YAMUNA VIHAR (PHASE-1) is a RERA-registered residential project by Prayagraj Development Authority in Prayagraj (RERA ID UPRERAPRJ12222). Registered with a completion deadline of 30 Dec 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ12222 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Allahabad Development Authority |
| Proposed start | 28 Apr 2017 |
| Original start | 28 Dec 2016 |
| Project duration | 57 months |
| Address | Karchhana, Prayagraj |
| Tehsil | Karchhana |
| Applicant type | Competent authority |
| Applicant address | Indira Bhawan, Civil Lines, Prayagraj-211001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
14/TP/NIYOJAN/ADA
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- to
Extension granted
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 3 Oct 2017 |
| Original completion | 27 Apr 2020 |
| Revised completion | 30 Dec 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 26 Apr 2023 |
| Registration fee | ₹27,000 |
| Sanctioning authority | Allahabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 192 | 57 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| B-3 · 2 BHK | 12 | 96 | 57 |
| B-4 · 2 BHK | 12 | 96 | 57 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Located on 18 m wide road |
| 2 | Boundary Wall RCC structure with brick work and railing |
| 3 | Road Work RCC pavement roads |
| 4 | Footpaths Roads as above |
| 5 | Water Supply Including Drinking Water Facilities Tube well |
| 6 | Sewer System RCC hume pipes |
| 7 | Drain Brick masonary drain |
| 8 | Parks As per plan |
| 9 | Tree Planting Inside parks |
| 10 | Design For Electric Supply Including Street Lighting Transformer and LED lights |
| 11 | Community Buildings In the neighbourhood |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP |
| 13 | Solid Waste Management And Disposal System One point collection and disposal |
| 14 | Water Conservation System Rain water harvesting |
| 15 | Energy Management System Including Use of Renewable Energy LED street lights |
| 16 | Fire Protection And Fire Safety System Sprinkler system in basement and yard hydrant system in stilt and all floors |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services In the neighbourhood |
| 18 | Emergency Evacuation Services Fire escape staircase |
| 19 | Other Miscellaneous Work Parking |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 26 Feb 2022.
Sanctioned by Allahabad Development Authority · 4,314 sqm of land · an approved plan of 2 blocks and 192 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 14/TP/NIYOJAN/ADA | 27 Feb 2017 | 26 Feb 2022 | 26 Feb 2025 | 27 Apr 2020 |
| Document | File |
|---|---|
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 4 completion extensions for this project, the latest running to 30 Dec 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 27 Apr 2020 | 26 Oct 2020 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 26 Oct 2020 | 31 Mar 2021 | — |
| 3 | 31 Mar 2021 | 30 Sept 2021 | — |
| 4 | 30 Sept 2021 | 30 Dec 2021 | — |
Land & documents
3 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 43,44,45,46,47,48,49,50,51,52,53,54/1,54/2,72,73,7 | 25884.27 | — |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 16 Jun 1983.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 7462/37-2-82-62-LA-81 UNDER SECTION6 OF LAND AQUIS | 16 Jun 1983 | self | — |
| Khatauni extract · 1425-1430 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1425-1430 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 30 Nov 2019 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 23 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | FROM OVER HEAD TANKS FILLED BY BORWELL |
| Fire safety (as filed with RERA) | YES AS PER NBC 2016 |
| Health service | no |
| Renewable energy | NO |
| Other facilities | OPEN AREA |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
6 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | Arch ↗ · Eng ↗ |
| 2020-Q2 | — | Arch ↗ · Eng ↗ |
| 2020-Q3 | — | Arch ↗ · Eng ↗ |
| 2020-Q4 | — | Arch ↗ · Eng ↗ |
| 2021-Q1 | — | Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Prayagraj Development Authority |
| Role | Promoter · current |
| RERA ID | UPRERAPRM11999 |
| PAN | AAALA0144P |
| CIN / TAN | LKNA05622B |
| Registered address | Indira Bhawan, Civil Lines, Prayagraj-211001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Prayagraj
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | SECRETARY ALLAHABAD DEVELOPMENT AUTHORITYBankHDFC BANK LIMITEDBranchCIVIL LINES ALLAHABADA/C no.IFSCHDFC0000226 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about YAMUNA VIHAR (PHASE-1)
Is YAMUNA VIHAR (PHASE-1) RERA registered?
Yes. YAMUNA VIHAR (PHASE-1) is registered with UPRERA under registration number UPRERAPRJ12222, registered on 3 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has YAMUNA VIHAR (PHASE-1) been completed?
UPRERA still lists YAMUNA VIHAR (PHASE-1) as Registered, so it is not shown as completed here. A completion certificate dated 26 Apr 2023 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of YAMUNA VIHAR (PHASE-1)?
Prayagraj Development Authority is the promoter entity that filed YAMUNA VIHAR (PHASE-1) with UPRERA (promoter RERA ID UPRERAPRM11999). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted YAMUNA VIHAR (PHASE-1) more time to complete?
UPRERA's record carries 4 completion extensions for YAMUNA VIHAR (PHASE-1), the latest running to 30 Dec 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does YAMUNA VIHAR (PHASE-1) have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is YAMUNA VIHAR (PHASE-1) located?
YAMUNA VIHAR (PHASE-1) is registered in Prayagraj, as filed with UPRERA.
What configurations are available in YAMUNA VIHAR (PHASE-1)?
The unit plan filed with UPRERA lists 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
How many towers and units are planned in YAMUNA VIHAR (PHASE-1)?
The approved unit plan describes 2 blocks and 192 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is YAMUNA VIHAR (PHASE-1)?
About 180 units per acre: 192 planned units across 1.07 acres (4,314 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗