Timeline Bar
Registered12 Aug 2017
Promised21 Sept 2020
NCLT25 Feb 2025
Timeline
Promised completion21 Sept 2020
Revised completion21 Sept 2020
Actual completion—
Possession delay70 mo delay
Registration & Cost Details
Registration fee (in ₹)₹3,12,500
Project cost (in ₹ Lakhs)₹2,776 Lakhs
Project duration66 months
Project categoryResidential
Locality—
Original start date22 Sept 2015
Proposed start date22 Sept 2015
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator6389022192
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 38830 | 22 Sept 2015 | 13 Mar 2017 | 21 Sept 2020 | 13 Mar 2020 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 734, 735, 738, 740, 741, 742, 743, 744, 745, 746, | 61486.88 Sq. Meter | — |
| 734 | 1010 | Khasra |
| 735 | 250 | Khasra |
| 738 | 630 | Khasra |
| 740 | 6440 | Khasra |
| 741 | 40 | Khasra |
| 742 | 20360 | Khasra |
| 743 | 4170 | Khasra |
| 744 | 6230 | Khasra |
| 745 | 3890 | Khasra |
| 746 | 2620 | Khasra |
| 747 | 3920 | Khasra |
| 748 | 12380 | Khasra |
| 750 | 6590 | Khasra |
| 751 | 8050 | Khasra |
| 752 | 2530 | Khasra |
| 753 | 2530 | Khasra |
| 754 | 6480 | Khasra |
| 755 | 9640 | Khasra |
| 794 | 2950 | Khasra |
| 796 | 7410 | Khasra |
| 797 | 3690 | Khasra |
| 798 | 4460 | Khasra |
| 799 | 1070 | Khasra |
| 800 | 1150 | Khasra |
| 800 | 1150 | Khasra |
| 801 | 1350 | Khasra |
| 803 | 10930 | Khasra |
| 804 | 5540 | Khasra |
| 805 | 7810 | Khasra |
| 817 | 380 | Khasra |
| 818 | 1200 | Khasra |
| 819 | 690 | Khasra |
| 820 | 2150 | Khasra |
| 827 | 3220 | Khasra |
| 828 | 4490 | Khasra |
| 829 | 830 | Khasra |
| 832 | 1390 | Khasra |
| 833 | 2150 | Khasra |
| 834 | 1860 | Khasra |
| 835 | 5310 | Khasra |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 1519 | 14 Feb 2008 | — | — |
| 2386 | 16 Mar 2009 | — | — |
| 2482 | 13 Mar 2007 | — | — |
| 3543 | 5 Apr 2007 | — | — |
| 3620 | 9 Apr 2007 | — | — |
| 3668 | 10 Apr 2007 | — | — |
| 3720 | 11 Apr 2007 | — | — |
| 4144 | 24 Apr 2007 | — | — |
| 4243 | 26 Apr 2007 | — | — |
| 5109 | 23 May 2007 | — | — |
| 5468 | 2 May 2011 | — | — |
| 7799 | 18 Aug 2007 | — | — |
| 8598 | 12 Sept 2007 | — | — |
| 14720 | 10 Nov 2010 | — | — |
| 23 | 3 Jan 2011 | — | — |
| 1355 | 8 Feb 2007 | — | — |
| 1821 | 22 Feb 2007 | — | — |
| 2008 | 26 Feb 2007 | — | — |
| 2827 | 21 Mar 2007 | — | — |
| 4464 | 5 May 2007 | — | — |
| 4883 | 17 May 2007 | — | — |
| 5110 | 23 May 2007 | — | — |
| 5500 | 4 Jun 2007 | — | — |
| 7652 | 14 Aug 2007 | — | — |
| 7797 | 18 Aug 2007 | — | — |
| 8892 | 30 Oct 2004 | — | — |
| 9006 | 1 Dec 2004 | — | — |
| 9240 | 10 Oct 2007 | — | — |
| 9412 | 16 Oct 2007 | — | — |
| 9602 | 23 Nov 2004 | — | — |
| 10298 | 15 Dec 2004 | — | — |
| 11006 | 28 Nov 2006 | — | — |
| 11074 | 29 Nov 2006 | — | — |
| 11239 | 4 Dec 2006 | — | — |
| 11265 | 5 Dec 2006 | — | — |
| 11266 | 5 Dec 2006 | — | — |
| 11267 | 5 Dec 2006 | — | — |
| 11319 | 6 Dec 2006 | — | — |
| 11446 | 11 Dec 2006 | — | — |
| 11586 | 18 Dec 2007 | — | — |
| 11827 | 20 Dec 2006 | — | — |
| 11972 | 22 Dec 2006 | — | — |
| 11973 | 23 Dec 2006 | — | — |
| 11997 | 26 Dec 2006 | — | — |
| 12027 | 26 Dec 2006 | — | — |
| 12148 | 29 Dec 2006 | — | — |
| 125 | 7 May 2007 | — | — |
| 128 | 9 May 2007 | — | — |
| 116 | 17 Mar 2008 | — | — |
| 492 | 22 Oct 2013 | — | — |
Frequently Asked Questions
What is the RERA registration number of ANSAL API-POCKET 3-SECTOR D-SGC LKO?
The RERA registration number of ANSAL API-POCKET 3-SECTOR D-SGC LKO is UPRERAPRJ10101, as recorded on the UP-RERA portal.
What is the RERA status of ANSAL API-POCKET 3-SECTOR D-SGC LKO?
As reported by UP-RERA, the status of ANSAL API-POCKET 3-SECTOR D-SGC LKO is "NCLT".
Where is ANSAL API-POCKET 3-SECTOR D-SGC LKO located?
As reported to UP-RERA, ANSAL API-POCKET 3-SECTOR D-SGC LKO is located at Lucknow, Lucknow, Uttar Pradesh.
When will ANSAL API-POCKET 3-SECTOR D-SGC LKO be completed?
The latest completion date reported to UP-RERA for ANSAL API-POCKET 3-SECTOR D-SGC LKO is 21 Sept 2020.
Is ANSAL API-POCKET 3-SECTOR D-SGC LKO delayed?
Measured against the latest completion date reported to UP-RERA, ANSAL API-POCKET 3-SECTOR D-SGC LKO is 70 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026