3,410 to 5,645 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗