Registered28 Jul 2017
Promised31 Aug 2019
Completed11 Oct 2019

Timeline

Promised completion31 Aug 2019
Revised completion31 Aug 2019
Actual completion11 Oct 2019
Possession delay1 mo delay

Registration & Cost Details

Registration fee (in ₹)₹74,500
Project cost (in ₹ Lakhs)₹19,000 Lakhs
Project duration45 months
Project categoryResidential
Locality
Original start date22 Jan 2013
Proposed start date2 Jun 2017

Inventory

Total units862
Unit TypeUnitsCarpet Area (sqm)
2 BHK80254.65–68.64
3 BHK6071.22–71.47

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582006011
Emailail@ajnara.com
Coordinator9582006011
Helpline7835883228
Address1. B-189, YOJNA VIHAR, DELHI-92 2. B-189, YOJNA VIHAR, DELHI-92 3. B-189, YOJNA VIHAR, DELHI-92 4

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BO-07/23326/20172 Jun 20176 Dec 202131 Aug 20196 Dec 2026

Land Parcels

Khasra No.AreaPlot Type
GH-04, SEC-22A AT YAMUNA EXPRESSWAY85391Plot

Approved Unit Plan

Unit plan rows on file480
Total flats (sum of rows)862
BlocksTOWER A, TOWER B, TOWER C, TOWER G
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
233407 Dec 2011

Frequently Asked Questions

What is the RERA registration number of Ajnara Panorama (Phase-1: Twr A, B C & G)?

The RERA registration number of Ajnara Panorama (Phase-1: Twr A, B C & G) is UPRERAPRJ2605, as recorded on the UP-RERA portal.

What is the RERA status of Ajnara Panorama (Phase-1: Twr A, B C & G)?

As reported by UP-RERA, the status of Ajnara Panorama (Phase-1: Twr A, B C & G) is "NCLT".

Where is Ajnara Panorama (Phase-1: Twr A, B C & G) located?

As reported to UP-RERA, Ajnara Panorama (Phase-1: Twr A, B C & G) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Ajnara Panorama (Phase-1: Twr A, B C & G) completed?

As reported to UP-RERA, Ajnara Panorama (Phase-1: Twr A, B C & G) was completed on 11 Oct 2019.

Is Ajnara Panorama (Phase-1: Twr A, B C & G) delayed?

Measured against the latest completion date reported to UP-RERA, Ajnara Panorama (Phase-1: Twr A, B C & G) is 1 month beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026