AJANTA TOWER

UPRERARegistered

AJANTA TOWER is a RERA-registered commercial project by AJANT KUMAR AGARWAL in Lucknow (RERA ID UPRERAPRJ16077). Registered with a completion deadline of 13 Nov 2021.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ16077
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start15 May 2018
Project duration42 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeIndividual
Applicant address35B, J PARK, MAHANAGAR EXTENTION, LUCKNOW, UTTAR PRADESH - 226006
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    40186

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered10 May 2018
Original completion14 May 2021
Revised completion13 Nov 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹33,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors6 · 1 · 7 (units from plan)
ConfigurationUnitsCarpet area
OTHER6595
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · OTHER76595
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Repunjay Patel
License CA/2001/28562
D-2/122 Ground Floor, Sambhav Tower, Vibhuti Khand, Gomti Nagar, Lucknow.
Engineer
Irshad Ahmad
Buildtech Consultancy Services, Indira Nagar, Lucknow
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
NA
2Boundary Wall
NA
3Road Work
NA
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
NA
6Sewer System
NA
7Drain
NA
8Parks
NA
9Tree Planting
NA
10Design For Electric Supply Including Street Lighting
NA
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
NA
13Solid Waste Management And Disposal System
NA
14Water Conservation System
NA
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
NA
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 19 Jun 2021.

Sanctioned by Lucknow Development Authority · 2,280 sqm of land · an approved plan of 1 block and 6 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoRevised endDocuments filed
4018620 Jun 201619 Jun 202114 May 2021
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 13 Nov 2021.

#Granted fromExtended uptoNote
114 May 202113 Nov 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4342279.71Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 1898/98
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAJANT KUMAR AGARWAL
RolePromoter · current
RERA IDUPRERAPRM44767
PANABKPA4247J
Registered address35B, J PARK, MAHANAGAR EXTENTION, LUCKNOW, UTTAR PRADESH - 226006
RERA contact
Registered since2018
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
AJANTA ENTERPRISESBankOriental Bank of CommerceBranchALAMBAGHA/C no.IFSCORBC0100752
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about AJANTA TOWER

Is AJANTA TOWER RERA registered?

Yes. AJANTA TOWER is registered with UPRERA under registration number UPRERAPRJ16077, registered on 10 May 2018. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for AJANTA TOWER?

The completion date filed with UPRERA is 13 Nov 2021. No completion certificate is on record yet.

Who is the builder of AJANTA TOWER?

AJANT KUMAR AGARWAL is the promoter entity that filed AJANTA TOWER with UPRERA (promoter RERA ID UPRERAPRM44767). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted AJANTA TOWER more time to complete?

UPRERA's record carries 1 completion extension for AJANTA TOWER, the latest running to 13 Nov 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does AJANTA TOWER have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is AJANTA TOWER located?

AJANTA TOWER is registered in Lucknow, as filed with UPRERA.

What configurations are available in AJANTA TOWER?

The unit plan filed with UPRERA lists OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in AJANTA TOWER?

The approved unit plan describes 1 block and 6 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is AJANTA TOWER?

About 11 units per acre: 6 planned units across 0.56 acres (2,280 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗