ANSAL PROPERTIES & INFRASTRUCTURE LIMITED (RERA ID: UPRERAPRM6378) is a company registered with UP-RERA since 2017. It has 103 projects on record with Estanzo, of which 89 are on RERA's NCLT list, 9 are in abeyance with RERA and 21 are on RERA's Default-on-QPR list.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
103 on record · 1 as co-promoter
Showing 20 of 103 projects on record. See all 103 projects
Filings for more time
95 filings
| Extension filings | 95 |
| Projects with at least one | 92 of 100 |
| Longest single extension | 365 days - SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5D |
| Latest extension runs to | 27 Jun 2026 - ANSAL API-GH7(EWS/LIG)-PKT 3-SEC K-SGC LKO |
| Permits carrying a revalidation | 6 across 5 projects |
Directors & ownership
6 named by UPRERA
Promoter timeline
30 Nov 2010 - 28 Dec 2025
- Extension filednew completion date on file 27 Jun 2026as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
Show 279 earlier filings
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- Extension filednew completion date on file 30 Apr 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Oct 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 10 May 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 13 Apr 2024official source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- NCLT orderofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 12 Nov 2023official source ↗
- Extension filednew completion date on file 30 Sept 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 10 Jul 2023official source ↗
- Extension filednew completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 19 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 6 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 29 Mar 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Sept 2022official source ↗
- Extension filednew completion date on file 29 Mar 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 23 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 22 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 21 Dec 2021official source ↗
- Extension filednew completion date on file 30 Sept 2021official source ↗
- Extension filednew completion date on file 29 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 20 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 19 Mar 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 22 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 24 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 14 Oct 2019official source ↗
- Permit revalidatedvalid to 15 Apr 2023as recorded by UPRERA: PLG/(BP)1534/2433official source ↗
- Permit revalidatedvalid to 15 Apr 2023as recorded by UPRERA: PLG/(BP)1534/2433official source ↗
- Project registeredofficial source ↗
- Extension filednew completion date on file 5 Sept 2018official source ↗
- Extension filednew completion date on file 5 Sept 2018official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 24 Mar 2021as recorded by UPRERA: 35110official source ↗
- Permit revalidatedvalid to 23 Mar 2021as recorded by UPRERA: 35109official source ↗
- Permit revalidatedas recorded by UPRERA: MSR 38685/119477official source ↗
- Permit revalidatedas recorded by UPRERA: MSR 38685/119477official source ↗
Quarterly reports filed, by financial year
Statuses published without a date
Common questions about ANSAL PROPERTIES & INFRASTRUCTURE LIMITED
How many projects has ANSAL PROPERTIES & INFRASTRUCTURE LIMITED registered with RERA?
Estanzo holds 103 projects on record with UPRERA, filed by ANSAL PROPERTIES & INFRASTRUCTURE LIMITED (promoter RERA ID UPRERAPRM6378). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of ANSAL PROPERTIES & INFRASTRUCTURE LIMITED?
ANSAL PROPERTIES & INFRASTRUCTURE LIMITED disclosed 6 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was ANSAL PROPERTIES & INFRASTRUCTURE LIMITED registered with RERA?
ANSAL PROPERTIES & INFRASTRUCTURE LIMITED has been registered with UPRERA since 28 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗