Timeline Bar

Registered28 Jul 2017
Promised30 Sept 2020
NCLT25 Feb 2025

Timeline

Promised completion30 Sept 2020
Revised completion30 Sept 2020
Actual completion
Possession delay70 mo delay

Registration & Cost Details

Registration fee (in ₹)₹40,500
Project cost (in ₹ Lakhs)₹3,177 Lakhs
Project duration132 months
Project categoryResidential
Locality
Original start date26 Nov 2008
Proposed start date1 Apr 2010

Inventory

Total units117
Unit TypeUnitsCarpet Area (sqm)
2 BHK11759.57–75.76

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator6389022192
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
4115623 Feb 201722 Feb 202230 Sept 202022 Feb 2025

Land Parcels

Khasra No.AreaPlot Type
45, 46, 47, 66, 67, 687026.02 Sq. Meter
454840Khasra
462390Khasra
47110Khasra
6613720Khasra
6780Khasra
682780Khasra

Approved Unit Plan

Unit plan rows on file116
Total flats (sum of rows)117
BlocksC, D
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1474631 Jul 2013
94732 Nov 2004
85887 Oct 2004
126835 Jul 2012
831727 Sept 2004
512314 Jun 2006
1289 May 2007
57022 Nov 2012
1257 May 2007

Frequently Asked Questions

What is the RERA registration number of ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT?

The RERA registration number of ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT is UPRERAPRJ3382, as recorded on the UP-RERA portal.

What is the RERA status of ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT?

As reported by UP-RERA, the status of ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT is "NCLT".

Where is ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT located?

As reported to UP-RERA, ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

When will ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT be completed?

The latest completion date reported to UP-RERA for ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT is 30 Sept 2020.

Is ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT delayed?

Measured against the latest completion date reported to UP-RERA, ANSAL API-PARADISE CRYSTAL TOWER-C & D, GH-1, SECT is 70 months beyond that date.