ANSALS AANGAN EWS LUCKNOW PHASE-II

UPRERARegistered

ANSALS AANGAN EWS LUCKNOW PHASE-II is a RERA-registered residential project by Ansal Housing Limited in Lucknow (RERA ID UPRERAPRJ17715). Registered with a completion deadline of 30 Apr 2023. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ17715
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Nov 2018
Project duration54 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant address606, 6th Floor Indraprakash, 21 Barakhamba Road, New Delhi 110001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    613/BULKSALE/18

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered9 Oct 2018
Original completion31 Oct 2022
Revised completion30 Apr 2023
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹23,000
Sanctioning authorityLucknow Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
J B KARAMCHANDANI
License CA/78/4302
4485, SECTOR B POCKET 5/6 VASANT KUNJ NEW DELHI
Engineer
RAJAN ABROL
S/O SH. J P ABROL A-2/161, SAFDARJUNG ENCLAVE, NEW DELHI
Contractor
e CONSTRUCTIONS SOLUTIONS PVT.LTD
E CHAMBER KURSI ROAD TERI PULIA LUCKNOW
Sr.Development work declared to RERA
1Demarcation of Plots
completed.
2Boundary Wall
N.A.
3Road Work
Bitumen Road on Outer Periphery and Brick Kharanja
4Footpaths
N.A.
5Water Supply Including Drinking Water Facilities
HDPE/MDPE pipes.
6Sewer System
Under Ground Sewerage System with RCC hume pipe
7Drain
Open Drainage System.
8Parks
As per Sanction.
9Tree Planting
As per Sanction.
10Design For Electric Supply Including Street Lighting
Overhead/Under Ground electrical cabling to be done
11Community Buildings
N.A.
12Treatment and Disposal System of Sewage and Sullage water
N.A.
13Solid Waste Management And Disposal System
N.A.
14Water Conservation System
N.A.
15Energy Management System Including Use of Renewable Energy
N.A.
16Fire Protection And Fire Safety System
N.A.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A.
18Emergency Evacuation Services
N.A.
19Other Miscellaneous Work
N.A.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 31 Aug 2022.

Sanctioned by Lucknow Development Authority · 3,600 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
613/BULKSALE/181 Sept 201831 Aug 202231 Aug 202631 Oct 2022
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Apr 2023.

#Granted fromExtended uptoNote
131 Oct 202230 Apr 2023Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1203600Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 107/CA/PO-16
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Oct 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New29 Sept 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Oct 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New9 Oct 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New1 Oct 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New1 Oct 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New29 Sept 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New9 Oct 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New1 Oct 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New1 Oct 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Sept 2018 ↗

Quarterly progress reports

1 filed report

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

1 quarterly progress report is on file with UPRERA, for 2020-Q3.

QuarterConstructionCertificates
2020-Q3—Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAnsal Housing Limited
RolePromoter · current
RERA IDUPRERAPRM450
PANAAACA0377R
CIN / TANDELA12078D
Name of chairmanDeepak Ansal
Registered address606, 6th Floor Indraprakash, 21 Barakhamba Road, New Delhi 110001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ANSAL HOUSING AND CONSTRUCTION LIMITEDBankAXIS BANK LTDBranchSTATESMAN HOUSE NEW DELHIA/C no.IFSCUTB0000007
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ANSALS AANGAN EWS LUCKNOW PHASE-II

Is ANSALS AANGAN EWS LUCKNOW PHASE-II RERA registered?

Yes. ANSALS AANGAN EWS LUCKNOW PHASE-II is registered with UPRERA under registration number UPRERAPRJ17715, registered on 9 Oct 2018. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ANSALS AANGAN EWS LUCKNOW PHASE-II?

The completion date filed with UPRERA is 30 Apr 2023. No completion certificate is on record yet.

Who is the builder of ANSALS AANGAN EWS LUCKNOW PHASE-II?

Ansal Housing Limited is the promoter entity that filed ANSALS AANGAN EWS LUCKNOW PHASE-II with UPRERA (promoter RERA ID UPRERAPRM450). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does ANSALS AANGAN EWS LUCKNOW PHASE-II show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted ANSALS AANGAN EWS LUCKNOW PHASE-II more time to complete?

UPRERA's record carries 1 completion extension for ANSALS AANGAN EWS LUCKNOW PHASE-II, the latest running to 30 Apr 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does ANSALS AANGAN EWS LUCKNOW PHASE-II have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ANSALS AANGAN EWS LUCKNOW PHASE-II located?

ANSALS AANGAN EWS LUCKNOW PHASE-II is registered in Lucknow, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗