BCC SAPPHIRE

UPRERARegistered

BCC SAPPHIRE is a RERA-registered residential project by HALLMARK VYAPAAR PRIVATE LIMITED in Lucknow (RERA ID UPRERAPRJ17017). Registered with a completion deadline of 28 Jun 2023.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2023
Quarters shown are calendar quarters. UP-RERA files them by financial year.
100%Q3'21
100%Q4'21
100%Q1'22
100%Q2'22
100%Q3'22
100%Q4'22
100%Q1'23
100%Q2'23

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ17017
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAny Other Competent Authority
Proposed start1 Jul 2018
Project duration60 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant addressFourth Floor Ganj Trade Centre 10 Capper Road, Hazrat Ganj, Lucknow G.P.O., Lucknow, Lucknow, Uttar Pradesh, India 226001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    264/Naksha/Ni.vi./ZilaPanchayat/2017-2018

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. valid to

    Permit revalidated

    406/Naksha/Zila.Panca./2020-2021

  8. to

    Extension granted

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered12 Jul 2018
Original completion30 Jun 2021
Revised completion28 Jun 2023
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹21,000
Sanctioning authorityAny Other Competent Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors140 · 1 · 11 (units from plan)
  • 3 BHK80 57%
  • 2 BHK60 43%
ConfigurationUnitsCarpet area
2 BHK6074
3 BHK80111
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER A · 2 BHK, 3 BHK, OTHER1114074-111
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
AR. PRAGYA SINGH
License CA/2007/40920
1/102, VIJAY KHAND, GOMTI NAGAR, LUCKNOW
Engineer
NA
NA
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
NA
2Boundary Wall
TO BE CONSTRUCTED
3Road Work
TO BE UNDERTAKEN
4Footpaths
TO BE CONSTRUCTED
5Water Supply Including Drinking Water Facilities
WILL BE MADE AVAILABLE
6Sewer System
FACILITY WILL BE PROVIDED
7Drain
FACILITY WILL BE PROVIDED
8Parks
NA
9Tree Planting
65 TREES PLANTATION IS BEING UNDERTAKEN
10Design For Electric Supply Including Street Lighting
FACILITY WILL BE PROVIDED
11Community Buildings
WILL BE CONSTUCTED AS PER NEED
12Treatment and Disposal System of Sewage and Sullage water
FACILITY WILL BE PROVIDED
13Solid Waste Management And Disposal System
FACILITY WILL BE PROVIDED
14Water Conservation System
FACILITY WILL BE PROVIDED
15Energy Management System Including Use of Renewable Energy
MEASURES WILL BE UNDERTAKEN
16Fire Protection And Fire Safety System
PROPER MEASURES WILL BE UNDERTAKEN
17Social Infrastructure And Other Public Amenities Including Public Health Services
FACILITY WILL BE PROVIDED
18Emergency Evacuation Services
FACILITY WILL BE PROVIDED
19Other Miscellaneous Work
CLUB, GYM, SWIMMING POOL ETC.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 11 Mar 2020. 2 of them carry a revalidation, the latest valid to 11 Dec 2023.

Sanctioned by Any Other Competent Authority · 3,121 sqm of land · an approved plan of 1 block and 140 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
264/NAKSA/Ni.Vi./Zi.P./2017-201812 Mar 201811 Mar 202030 Jun 202130 Jun 2021—
—11 Mar 202011 Dec 202329 Dec 202112 Dec 2021
valid to 11 Dec 2023
as 406/Naksha/Zila.Panca./2020-2021
264/Naksha/Ni.vi./ZilaPanchayat/2017-201812 Mar 201811 Mar 202011 Dec 202328 Jun 202312 Mar 2018
valid to 11 Dec 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 28 Jun 2023.

#Granted fromExtended uptoNote
130 Jun 202129 Dec 2021Six months extension in view of force majeure caused by covid-19 pandemic
229 Dec 202128 Jun 2023—

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
625,626,6281481.06Khasra
6241640Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · BAHI NO.1, JILD NO. 21059 PAGE NO. 155 TO 174, SL 8698
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · BAHI NO. 1, JILD NO. 21059, PAGE NO. 175 TO 192, SL NO. 8699
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New12 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New12 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New12 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New12 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New12 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New12 Jul 2018 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q1.

QuarterConstructionCertificates
2020-Q1100%CA ↗ · Arch ↗ · Eng ↗
2020-Q2100%CA ↗ · Arch ↗ · Eng ↗
2020-Q3100%CA ↗ · Arch ↗ · Eng ↗
2020-Q4100%CA ↗ · Arch ↗ · Eng ↗
2021-Q1100%CA ↗ · Arch ↗ · Eng ↗
2021-Q2100%CA ↗ · Arch ↗ · Eng ↗
2021-Q3100%CA ↗ · Arch ↗ · Eng ↗
2021-Q4100%CA ↗ · Arch ↗ · Eng ↗
2022-Q1100%CA ↗ · Arch ↗ · Eng ↗
2022-Q2100%CA ↗ · Arch ↗ · Eng ↗
2022-Q3100%CA ↗ · Arch ↗ · Eng ↗
2022-Q4100%CA ↗ · Arch ↗ · Eng ↗
2023-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2023-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHALLMARK VYAPAAR PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM48634
PANAACCH0589A
CIN / TANU51109UP2008PTC096566
Name of chairmanRavi Singh
Registered addressFourth Floor Ganj Trade Centre 10 Capper Road, Hazrat Ganj, Lucknow G.P.O., Lucknow, Lucknow, Uttar Pradesh, India 226001
RERA contact
Registered since2018
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
HALLMARK VYAPAAR PVT. LTD.BankVIJAYA BANKBranchB.N. ROAD BRANCHA/C no.IFSCVIJB0007127
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about BCC SAPPHIRE

Is BCC SAPPHIRE RERA registered?

Yes. BCC SAPPHIRE is registered with UPRERA under registration number UPRERAPRJ17017, registered on 12 Jul 2018. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for BCC SAPPHIRE?

The completion date filed with UPRERA is 28 Jun 2023. No completion certificate is on record yet.

Who is the builder of BCC SAPPHIRE?

HALLMARK VYAPAAR PRIVATE LIMITED is the promoter entity that filed BCC SAPPHIRE with UPRERA (promoter RERA ID UPRERAPRM48634). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted BCC SAPPHIRE more time to complete?

UPRERA's record carries 2 completion extensions for BCC SAPPHIRE, the latest running to 28 Jun 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does BCC SAPPHIRE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is BCC SAPPHIRE located?

BCC SAPPHIRE is registered in Lucknow, as filed with UPRERA.

What configurations are available in BCC SAPPHIRE?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in BCC SAPPHIRE?

The approved unit plan filed with UPRERA runs from 74 to 111 m² of carpet area (about 800 to 1,200 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in BCC SAPPHIRE?

The approved unit plan describes 1 block and 140 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is BCC SAPPHIRE?

About 182 units per acre: 140 planned units across 0.77 acres (3,121 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗