Vinayak Central Park @ Shervani Legacy Phase-2

UPRERARegistered

Vinayak Central Park @ Shervani Legacy Phase-2 is a RERA-registered residential project by Vinayakkripa Homebuild LLP in Prayagraj (RERA ID UPRERAPRJ421675). Registered with a completion deadline of 30 Jun 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
100%Q3'25
100%Q4'25
100%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ421675
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAllahabad Development Authority
Proposed start1 Nov 2019
Project duration92 months
AddressAllahabad **, Prayagraj
TehsilAllahabad **
Applicant typePartnership Firm
Applicant address4th Floor Vinayak Solitaire, 32/18, S.P. Marg, Civil Lines, Allahabad, Allahabad, Uttar Pradesh, India, 211001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    62/Pr.A.(Ta.Sa-1)/Zone-1/Prasta./2018-19

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion certificate filed

  5. Completion certificate filed

  6. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Dec 2019
Original completion31 Dec 2026
Revised completion30 Jun 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary19 Feb 2024
Registration fee₹1,04,000
Sanctioning authorityAllahabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors664 · 3 · 14 (units from plan)
Homes · commercial units657 · 7 (shops and offices filed in the same plan)
  • 2 BHK422 64%
  • 1 BHK235 35%
  • SHOP7 1%
ConfigurationUnitsCarpet area
1 BHK23542-43
2 BHK42259-60
SHOP724-33
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block- A · OTHER, 1 BHK, 2 BHK1432842-60
Block- B · OTHER, 1 BHK, 2 BHK1432942-60
Block- C · SHOP, OTHER4724-33
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AR. AKHILESHWAR SINGH
License CA/94/16740
49/G-7, LOTUS APARTMENT, TASHKANT MARG, ALLAHABAD - 211001
Engineer
Er. Akhilesh Singh
D-27, Indira Nagar, Lucknow
Contractor
M/s Shobha Construction
Arazi No.-95, Jhalwa Indian Oil Road, Near Mayur Vihar, Allahabad (U.P)- 211012
Sr.Development work declared to RERA
1Demarcation of Plots
THE BLOCKS CONCERNED WITH PHASE-2 WILL BE AS PER THE LAYOUT APPROVED BY AUTHORITY WITH THE INTERBLOCK DISTANCE AS SPECIFIED IN THE DRAWINGS.
2Boundary Wall
THERE WILL BE BOUNDRY WALL WITH BRICK WORK & GRILL ENCLOSING THE AREA UNDER PHASE II.
3Road Work
CC/ BITHUMIN ROAD SHALL BE PROVIDED AS PER NORMS.
4Footpaths
FOOTPATH WITH SOFT PAVEMENT BLOCKS SHALL BE PROVIDED.
5Water Supply Including Drinking Water Facilities
WATER SUPPLY TO THE SCHEME UNDER PHASE-II SHALL BE THROUGH UNDERGROUND WATER TANK CONNECTED TO EXISTING MAIN MUNICIPAL LINE.
6Sewer System
THE SEWER SYSTEM OF THE SCHEME SHALL BE CONNECTED TO PROPOSED STP OF REQUIRED CAPACITY & TREATED WATER WILL BE USED FOR FLUSHING/ GARDNING /WASHING ETC USING THE DUAL PIPE SYSTEM AS PER LAYOUT.
7Drain
DRAIN ALONG THE MAIN ROAD SHALL BE PROVIDED WITH PROPER SLOPE.
8Parks
PARK SHALL BE DEVELOPED WITH STRUCTURED GREEN AREA.
9Tree Planting
MORE THAN 128 NUMBERS OF TREES SHALL BE PLANTED.
10Design For Electric Supply Including Street Lighting
ELECTRIC SUPPLY TO THE SCHEME SHALL BE THOUGH TRANSFORMER OF REQUIRED CAPACITY CONNECTED TO MAIN EXISTING GOVT. POWER SUPPLY LINE WITH REQUIRED INFRASTRUCTURE.
11Community Buildings
COMMUNITY BUILDING SHALL BE CONSTRUCTED AS PER PLAN APPROVED BY THE AUTHORITY.
12Treatment and Disposal System of Sewage and Sullage water
STP OF REQURED CAPACITY SHALL BE CONSTRUCTED / INSTALLED & TREATED WATER WILL BE USED FOR FLUSHING/ GARDNING/ WASHING USING DUAL PIPE SYSTEM WITH OVERFLOW CONNECTING TO EXISTING MUNICIPAL SEWER LINE.
13Solid Waste Management And Disposal System
DUSTBINS WILL BE PROVIDED AS PER DRAWING WHICH SHALL BE COLLECTED & DISPOSED BY THE PRAYAGRAJ NAGAR NIGAM.
14Water Conservation System
RAINWATER HARVESTING SYSTEM SHALL BE CONSTRUCTED AS PER APPROVED LAYOUT.
15Energy Management System Including Use of Renewable Energy
1. PHOTOVOLTAIC POWER PLANT SHLL BE INSTALLED ON THE TERRACE FOR THE DESIGNATED USAGE. 2. SOLAR WATER HEATERS SHALL BE PROVIDED AS PER GUIDELINES 3. STREET LIGHTS WITH SOLAR PANELS SHALL BE INSTALLED
16Fire Protection And Fire Safety System
FIRE PROTECTION & FIRE SAFETY SYSTEM SHALL BE PROVIDED AS PER THE GUIDELINES GIVEN BY THE FIRE DEPARTMENT.
17Social Infrastructure And Other Public Amenities Including Public Health Services
PROVISION OF A NURSERY SCHOOL AS PER SANCTIONED DRAWING SHALL BE CONSTRUCTED WHICH MAY BE USED BY THE RESIDENTS AND OTHERS IN THE VICINITY ON PAYMENT BASIS
18Emergency Evacuation Services
ADEQUATE NUMBERS OF STAIRCASE WITH PROPER VENTILATION SHALL BE PROVIDED.
19Other Miscellaneous Work
N/A
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 20 Feb 2024.

Sanctioned by Allahabad Development Authority · 19,760 sqm of land · an approved plan of 3 blocks and 664 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
62/Pr.A.(Ta.Sa-1)/Zone-1/Prasta./2018-1921 Feb 201920 Feb 202420 Feb 202731 Dec 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Jun 2027.

#Granted fromExtended uptoNote
131 Dec 202630 Jun 2027Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Vinayak Central Park @ Shervani Legacy, Harwara Sulemsarai, Prayagraj25376Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 1532
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · Reply to Objection Letter received from RERA for registration
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Nov 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New23 Nov 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New23 Nov 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New23 Nov 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New23 Nov 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New23 Nov 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New23 Nov 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New23 Nov 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Nov 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 Nov 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New23 Nov 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 Nov 2019 ↗

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2100%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameVinayakkripa Homebuild LLP
RolePromoter · current
RERA IDUPRERAPRM87312
PANAAOFV3348L
CIN / TANALDV01322G
Registered address4th Floor Vinayak Solitaire, 32/18, S.P. Marg, Civil Lines, Allahabad, Allahabad, Uttar Pradesh, India, 211001
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Vinayakkripa Homebuild LLPBankFEDERAL BANK LIMITEDBranchCivil Lines,AllahabadA/C no.IFSCFDRL0001392
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Vinayak Central Park @ Shervani Legacy Phase-2

Is Vinayak Central Park @ Shervani Legacy Phase-2 RERA registered?

Yes. Vinayak Central Park @ Shervani Legacy Phase-2 is registered with UPRERA under registration number UPRERAPRJ421675, registered on 24 Dec 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Has Vinayak Central Park @ Shervani Legacy Phase-2 been completed?

UPRERA still lists Vinayak Central Park @ Shervani Legacy Phase-2 as Registered, so it is not shown as completed here. A completion certificate dated 19 Feb 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Vinayak Central Park @ Shervani Legacy Phase-2?

Vinayakkripa Homebuild LLP is the promoter entity that filed Vinayak Central Park @ Shervani Legacy Phase-2 with UPRERA (promoter RERA ID UPRERAPRM87312). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Vinayak Central Park @ Shervani Legacy Phase-2 more time to complete?

UPRERA's record carries 1 completion extension for Vinayak Central Park @ Shervani Legacy Phase-2, the latest running to 30 Jun 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Vinayak Central Park @ Shervani Legacy Phase-2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Vinayak Central Park @ Shervani Legacy Phase-2 located?

Vinayak Central Park @ Shervani Legacy Phase-2 is registered in Prayagraj, as filed with UPRERA.

What configurations are available in Vinayak Central Park @ Shervani Legacy Phase-2?

The unit plan filed with UPRERA lists OTHER, 1 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Vinayak Central Park @ Shervani Legacy Phase-2?

The approved unit plan filed with UPRERA runs from 24 to 60 m² of carpet area (about 262 to 645 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Vinayak Central Park @ Shervani Legacy Phase-2?

The approved unit plan describes 3 blocks and 664 units of which 657 are homes and 7 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Vinayak Central Park @ Shervani Legacy Phase-2?

About 136 units per acre: 664 planned units across 4.88 acres (19,760 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗