Timeline Bar

Registered3 Feb 2020
Completed21 Apr 2023
Promised20 Jun 2023

Timeline

Promised completion20 Jun 2023
Revised completion20 Jun 2023
Actual completion21 Apr 2023
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹19,500
Project cost (in ₹ Lakhs)₹5,566 Lakhs
Project duration48 months
Project categoryResidential
Locality
Original start date
Proposed start date25 Dec 2019

Inventory

Total units150
Unit TypeUnitsCarpet Area (sqm)
2 BHK3967.209
3 BHK11174.986–79.839

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810217573
EmailALPINEINFRAPROJECTS@GMAIL.COM
Coordinator9810217573
Addresschamber no.11, vindhyachal apartment, kaushambi, Ghaziabad, U.P. 201010

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q295.0%
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q390.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/3576/403521 Jun 201820 Jun 202320 Jun 202320 Jun 2024

Land Parcels

Khasra No.AreaPlot Type
GH-16D13800Plot

Approved Unit Plan

Unit plan rows on file64
Total flats (sum of rows)150
BlocksTOWER-4, Tower-5
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of AIG ROYAL ( PHASE-2)?

The RERA registration number of AIG ROYAL ( PHASE-2) is UPRERAPRJ958972, as recorded on the UP-RERA portal.

What is the RERA status of AIG ROYAL ( PHASE-2)?

As reported by UP-RERA, the status of AIG ROYAL ( PHASE-2) is "Registered".

Where is AIG ROYAL ( PHASE-2) located?

As reported to UP-RERA, AIG ROYAL ( PHASE-2) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is AIG ROYAL ( PHASE-2) completed?

As reported to UP-RERA, AIG ROYAL ( PHASE-2) was completed on 21 Apr 2023.

Is AIG ROYAL ( PHASE-2) delayed?

Measured against the latest completion date reported to UP-RERA, AIG ROYAL ( PHASE-2) is on time.